Cemindia Projects Ltd Q3 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/wxio4nc0h24qkbt9vwauzw9p.pdf

Key Takeaways


Bangladesh: The Quarter's Missing Revenue

Basu: "Otherwise, our revenue top line would have been at least INR200 crores more, then we could have seen the similar type of growth of 23%, 24% quarter-to-quarter."

Order Book & Inflow

Basu: "It depends upon what stroke of luck because if we get an one single order of INR5,000 crores, the INR12,000 crores figure will be INR17,000 crores."

New Promoter: Opportunity & Mechanics

Basu: "So the new promoter, they have got a huge internal planning to invest a lot of money to have green energy, to have many, many other things. So data centers and roads and whatnot. So those require infrastructure, I mean, those require a lot of construction and energy activity. So the huge opportunities are lying in front of us to do a lot of work with our Adani Group."

Margins & Costs

Basu: "Basically, the construction industry margin is around that 9%, 10%, 11%. Some of the company, those who go for different model, BOT and annuity, etcetera, there is difference. But we are purely EPC infrastructure company. So I don't see there will be much change unless we do something exceptional in a particular job."

Execution & Capability


Guidance & Commitments

CommitmentSpecificsTimeline
FY25 order inflow~₹9,000 croresBy FY25 close
FY26 order inflow₹10,000–₹13,000 crores (higher if a large single order lands)FY26
Revenue growth20–25% for 2–3 years, holds even excluding Bangladesh2–3 year horizon
EBITDA marginAround 10%, stableOngoing
Bangladesh project normalizationNo further effects expectedFY26
Open offer completionSEBI + lender consents remainBy March (~1–2 months)
New segment entry (green hydrogen, data centers)Requires new team; in-house, not JV/M&AMaybe 7–8 months after new promoter arrives
International marine orderAt least one expected very soonNear term

Key Metrics

MetricQ3 FY25
Revenue₹2,240–₹2,250 cr, impacted by Bangladesh project; at least ₹200 cr less than expected
Revenue growth (QoQ, ex-Bangladesh)23%–24%, growth that would have been achieved without Bangladesh impact
EBITDA margin~9.5%, versus over 10% historically maintained
EBITDA margin guidanceDouble-digit, expected for full year
Work secured (YTD)~₹6,600 cr, with full-year inflow guidance of ~₹9,000 cr
Order inflow guidance (FY25)~₹9,000 cr, confident of achieving; 2/3 met so far
Order inflow guidance (FY26)~₹12,000–₹13,000 cr, including new promoter opportunities
Work in hand₹20,000 cr, composition: government 50%, private 42%, PSU 8%
Revenue guidance (FY25)Close to ₹10,000 cr
Revenue growth guidance (medium-term)20%–25%, for 2–3 years, holds ex-Bangladesh
Bangladesh order book~₹1,500 cr, to be completed in 30 months
Bangladesh revenue impact (9M FY25)₹500 cr budgeted, ~₹150 cr executed; Q3 budgeted ₹300 cr, executed ₹97 cr
Bid pipeline~₹31,000 cr total; ~₹15,000 cr submitted, ~₹15,000 cr yet to be submitted
L1 position~₹800 cr, metro work in Bengaluru
Overseas bid pipeline~₹2,500 cr, out of ₹15,000 cr submitted
International order book share~10% of total order book
Capex (9M FY25)~₹100 cr, with another ₹15–₹20 cr expected; full-year max ₹120–₹125 cr
Net working capitalUnder 100 days, in line with or better than industry
Execution capabilityUp to ₹13,000–₹14,000 cr annually with current setup