Key Takeaways
- PAT margin hits 5%, a structural shift: Management frames this as a new normal for the construction business, up from a historical 2–3.5% range, with no material legacy provision drag left.
- Order book set to nearly double: The company targets ₹15,000–16,000 crores by year-end, with H2 inflows alone expected above ₹15,000 crores, and a ₹90,000 crores bid pipeline backing the ambition.
- Data centers are the new growth vertical: A ₹1,500 crores starting order book, a stated goal to reach 15% of the total book within two years, and a move into electromechanical work mark a deliberate diversification beyond civil construction.
- Revenue doubling in under three years is "reasonable": Management endorsed the analyst's math, anchored on the current order book and execution timelines, while keeping margin targets at 11% EBITDA and 4% PAT.
- What to watch next quarter: Whether the ₹2,000 crores "almost with us" order converts, the pace of data center electromechanical integration, and any margin lift as legacy jobs roll off.
Order Book & Inflow Trajectory
- H2 inflow surge expected: Management guided to a little more than ₹15,000 crores in H2 order inflows, which would nearly match the full-year target in six months.
- L1 pipeline is deep: Pune Metro (₹1,700 crores), Project Varsha for the Indian Navy (₹1,000 crores), and an undisclosed job of around ₹2,000 crores are all at L1 stage and close to conversion.
- Group share is material but bounded: Around 25–26% of the ₹90,000 crores bid pipeline comes from the promoter group, and roughly 50% of current order inflow plus L1 is group-linked.
- Bangladesh is on autopilot: The ₹600-odd crores remaining on the job is fully under control and within schedule, receivables of ₹100–130 crores are normal per contract terms, but management is not focusing on the geography for new work.
- Vizhinjam and Vadhvan anchor the marine story: A ₹400 crores breakwater order at Vizhinjam is in hand, with future extensions possible, while work has started on the first Vadhvan Port contract.
Basu: "Those who have started working in Marine division since '89, they are almost all are there today in our company. There are hardly any migration of people. So the knowledge which is there is there."
Data Center Vertical Launch
- A deliberate diversification play: The new vertical starts with a ₹1,500 crores order book and a Navi Mumbai project already in execution; management intends to capture the majority of the promoter group's civil data center work.
- Electromechanical is the margin wildcard: The company is building electromechanical capability in-house, recruiting people and engaging consultants, because that is where the bulk of data center revenue sits. Integration is expected within a few months.
- Go-to-market is phased: For the first year or so, the vertical will work exclusively with the promoter; external customer pursuit comes after that.
- Scale ambition is explicit: Management wants the data center vertical to reach at least 15% of the overall order book within a two-year horizon.
Basu: "So whatever data center civil work is there, majority portion we intend to do and that is the intention, I hope from the group company also provided everything going okay. But the interesting part is that we are getting involved in the electromechanical part also, which is the bulk of the revenues."
Margin Structure & Trajectory
- PAT margin reset is complete: At 5%, PAT margin has moved structurally above the 2–3.5% historical band, and legacy provisions from Delhi Metro and Bangalore Metro are largely behind the company.
- EBITDA already at target: This quarter printed 11% EBITDA, which is the stated target level; management sees no reason data center margins would be lower than standard civil construction margins.
- Operating leverage is the next lever: An analyst flagged that corporate overhead absorption over a higher top line could push EBITDA to 10–11% or beyond; management noted the company is already there.
- Segmental margin hierarchy: Underground metro and marine segments normally deliver better margins than other segments, though management declined to quantify the spread.
- Electromechanical margin question is unanswered: Asked whether data center electromechanical work carries better margins than civil, management said it is too early to know and deferred to execution evidence.
Basu: "You want to increase your revenue, you cannot be competitive. If you are competitive your revenue is restricted. And to what extent you will reduce the cost because you have to deliver the job. So you have to leave in this same line of boundaries and still expect to do better."
Project Execution & Legacy Clean-Up
- Major projects are winding down or done: Ganga Expressway is "almost completed," Udangudi is "all completed," Bangalore Metro tunneling is completed, and Colombo is almost completed.
- Chennai Metro was tough but is now under control: Geology made it a very challenging job; the TBM tunnel is almost completed and the situation is managed.
- LNG Petronet and Dahej progressing smoothly: Described as an amazing job at a very challenging place to work, with work going on very smoothly.
- Project Varsha delivered on time and quality: A tough job with a long history, now delivered as per the client's requirement in both timeline and quality.
- Abu Dhabi ADNOC is in mobilization: The job is just entering the mobilization phase.
- IKEA Noida started well: The building project has started very well and management hopes to complete within time.
Balance Sheet & Capital Deployment
- Capex remains modest: Full-year capex is expected at close to ₹250 crores to ₹30-odd crores, though this may change if new large equipment like TBMs is required.
- Working capital is stable: Net working capital days are close to 90, and management is not worried about funding requirements as revenue scales, with the team working on arranging what is needed.
- Mobilization advances carry limited interest burden: Total advances stand at around ₹900-odd crores, of which almost 20% is interest-bearing.
- Other income is predictable: The normalized quarterly run rate is ₹10–15 crores, with this quarter's figure reflecting exchange gains on an overseas operation and interest on fixed deposits, with no write-backs.
- Credit rating upgrade may help: Management acknowledged a rating upgrade could have a favorable impact on interest rates but noted many factors drive that cost, and the team is working to bring it down.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | Around 20% | FY26 full year |
| Order book | ₹15,000–16,000 crores, if not more | End of FY26 |
| H2 order inflows | A little bit more than ₹15,000 crores | H2 FY26 |
| Capex | Close to ₹250 crores to ₹30-odd crores | FY26 full year |
| Data center vertical scale | At least 15% of overall order book | Within 2 years |
| Data center go-to-market | Work with promoter only for ~1 year, then external customers | After ~1 year |
| Thermal opportunity from Adani Power | ₹2,000–2,500 crores maximum | This year |
| Revenue doubling | "Reasonable assumption" per management | In less than 3 years |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Total operating income | ₹2,175 cr, +9% YoY |
| EBITDA | ₹242 cr, +19% YoY |
| EBITDA margin | 11.1%, up from 10.3% in Q2 FY25 |
| PAT | ₹108 cr, +49% YoY |
| PAT margin | ~5% |
| PBT margin | 6.7% |
| H1 total operating income | ₹4,718 cr, +8% YoY |
| H1 EBITDA | ₹496 cr, +13% YoY |
| H1 EBITDA margin | 10.5%, up from 10.1% in H1 FY25 |
| H1 PAT | ₹245 cr, +42% YoY |
| Net debt-to-equity ratio | 0.25x |
| Revenue growth target for FY26 | ~20% |
| Order inflow in H1 | ₹6,189 cr |
| Order inflow post-September 2025 | ~₹1,000 cr |
| Total order inflow so far in FY26 | ~₹7,200 cr |
| L1 position | ~₹3,500 cr (including Pune Metro ₹1,700 cr, Project Varsha ~₹1,000 cr, and one undisclosed ~₹2,000 cr) |
| Total order book | ~₹9,700 cr |
| Order book target by FY26-end | ₹15,000–16,000 cr |
| Share of Adani Group in order book | 25–26% |
| Share of Adani Group in order inflow plus L1 | ~50% |
| Domestic revenue share | 90–93% |
| Net working capital days | ~90 days |
| Working capital limits utilization | 85–90% of ₹6,500 cr limits |
| Capex in Q2 | ₹50–58 cr |
| Capex guidance for FY26 | ₹250–300 cr, subject to new large equipment needs |
| Mobilization advances | ~₹900 cr, of which ~20% is interest-bearing |
| Retention money outstanding | ~₹600 cr |
| Bangladesh project receivables | ₹100–130 cr |
| Bangladesh order balance to execute | ~₹600 cr out of ₹1,400–1,500 cr |
| Data center order book | ₹1,500 cr |
| Data center civil component | 25–30% of project value |
| Data center execution timeline | ~2 years (16–17 months civil, 6–7 months commissioning) |
| Bid pipeline | ~₹90,000 cr |
| Currency gain in Q2 other income | ~₹15 cr |