Key Takeaways
- All-time high standalone revenue and PBT: PBT margins improved ~90 bps sequentially and 230 bps YoY, with PAT up 38% YoY on positive operating leverage.
- Power Systems the star, Industrial Systems the drag: Power sales surged 48% YoY with 310 bps margin expansion, while Industrial sales slipped 2% on railway project deferments and price realization challenges.
- Semiconductor foundations laid, costs still a headwind: The G1 factory opened and the G2 main plant targets a late-2026/early-2027 close, but the segment is only at breakeven and management declined to provide a multi-year scaling roadmap.
- Capacity expansion bets big on demand durability: Transformer capacity jumped from 15,000 MVA to 40,000 MVA, a new switchgear greenfield was approved at ₹748 crores, and exports are set to rise from ~10% to ~20% of current capacity.
- What to watch next quarter: Whether the ~1.5-month KAVACH shipment delay clears by December, the pace of railway order normalization, and any concrete updates on the EV motor and Axiro scale-up plans that management asked investors to be "patient" on.
Power Systems: The Growth Engine
- Transformer demand unrelenting: Sales up 48% YoY with 310 bps margin expansion, driven by better price realization, resilient demand trends, and improved operating leverage. The inquiry pipeline is ~85% higher than last year.
- Capacity expansion executed ahead of plan: The move from 15,000 MVA to 40,000 MVA was completed on 1st October, with Power Grid Corporation approval received up to 35,000 MVA. The next phase to push further is due next month. Most of the new capacity is already absorbed by the order backlog, with customers placing orders up to 24 months out.
- Market share gains rooted in speed: Management attributes share gains to execution excellence under its CGEDGE program, compressing cycle times and moving at double the speed of competitors.
- Execution delays are logistical, not demand-driven: Developers are taking delivery of transformers even when projects are delayed, storing them near sites due to supply constraints. Heavy rains caused some slippage this year, but government focus on right-of-way and land acquisition is expected to resolve structural bottlenecks over the long run.
- Switchgear rides the same wave: Demand remains consistently higher, tracking transformer trends, with no shift toward lower demand for EHV, EHVS or Medium Voltage business. A ₹748 crore greenfield expansion for switchgear (medium voltage and EHV circuit breakers, instrument transformers, GIS) was approved, targeting domestic and export markets with a planned capacity of 45,000 MVA.
- Product portfolio broadening into adjacencies: New developments include 765 kV bushings (OIP and RAP, a homegrown solution), a move from SF6 to SF6-free solutions at Nashik and Aurangabad factories, and a complete Make in India 400 kV GIS solution expected next fiscal year. STATCOMs are under consideration via both organic and inorganic routes.
Kaul: "It's a combination of many things. But what is important is our execution excellence, which is CGEDGE, as you can look at our website. I think that's what we are practicing every day, keep compressing the cycle time, go faster, double the speed of what anybody else can do."
Industrial Systems: Railway Headwinds
- Railway deferments drove the decline: Sales fell 2% YoY primarily because railway project shipments were deferred from around 15th September onwards for more than a month. Some of the deferred orders were covered, with the balance shifting into the current quarter.
- Price realization under structural pressure: The railway business faces thin margins by the nature of its tendering process, and the PVC clause (an average of three different formulas) takes 1-2 quarters to adjust, meaning commodity inflation is not fully passed on in real time. Pricing discipline, cost optimization, and operational productivity gains partly cushioned the impact.
- KAVACH orders booked, shipments pending: Additional orders of ~₹150 crores were received for Station KAVACH, but execution faces a delay of about 1-1.5 months. Two final approvals are pending and expected to clear by end of December, at which point shipments can begin.
- Motor business showing early recovery: Order input grew in double digits and sales in single digits (on the positive side), with profitability improving. The broader market, per IEEMA data, has moved from negative to flat. HT motor inquiry pipelines are positive, though LT remains far larger at roughly an 80-20 split. Management expressed comfort with a bounce-back, calling it "good days ahead."
- EV motor progress still stalled: Progress remains slow, with management asking for "a couple of days more" before providing an update, describing the outlook as "exciting days ahead" but offering no concrete timeline.
Exports: The Next Leg
- Early traction visible: H1 exports were up ~20-25% in absolute terms versus H1 last year, showing initial results from the strategy.
- Capacity unlocks export ambition: With transformer capacity now at 40,000 MVA, management plans to push exports more aggressively for business sustainability, participating in more projects and tying up with state utilities abroad. Exports are expected to grow from ~10% to ~20% of current capacity revenues, with the new switchgear plant planned at a ~35-40% export mix.
- Geographic and channel expansion underway: The company is gradually expanding in Southeast Asia, Europe, Africa (Morocco), and the US, while simultaneously upgrading manufacturing capabilities to meet global standards. The Flanders partnership provides repair, remanufacturing, and warehousing services in North America for the motor business, described as a joint, win-win arrangement.
Kaul: "It's like a foot on the gas and foot on the brake thing. So, on one side, as I have been talking about in the last few quarters, we are upgrading our manufacturing capabilities to make sure the standards are at par with the global standards. And on the other side, we are expanding in different markets..."
Semiconductors: Building the Platform
- G1 factory opened, G2 on the way: CG Semi Private Limited opened its first factory (G1) near Ahmedabad, marking the initial step into semiconductor capability with a peak capacity of 0.05 crore units per day. The main plant (G2), 3 km away and under construction, is expected to close by end of next year or early 2027, with capacity of ~1.45 crore chips per day. Combined capacity will be ~1.5 crore chips per day, generating ~5,000 direct and indirect jobs.
- Fiscal support agreement locked: The agreement was signed on January 17, 2025, and the Trust and Retention Account Agreement was signed on September 15, 2025.
- Axiro Semicon at breakeven, scaling ambitions clear: Revenue is running at ~$50 million versus ~$55-56 million in the prior year, with the team doing a "fantastic job" given acquisition integration and infrastructure setup. The business is at breakeven. Management emphasized much larger plans, including more acquisitions, complementing technologies, hiring more technical people, and expanding beyond Radio Frequency into other technologies.
- Cost trajectory undisclosed: The consolidated margin improvement was partially offset by strategic investment in talent for CG Semi and Axiro. When asked for a multi-year revenue scaling and cost roadmap, management provided only current-year Axiro guidance and declined to quantify when semiconductor costs would stop weighing on overall EBITDA.
Kaul: "We didn't just buy this company to stay at that level. So, we have much larger plans, and that's what keeps us awake at night in terms of strategy, where do we go from here, more and more acquisition, complementing, hiring more people, more tech people to make sure it goes in the long way."
Margins & Capital Allocation
- Consolidated margin walk: PBT margins improved ~90 bps sequentially and 230 bps YoY, driven by strong power performance and positive operating leverage. This was partially offset by strategic investment in senior personnel and technology talent in CG Semi and Axiro, with other intangible assets rising from ₹263 crores to ₹427 crores due to the Axiro acquisition.
- Industrial segment margin muted: PBIT came in at 9.7% of sales, pressured by railway price realization challenges, order deferment leading to lower operating leverage, and commodity price increases not fully passed on. A 5% price increase implemented in July was well received and compensated for copper and steel prices, with many competitors also raising prices.
- Capital allocation dual-track: Internal capacity expansion of ₹750 crores was approved for the switchgear greenfield. In parallel, the strategy team is actively looking at M&A candidates across both CG and semiconductor businesses, though no specific targets, timelines, or deal sizes were disclosed.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Transformer capacity next phase | Further increase beyond 40,000 MVA | Next month |
| KAVACH shipment start | ~₹150 crores of orders; 2 final approvals pending | Expected clearance by end of December |
| CG Semi G2 plant close | Main plant with ~1.45 crore chips/day capacity | End of next year or early 2027 |
| Axiro Semicon revenue | Approximately $50 million (~₹450 crores) | Current fiscal year |
| 400 kV GIS Make in India solution | Complete solution launch | Next fiscal year |
| New switchgear plant (45,000 MVA) | Greenfield expansion; planning ~35-40% export mix | Target '27-'28, management expects to be ahead |
| Exports mix from current capacity | Grow from ~10% to ~20% of revenues | Coming years |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Standalone revenue | ₹2,649 cr, 17% YoY growth |
| Standalone PAT | ₹307 cr, 38% YoY growth (vs ₹223 cr in Q2 FY25) |
| Standalone PBT margin improvement | ~90 bps sequentially and 230 bps YoY |
| Consolidated revenue | ₹2,923 cr, 21% YoY growth |
| Consolidated PAT | ₹284 cr, 30% YoY growth (vs ₹220 cr in Q2 FY25) |
| Standalone order intake | ₹4,210 cr, 32% YoY growth |
| Consolidated order intake | ₹4,772 cr, 45% YoY growth |
| Standalone unexecuted order backlog | ₹13,568 cr as of 30 Sep 2025 |
| Consolidated unexecuted order backlog | ₹14,953 cr, 88% YoY growth |
| Standalone ROCE (excl. QIP proceeds) | 34% |
| Consolidated ROCE (excl. QIP proceeds) | 31% |
| Industrial segment revenue | ₹1,395 cr, -2% YoY |
| Industrial segment PBIT margin | 9.7% of sales (₹135 cr vs ₹166 cr in Q2 FY25) |
| Power Systems segment revenue | ₹1,254 cr, 48% YoY growth |
| Power Systems segment PBIT margin expansion | 310 bps YoY (₹260 cr vs ₹149 cr in Q2 FY25) |
| Power Systems order intake | ₹2,643 cr, 81% YoY growth |
| Power Systems unexecuted backlog | ₹10,474 cr, 104% YoY growth |
| Inquiry pipeline growth | ~85% up from last year |
| Exports growth (H1 absolute) | 20% to 25% up vs H1 FY25 |
| Transformer capacity | 40,000 MVA as of 1 Oct 2025, expanded from 15,000 MVA |
| Switchgear capacity utilization | 85% to 88% |
| Axiro expected revenue (FY26) | ~$50 million (~₹450 cr) |
| CG Semi and Axiro combined EBIT loss | ~₹22 cr EBIT loss; Axiro at breakeven |
| Board-approved switchgear greenfield expansion | ₹748 cr, net of taxes |