Cemindia Projects Ltd Q2 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/0x0npkjl14tf8i4x9rrg574r.pdf

Key Takeaways


Quarterly Performance & Headwinds

Basu: "So hopefully, from December onwards we'll be able to start the work. And as a local competition, so far, we are okay. I mean, we don't see much of problem. So let us keep finger crossed."

Project Progress & Execution Velocity

Basu: "Today, you can imagine a job of INR5,000 crores we are completing 2.5 years. In earlier days, a job of INR1,000 crores used to take 4 years' time."

Order Book & Pipeline


Adani Ownership & Strategic Implications


Margin & Growth Outlook

Basu: "We still maintain that 20%-25% growth is possible."

New Segments & Geographic Expansion

Basu: "We also can keep at it from the new segments like data center, green energy, renewable energy. There are many new types of structures that are going to come. Even for the high speed, there's also going to be track laying. So those things we are already talking to our various experts. Maybe someday we have to be there."

Guidance & Commitments

CommitmentSpecificsTimeline
Ganga Expressway completionWork substantially completedJune or July next year
Order inflow₹10,000 cr total orders secured this yearEnd of FY25
H2 order booking₹5,000–₹6,000 cr from ₹30,000 cr pipelineSecond half of FY25
Bid finalizationMost bids finalizedBy February or March
Bangladesh work restartMobilization underway, work to beginDecember onwards
Revenue growth~20% next year, tapering to ~15% rangeFY26 and beyond
EBITDA margin10% plusGoing forward

Key Metrics

MetricQ2 FY25
Total income₹1,991 cr, +24% YoY
Revenue~₹2,000 cr, ~25% YoY growth
EBITDA~₹204 cr, +18% YoY
Profit after tax₹72 cr, +34% YoY
H1 EBITDA₹442 cr, +27% YoY
H1 profit after tax₹172 cr, +63% YoY
Debt-to-equity ratio0.4x
Revenue growth guidance~20% for next year, tapering to ~15% thereafter
EBITDA margin guidance10%+
Order pipeline~₹30,000 cr, with ~₹12,000–13,000 cr bids submitted
Orders expected in FY25₹5,000–6,000 cr from pipeline, plus ₹1,600 cr order received in October
Mobilization advance~₹1,300 cr as of September
Ganga Expressway progress~50% completed
Chennai Metro progress40–41% completed
Overseas pipeline share~25% of ₹30,000 cr pipeline