Key Takeaways
- Revenue held back by one stalled project: Growth was ~5.6% instead of 18-20% because the large Vadhvan Port job made almost no progress due to local issues, costing an estimated ₹200-300 crores in the quarter.
- Profitability structurally improved: PAT margin reached ~5% (vs 3.9% last year) and EBITDA held at ~11%, sustaining a double-digit run-rate even with the Vadhvan revenue gap.
- Order book primed for a step-change: ₹11,700 crores of inflows secured this year, with an L1 project of ~₹6,500 crores awaiting conversion and several ₹5,000-10,000 crore mega-tenders in the pipeline.
- Data center construction is now live: Foundation work is complete and precasting is half done on the first two Mumbai buildings, positioning the company for a new, multi-year vertical.
- What to watch next quarter: Whether the promised 15-20% QoQ revenue jump materializes, conversion of the Adani Mor Sagar L1 into the order book, and any closure of the big-ticket government tenders.
The Vadhvan Port Drag
- One project, one problem: The Vadhvan Port job, secured early last year, contributed almost no revenue this quarter because local problems stalled progress; management cannot predict when it will resolve.
- Revenue gap quantified: The stalled project cost the company an estimated ₹200-300 crores in revenue this quarter, which explains the gap between reported ~5.6% growth and the 18-20% that would have been reported otherwise.
- Costs did not follow the revenue loss: Only 2-3 engineers are deployed at the site with no material spend, so the missing revenue did not carry corresponding expenses and did not drag margins.
- No recovery timeline: Management stated the situation is "totally not in company's control" and declined to speculate on when work might resume.
Basu: "Otherwise, we would have been very happy to report around 18% to 20% revenue more than last quarter of last year."
Order Book & Pipeline
- Inflows recovering after a lean patch: ₹11,700 crores of orders secured this year, a sharp recovery from last year's subdued ₹2,000 crores up to Q2 and ₹874 crores in Q4; another ₹2,000-3,000 crores expected in February and March.
- The L1 that changes the math: The Adani Mor Sagar project in Rajasthan, a group company job worth ~₹6,500 crores, is at L1 stage and will be added to the order book very soon.
- Mega-tenders in sight: Several government tenders in the ₹5,000-10,000 crore range each are expected in Q4 or Q1/Q2 next year; management says winning even one or two would "change the whole scenario."
- Bid pipeline depth: ~₹25,000 crores of bids already submitted, with ₹10,000-12,000 crores of immediate order inflow possible depending on outcomes.
- Group company anchor: Group share of order inflow runs at 20-25%, with data center construction and possible road jobs providing a visible pipeline.
Basu: "There are a few jobs in that range. If we are lucky, if we get one or two jobs in that big-ticket jobs, the whole scenario will change."
Data Center: The New Vertical
- Construction underway: Two data center buildings in Mumbai have foundation work completed and precasting work half done; the company is in readiness mode for what management frames as a large, multi-year opportunity.
- Capacity and revenue cycle: Present capacity can handle roughly 500 megawatts per year; a 120-130 megawatt data center has a 2-year to 27-month construction cycle, with ~20% of revenue recognized in year one and ~80% in year two.
- Group ambition as demand driver: Adani has a big plan for data centers; management noted that even if the group executes half of that plan, the opportunity will be quite big for Cemindia.
- Per-megawatt economics undisclosed: Management declined to give a per-megawatt revenue figure, citing variability in conditions, terms, bidding and supplied items.
Basu: "We have already started 2 data center building in Mumbai and foundation work is already completed. Precasting work also half done. So we are in readiness to take up this activity."
Revenue Trajectory & Ramp-Up
- Q4 jump expected: Management guided for Q4 revenue to be at least 15-20% higher than Q3, driven by projects now exiting their initial slow phase.
- FY27 acceleration: Revenue growth of ~18% is expected next year as Pune Metro, Abu Dhabi Port and data center projects enter full swing, and the ₹11,000+ crores of orders secured this year begin converting at higher monthly run-rates.
- The ramp-up mechanics: New projects typically see lower progress in the first 5-6 months, then per-month turnover increases; this timing cycle means orders won this year will contribute meaningfully from Q1 and Q2 next year.
- 30% headroom in existing resources: Management stated the company has capacity to ramp up progress by 30% with current resources, implying operating leverage as revenue scales.
- Bangladesh on track: Work is proceeding normally with local government support and timely payments; the piling job will be almost complete by end of May, with physical work finished before next monsoon.
Margins & Profitability
- Structural step-up holding: EBITDA margin sustained at ~11% for several quarters now, up from a historical 9-9.5% band; PAT margin reached ~5% versus 3.9% last year.
- Vadhvan did not flatter margins: The revenue loss from Vadhvan Port did not carry corresponding expenses because only minimal site setup exists, so the margin improvement reflects genuine operational efficiency on active projects.
- Steady-state expectation: Management expects the same 10-11% EBITDA margin pattern to persist and does not anticipate a further hike.
- Capex modest: FY26 capex is ~₹300 crores, about 10-15% more than last year.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Q4 FY26 revenue | At least 15-20% more than Q3 | Q4 FY26 |
| FY26 revenue growth | 16% to 20% | FY26 |
| FY27 revenue growth | ~18% | FY27 |
| EBITDA margin | 10% to 11% maintained | Ongoing |
| FY26 order inflow | ~₹14,000-15,000 crores total | FY26 |
| Immediate order inflow | ₹10,000-12,000 crores may come immediately | Near term |
| Bangladesh order completion | Physical work complete before next monsoon | May/June next year |
| FY26 capex | ~₹300 crores (10-15% more than last year) | FY26 |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Total operating income | ₹2,315 cr, vs ₹2,270 cr in Q3 FY25 |
| EBITDA | ₹245 cr, +13% YoY |
| EBITDA margin | 10.6% |
| PAT | ₹111 cr, +27% YoY |
| PAT margin | ~5%, vs 3.9% in same period last year |
| 9M operating income | ₹7,087 cr, +6% YoY |
| 9M EBITDA | ₹749 cr, +12% YoY |
| 9M PAT | ₹356 cr, +37% YoY |
| Net debt to equity | 0.26x |
| Gross debt | ~₹920 cr as of December |
| Order inflow YTD | ₹11,700 cr (including ₹2,000 cr secured post December) |
| Order book | ₹21,800 cr |
| Group share of order book | 27% |
| FY26 revenue growth guidance | 15% to 20% |
| FY27 revenue growth guidance | ~18% |
| Q4 FY26 revenue expectation | 15% to 20% more than Q3 |
| EBITDA margin guidance | 10% to 11% going forward |
| FY26 order inflow target | ₹14,000 cr to ₹15,000 cr |
| Tenders submitted, yet to open | ~₹20,000 cr, with further ₹30,000 cr to ₹40,000 cr pipeline |
| Capex spent in 9M | ~₹200 cr |
| FY26 capex guidance | ~₹300 cr, 10% to 15% more than last year |
| Bangladesh receivables | ₹170 cr as of December |
| Vadhavan Port order value | ₹1,600 cr, less than 10% of order book |
| Revenue impact from Vadhavan Port delay | ₹200 cr to ₹300 cr would have been added had work proceeded |
| Data center annual capacity | ~500 MW with present resources |