Key Takeaways
- Record quarter, broad-based strength: Standalone revenue grew 32% YoY and PBT surged 47% YoY, with 180 bps of margin expansion led by power systems and a motors turnaround.
- Power systems margins hit 25%: A 430 bps YoY improvement driven by price realization and operating leverage; management is "hopeful" to maintain or exceed this level.
- Order book at ₹23,646 crores consolidated: Multi-quarter visibility is locked in, and power systems order intake jumped 137% YoY across utilities, AI/data centers, and exports with no single-material skew.
- Capacity build-out is accelerating: The Sehore mega-plant shipped its first transformer, and the board approved ~₹383 crores in new capex across bushings, breakers, GIS, and power transformers.
- What to watch next quarter: Whether Kavach final approval arrives and production begins, the pace of motors' sequential margin improvement, and any update on the G2 semiconductor qualification timeline.
Power Systems: The Margin Engine
- Record profitability: PBIT margin reached 25% of sales, up 430 bps YoY, on strong price realization and better operating leverage amid resilient demand.
- Efficiency, not just pricing: Management attributes the gains to week-over-week, year-over-year efficiency work, not just the cycle; intention is to maintain or go above current margins.
- Order intake broad-based: Q2 power systems orders of ₹6,258 crores (137% YoY) came from utilities, AI, data centers, domestic and exports with no single-material order requiring disclosure.
- Sehore facility live: India's largest transformer plant (220 kV to 1,200 kV class) rolled out its first unit on 4 Sep, built within 13 months; peak capacity of 35 power transformers per month, roughly 70,000 MVA.
- Capacity additions stacking up: T3 facility adding 10,000 MVA (total 75,000 MVA) via ₹68 crores capex; a new transformer plant expected to start in about a quarter adding 10,000 MVA+; eventual power transformer capacity target ~120,000 MVA "and still counting."
- GIS Vilholi scaling: Annual capacity rising from 228 equivalent bays to 468 as it matures; ~90% of project assets expected to transfer to the greenfield facility when commissioned.
Kaul: "I think important is, how are we becoming efficient day-by-day, week-over-week, year-over-year? That's exactly where we spend a lot of our energy on. So, I'm pretty hopeful that either maintain or go above these margins."
Motors & Industrial: The Turnaround Story
- Motors margin drivers: The improvement is "coming purely from the work done by our teams in motors" under CG EDGE (portfolio optimization, waste elimination), not from price; price increases of 30%+ over the last 12 months only nullified commodity inflation.
- Sequential consistency: Industrial segment PBIT margin improved 60 bps sequentially, and motors has already reached double-digit margins; management stated they are improving consistently on at least 50–60 bps every quarter.
- Product portfolio upgrade underway: First IE3/IE4280 frame launched on 3 August; additional frames launching every 45 days; full portfolio upgrade over the next 9–12 months; also working on permanent magnet motors and IE5+ motors to open export markets.
- No further price hikes expected: With commodity inflation nullified, management sees no immediate need for additional increases.
Kaul: "Price increase is directly only nullifying the commodity inflation. But the improvement that you see is coming purely from the work done by our teams in motors."
Railways: A Deliberate Pause
- Margin over top-line: Railways business is either flat or may decline; management is consciously choosing not to pursue revenue at the expense of the bottom line while it builds technology capabilities and market readiness.
- Kavach catalyst: Final certification expected "definitely in the current quarter"; production including installation and commissioning should commence this quarter.
- Order lapse risk contained: If approvals are delayed, some orders may lapse by end of next quarter, but they would be retendered and "won't be lost."
- Capability-building year: No huge improvements expected for a year or so as time is used for technology upgradation and strategy work.
Kaul: "We could still be making the top-line meet, but then we don't want it at the expense of bottom-line. So, we'll see. As we are progressing, our strategy work is happening on the railways side as well. So, we might take a bit of a step back on that instead of just worrying about the top-line and bleeding bottom-line."
Semiconductor: Investment Phase Continues
- Consolidated margin drag: Continued talent investments in CG Semi and Axiro semiconductor business impacted consolidated margins by ~₹35 crores (91 bps).
- Axiro at breakeven: Q2 revenue came only from Axiro, which reached breakeven in the quarter.
- Axiro acquires TOSIL: Completed acquisition of 100% equity in TOSIL Systems for ₹16.4 crores on 20 Aug, adding semiconductor and embedded engineering services including silicon design, verification, and Edge AI.
- G2 facility timeline: Construction progressing well; qualification to commence middle of next year; commercial production expected toward end of '28 or '29 (qualification takes 2–3 quarters).
Capex & Capacity: Building for the Cycle
- Core business capex: FY27 total expected ~₹1,000 crores; FY28 expected ~₹700–800 crores (excluding OSAT).
- Board-approved projects this quarter:
- S1 unit, Ambad Nashik: ₹300 crores to increase OIP bushings and instrument transformers capacity up to 800 kV; production tentatively within 30–36 months.
- S3 Unit2 Phase2: Additional ₹15.31 crores to enhance EHV circuit breaker capacity by 3,600 units annually; completion within 6–9 months.
- GIS Vilholi: Enhancement from ₹35.14 crores to ₹44.62 crores for 800 kV high-voltage testing system.
- T3 capacity: ₹68 crores net of taxes to enhance power transformer capacity by 10,000 MVA within existing facility; completion within 12–15 months.
- Revenue growth aspiration: Management aspires to keep high double-digit growth; new capacity investments are linked to business plans for next year and the year after.
- Power electronics ambition: Working on power electronics to get deeper into holistic solutions beyond switchgear and transformers over the next few quarters and years; could be organic or inorganic.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Kavach certification and production | Final approval expected; production including installation and commissioning to commence | "Definitely in the current quarter" |
| S1 unit production start | OIP bushings and instrument transformers up to 800 kV | Tentatively within 30–36 months |
| S3 Unit2 Phase2 capacity addition | 3,600 additional EHV circuit breaker units annually | Within 6–9 months |
| T3 capacity enhancement | 10,000 MVA additional power transformer capacity (total 75,000 MVA) | Within 12–15 months |
| G2 semiconductor qualification start | Qualification to commence | Middle of next year |
| G2 semiconductor commercial production | Commercial production start | Toward end of '28 or '29 |
| Motor portfolio upgrade | Full IE3/IE4 portfolio upgrade | Next 9–12 months |
| Core business capex | FY27: ~₹1,000 crores; FY28: ~₹700–800 crores (ex-OSAT) | FY27 and FY28 |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Standalone revenue | ₹3,505 cr, +32% YoY |
| Standalone PBT | ₹602 cr, 17.2% of sales, +47% YoY |
| Standalone PBT margin expansion | 180 bps YoY |
| Standalone ROCE (annualized) | 27% |
| Consolidated revenue | ₹3,802 cr, +30% YoY |
| Consolidated PBT | ₹559 cr, 14.7% of sales, +44% YoY |
| Consolidated PBT margin impact from semiconductor talent investments | ~₹35 cr, 91 bps drag |
| Consolidated ROCE (annualized) | 25% |
| Standalone order intake | ₹8,016 cr, +90% YoY |
| Standalone order backlog | ₹21,820 cr, +61% YoY as of 30 Sep 2026 |
| Power systems segment revenue | ₹1,769 cr, +41% YoY |
| Power systems segment PBIT margin | 25.0%, +430 bps YoY |
| Power systems segment order intake | ₹6,258 cr, +137% YoY |
| Industrial segment revenue | ₹1,738 cr, +25% YoY |
| Industrial segment PBIT margin | 9.4%, +60 bps sequential improvement |
| Export order intake growth | ~200% QoQ |
| G.G. Tronics order book | ~₹1,069 cr, flat QoQ |
| Core business capex FY27 (ex-OSAT) | ~₹1,000 cr expected |
| T3 power transformer capacity post-debottlenecking | 75,000 MVA, +10,000 MVA within same facility |
| Sehore greenfield transformer facility peak capacity | ~70,000 MVA, 35 transformers per month |
| Axiro Semiconductor Q2 profitability | Breakeven |