Key Takeaways
- Execution velocity unlocked: Revenue hit INR 2,017 crores in Q3, with 9M turnover already exceeding the full prior year, as quarterly execution doubled from INR 700 crores to INR 2,000 crores.
- Margins broke out of the legacy drag: EBITDA margin reached 10.9% from 8.9% a year ago, with virtually all low-margin legacy orders now completed and newer, better-margin projects driving the mix.
- The order book is deeper than it looks: Work-in-hand appears flat at INR 20,000 crores only because execution velocity has tripled, consuming the backlog faster; 10 large projects give 80% project control.
- Competition is the margin ceiling: Underground metro has gone from 3 to 7-8 players in four years, and management expects margins on new domestic wins to compress, pushing the strategy toward international marine work to sustain double-digit margins.
- What to watch next quarter: Whether the INR 13,000 crore bid pipeline converts at the 20% success rate, any news on the two Middle East and one West Africa marine bids, and the credit rating upgrade outcome from ongoing agency discussions.
Execution & Project Delivery
- Revenue run-rate transformed: Quarterly execution has scaled from INR 700 crores to INR 2,000 crores, a structural shift that consumed work-in-hand faster and made the backlog appear flat despite healthy order intake.
- 10 projects, 80% control: Chennai Metro underground, Bangalore Metro (nearing completion), Sikkim tunnel, Ganga expressway, Udangudi marine job and others contribute over INR 15,000 crores of work-in-hand, allowing tight monitoring of the bulk of the portfolio.
- Marine milestones: A critical ship unloader ordered from a Chinese company reached site yesterday, nearly completing that job; the Seabird navy job is nearing completion; a new navy job at Project Varsha near Vizag port has started.
- Building & airport completions: Thal Sena Bhawan (army headquarters) took off well; Trichy airport completed and inaugurated by the PM a month back; Pune airport completed; Sikkim University ongoing.
- Road project timeline: Expected completion by end of this year or beginning of next year.
- Sri Lanka project timeline: Completion expected by mid-2025, around June-July.
- Manpower cost declining: Manpower cost as a percentage of revenue has fallen from ~11% to 9.5% and is expected to come down a little further, driven by revenue growth on a fixed manpower base and a shift toward sub-mechanism work that relies less on direct labor.
Basu: "If we monitor 10 projects very closely, 80% of the project control we can have."
Margins: The Ceiling & The Escape
- Legacy drag eliminated: Legacy low-margin orders that had weighed on profitability are now virtually zero, completed, allowing newer projects awarded in the last one to two years to drive the margin profile.
- Q4 margin outlook: Expected to stay in the same range as Q3, around 10%.
- The competition math: Underground metro has gone from 3 players four years ago to 7-8 today, and management expects 10-12 next year; more players means margins on new domestic wins will come down, a reality management calls "business."
- The international escape route: To sustain double-digit margins, the company is targeting marine jobs abroad where the competitive set is thinner: Japanese and Korean players do not bid for jobs below INR 5,000-6,000 crores, leaving a gap for mid-size work that Cemindia intends to fill.
- International margin premium: International business should fetch better margins than domestic, and management says this is the rationale for going outside; margins quoted are after considering risk factors, with help from the promoter where they have prior presence.
- Peer margin debate: Management pushed back on the idea that 14-15% EBITDA is achievable consistently, stating 10-11% is standard in the construction space and that remaining in one segment or geography will cause margins to decline.
- Cost advantage abroad: Material cost is the same for all players; Cemindia's edge comes from operation cost, specifically temporary work and supporting structures, where it can execute much cheaper than international competitors, plus engineering cost savings from in-house marine design capability.
Basu: "Now, underground metro also will be crowded soon. So, the competitions will be there. So whatever margin we have achieved last year, coming year margin would be less if you have to win the job. That is one factor. That is why we are planning to go elsewhere, like abroad marine job, so that we are able to maintain the margin."
Order Book & Bid Pipeline
- Order inflow year-to-date: INR 6,000 crores-plus secured this year, with a few more in the pipeline.
- Bid pipeline: Around INR 13,000 crores of jobs in the pipeline, spanning marine, water, industrial structure, and building segments; management applies a 20% success rate assumption.
- Lumpy by nature: Large orders of INR 2,000-3,000 crores arrive once every three months, so the order book may appear static between such wins; management cautioned against reading silence as inactivity.
- Selectivity in action: The company will be very choosy: marine jobs pursued aggressively, tunnel jobs only in southern India (less appetite for the Himalayan range), and focus going forward on airport, underground metro, marine and a few overseas jobs.
- International bids submitted: Offers submitted for two marine jobs in the Middle East and one in West Africa; also focusing on marine work around Chittagong port in Bangladesh, where elections are over and a long list of marine work is in the pipeline.
- Domestic port opportunities: Present at greenfield port expansions by JSW and JSPL.
- Aviation pipeline: Great opportunities with a list of around 20 airports; tenders expected after elections, one by one, once the code of conduct clears.
- Nicobar Islands container terminal: Work is progressing at the government level but will take time due to feasibility studies and the 1,000 km distance from the Andaman mainland; management flagged it as not going to be very easy.
- Eligibility milestone: The company historically used joint ventures with the promoter to qualify; now able to bid for most jobs independently, including underground, metro and airport projects.
Basu: "Sometimes the silence should all you see. The moment if you get an order of INR 2,000 crores, INR 3,000 crores at a time, suddenly you'll find the number has changed. It is not that every month we are getting at the equal rate."
Balance Sheet & Working Capital
- Net working capital improved: Days improved in Q3 compared to Q2, now around 80-85 days; endeavor is to maintain or improve from here.
- Net debt position: Net debt as of December stands at INR 400 crores-plus; Q4 expected to be around the same level, maybe 5% up or down.
- Debt manageable: Management stated debt is significantly within manageable levels, not over-leveraged, and in line with growth in operations.
- Interest cost composition: Includes bank debt interest at 10-10.5%, guarantee and LC charges, and interest on mobilization advances from customers; the mix impacts total interest outlay.
- Credit rating upgrade in play: The company is working with the credit rating agency and talking to them; management said it should hopefully have some good news once discussions conclude, but declined to comment on a specific timeline.
- Other income increase: Substantial increase driven by income on fixed deposits, tax refunds, and interest on tax refunds; nothing non-recurring.
- Arbitration awards: No inflow received during the quarter; some awards have been challenged in court, some may be resolved through the Vivad Se Vishwas scheme; positive developments from 3-4 projects.
- Balance sheet trajectory: Management expects the balance sheet to improve as the company comes out of bad jobs, with almost all bad jobs now behind them.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY24 revenue | INR 7,500 crores, reaffirmed | FY24 full year |
| Q4 FY24 revenue | Almost same as Q3 | Q4 FY24 |
| Q4 FY24 EBITDA margin | Around 10%, same range as Q3 | Q4 FY24 |
| Q4 FY24 net debt | Around same level as December, maybe 5% up or down | Q4 FY24 |
| FY25 revenue growth | 20-25% growth | FY25 |
| Medium-term revenue growth | 20% growth maintainable for coming two to three years on top line | 2-3 years |
| Capex | INR 200-250 crores this year; almost same range next year | FY24 and FY25 |
| Net working capital | Maintain at 80-85 days or improve | Ongoing |
| Road project completion | End of this year or beginning of next year | FY25 early |
| Sri Lanka project completion | Mid-2025, June-July | Mid-2025 |
| Current work-in-hand coverage | Will cater for next year or up to 2025-2026 middle | Through mid-2026 |
| Manpower cost | Going to come down a little further | Ongoing |
| Airport tenders | Expected to start flowing post elections | Post-general election |
Key Metrics
| Metric | Q3 FY24 |
|---|---|
| Total operating income | ₹2,017 cr, +52% YoY |
| EBITDA | ₹220 cr, +87% YoY |
| EBITDA margin | 10.9%, vs 8.9% a year ago |
| Profit after tax | ₹79 cr, +113% YoY |
| Total operating income (9M) | ₹5,460 cr, +58% YoY |
| EBITDA (9M) | ₹567 cr, +80% YoY |
| PAT (9M) | ₹185 cr, +112% YoY |
| FY24 revenue guidance | ₹7,500 cr, reaffirmed |
| FY25 revenue growth guidance | 20-25% |
| Orders secured in Q3 | ₹1,300 cr |
| FY24 expected order inflow | ~₹8,000 cr, depending on order maturity |
| FY25 order inflow guidance | ₹8,000 cr to ₹10,000 cr |
| Work in hand | ₹20,000 cr-plus |
| Bid pipeline | ₹13,000 cr-plus |
| Net debt to equity | 0.3x |
| Gross debt | ₹860 cr as of 31st December |
| Net debt | ₹400 cr-plus as of December |
| Net working capital days | 80-85 days, improved vs previous quarter |
| Depreciation charge | ₹56 cr for the quarter |
| Manpower cost as % of revenue | 9.5%, down from ~11% earlier |