- HM Power acquisition completed, commercial production April 2026
Delivered - At the Q4 FY26 call, management stated HM Power commenced commercial production on April 1, 2026, with expected revenue of ₹200 crores in FY27. The acquisition was completed on March 30, 2026, and commercial production began April 1, 2026, as guided.
- Gross margin improve to at least 15% in FY27
On track - At the Q4 FY26 call, management guided that gross margin should improve to at least 15% in FY27, from \~12% in FY26. FY26 gross margin was \~12.8%, and FY27 commenced on 1 April 2026 and is currently in progress.
- ERC commercial production mid-July 2026, ₹30-35 cr contribution in FY27
Pending - At the Q4 FY26 call, management guided ERC commercial production in mid-July 2026 with ₹30-35 crores contribution in FY27. As of 14 July 2026, mid-July is imminent with no production commencement or revenue read yet.
- New manufacturing facility in South India near Nagpur or Chennai
Pending - At the Q2 FY26 call, management guided a new manufacturing facility in South India near Nagpur or Chennai, focusing on it in FY27. By the Q4 FY26 call, land had not been finalized and no timeline was given.
- EBITDA margins double-digit in FY26, mid-teen aspirational
Missed - At the Q2 FY26 call, management guided FY26 EBITDA margins would be double-digit and expressed hope for mid-teen margins. FY26 EBITDA margin was 9.78%, missing the double-digit threshold on a full-year basis.
- Trading turnover less than 15% of topline in 3-4 years
On track - At the Q2 FY26 call, management guided trading turnover should be less than 15% of topline in 3-4 years. FY26 trading was 27% of revenue, down from 33% in FY25, with an FY27 interim target of less than 20%.
- Revenue doubling in next 3-4 years
Pending - At the Q2 FY26 call, management guided revenue doubling in 3-4 years from a FY25 base of ₹205.79 crores, implying \~₹410 crores. FY26 revenue was ₹244.21 crores, and the 3-4 year horizon from September 2025 extends to September 2028-2029.
- FY27 revenue growth minimum 20% over FY26
Pending - At the Q2 FY26 call, management guided minimum 20% revenue growth in FY27 over FY26. The Q4 FY26 call revised guidance to ₹330-350 crores standalone revenue, above the \~₹293 crores floor, but FY27 has not commenced.
- Flux-Cored wire ₹25-30 cr annual revenue potential, 20-25% EBITDA margins
On track - At the Q2 FY26 call, management guided flux-cored wire at full capacity would contribute ₹25-30 crores with 20-25% EBITDA margins. Commercial production started end-September 2025, contributing \~₹4 crores+ in FY26 at \~15% capacity utilization, with FY27 target revised to at least ₹20 crores.
- FY26 revenue ₹260-275 crores
Missed - At the Q2 FY26 call, management guided FY26 revenue between ₹260 and ₹275 crores. Full-year FY26 total income was ₹244.21 crores, with management citing a shortfall in the last 15 days of March due to the U.S.-Iran war.