Cemindia Projects Ltd Q4 FY2022 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/6m3hbod8vmf91tmj55770zaw.pdf

Key Takeaways


The Margin Story: Legacy Jobs vs. Steel Reality

Prasad Patwardhan: "It is a combination of two-three things... the extension of timeline because of COVID and the commodity prices as well both the things have impacted the margins on that project. But the good thing is we have claims and we are going to pursue these claims and the money will get recovered, but in the Indian context the timeline for recoveries will be quite long."

Order Book & Pipeline: The Growth Engine

Jayanta Basu: "Opportunities are very large at the same time the risk is also very large, I mean doing tunnel in Himalayan Range you can see in paper everyday there are something happening. So, when you have good work in hand why to go there to that extent."

Project Progress: Metro & Marine Milestones

ProjectStatusCommentary
Mumbai Metro~90% completeExpected completion by end of year; cash balances exist but full margins are being withheld due to possibility of incidents; some release expected in current financial year or may slip a little into the next.
Kolkata Metro97% completeExpected completion in a few months; residual cash of ~₹200 Crores lying in bank; no further problems seen, should be profit.
Bengaluru Metro elevated85–86% done (last job)Three of four jobs almost handed over; expected to exit elevated job by end of year.
Bengaluru Metro underground~22% progressStarted a year back, tunnel in full swing.
Chennai Metro UG1 & UG2Mobilization stageManpower and temporary installations almost done; special equipment (trench cutter) ordered, some arriving by end of month; tunneling work to start around May or June next year after ~1 year of enabling work.
Udangudi~60% progressReached end point 8 km from shore.
Seabird jobs (Indian Navy)On trackGoing well except one at Chhara which was suspended due to client issue.

Balance Sheet & Working Capital


Margin Recovery Path

Jayanta Basu: "Margin is a function of various things, I can only tell you that towards the end of this year we will be in a very good position and we will be able to tell you exactly that what will be our margin, which should be very close to 10%."

Guidance & Commitments

CommitmentSpecificsTimeline
Topline growth25% more than FY22FY23
Topline growth20–25% growth momentum expectedFY24
Operating marginBetter than FY22; hope to touch or be very close to double-digit if steel prices continue coolingFY23
Operating marginNormalized double-digit margins expectedFY24
Bengaluru Metro elevated exitComplete and exit the last elevated jobBy end of calendar year 2022
Kolkata Metro TBM removalComplete removal of stuck TBMBy June end 2022
Chennai Metro tunneling startTunneling work to beginAround May or June 2023
Bengaluru Metro provisionsNo further provisions expected; all losses already considered in March financialsOngoing
Capex~₹300 Crores total, mostly for Chennai MetroFY23
CapexNot much requirement foreseenFY24

Key Metrics

MetricQ4 FY22
Revenue₹1,175 cr, record quarterly revenue, +40% YoY for full year at ₹3,810 cr
EBITDA margin~7%, down from ~8% in Q3 FY22; Bengaluru Metro provision of ₹30 cr impacted margins
Provision for Bengaluru Metro loss₹30 cr, booked in Q4; all envisaged losses now accounted for
Gross debt₹515 cr, consolidated as of March 2022
Net debt₹123 cr
Debt utilization ratio0.2x as of March 2022
Order backlog₹15,500 cr, all-time high as of March 2022
New orders booked in FY22₹7,700 cr
New orders secured in April 2022₹450 cr
FY23 revenue growth guidance25% over FY22
FY24 revenue growth guidance20–25%
Contracts with escalation clauses~90% of order book
Mumbai Metro progress~90% completed
Kolkata Metro progress97% completed
Bengaluru Metro underground progress~22% completed
Udangudi project progress~60% completed
Bengaluru Metro elevated last job progress85–86% completed
Order book execution timeline3 to 3.5 years on average
FY23 expected capex~₹300 cr, largely for Chennai Metro TBM and trench cutter
Mobilization advances expected in FY23₹250–300 cr from recently added projects
Marine order pipeline₹6,000 cr (JNPT, Colombo, Bangladesh) under active pursuit
Total order pipeline near conclusion₹15,000 cr
Margin range on new bids8–15%, varying by segment and job size
Marine segment margins10–11% for large jobs, ~15% for small jobs
Ahmedabad airport contract value~₹500 cr for T1 and T2 terminals
JNPT Jetty work target value~₹1,000 cr
Kolkata Metro cash held~₹200 cr in bank