Chambal Fertilisers & Chemicals Ltd Q4 FY2022 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/mjoh1irg5tl0ew7mfd5rs42b.pdf

Key Takeaways


Gas Cost & Subsidy Dynamics

Management: "The subsidy is a pass-through, but the timing of receipt is something we cannot control. That is where the working capital pressure comes from."

Financial Position & Capital Allocation


Business Volumes & Demand


Industry & Policy Context

Management: "We are evaluating green ammonia, but the economics are not there yet. For now, our focus is on executing the TAN project and managing the gas cycle."

Guidance & Commitments

CommitmentSpecificsTimeline
TAN plant commissioningNew technical ammonium nitrate plant to start productionFY24
Working capital debt increaseSignificant rise in short-term debt expected due to gas cost and subsidy timingNear term, until subsidy receipts normalize
Capex outlayOver ₹1,000 crore for debottlenecking and the TAN projectOver FY23-FY24

Key Metrics

MetricQ4 FY22
Revenue₹4,426 cr, +28% YoY
EBITDA₹1,098 cr, +42% YoY
EBITDA margin24.8%, up from 22.4% YoY
Profit After Tax₹694 cr, +53% YoY
Urea production5.27 lakh MT, up from 4.89 lakh MT YoY
Urea sales5.31 lakh MT, up from 4.92 lakh MT YoY
Urea energy efficiency5.872 Gcal/MT, improved from 5.912 Gcal/MT YoY
Complex fertilizer production2.14 lakh MT, down from 2.31 lakh MT YoY
Complex fertilizer sales2.18 lakh MT, down from 2.35 lakh MT YoY
Trading sales volume1.02 lakh MT, up from 0.72 lakh MT YoY
Nano Urea sales0.65 lakh bottles (launched in Q4)
Subsidy outstanding₹2,800 cr as of March 31, 2022
Gas cost$14.5/mmbtu (spot LNG), up significantly YoY
Capex for FY22₹350 cr, against guidance of ₹400 cr
FY23 capex guidance₹500 cr