Key Takeaways
- Data and AI now 42% of contracted capacity, up from 14% two years ago, a 10x MW expansion that is reshaping the portfolio and driving repeat business with top-tier corporates.
- EBITDA grew 28% to INR1,295 crores, with operating leverage compressing SG&A from 18% to 9% of total income; PAT jumped ~4.4x to above INR85 crores.
- Run-rate EBITDA stands at INR1,870 crores entering FY27, with management noting reported EBITDA historically runs ~1.1x that figure, though no formal forecast is given.
- Curtailment risk is concentrated and quantified: the 525 MW Bikaner CTU project faces ~30% backdown, but at the company level it represents a manageable ~2.5% of EBITDA even under a full-year 50% backdown scenario.
- What to watch next quarter: whether the 1,500 MW minimum capacity addition guidance for FY27 stays on track given ALMM-related solar module procurement uncertainty, and any resolution on the DSM rules currently sub-judice.
The Data and AI Transformation
- Portfolio reshaping in progress: Data and AI contracted capacity reached 2,400 MW, growing 10x from ~260 MW two years ago, while the overall business also expanded. The share rose from 14% to 42% of contracted capacity over that period.
- Who is driving it: New inroad accounts include Princeton Digital Group and Iron Mountain, alongside repeat deals with STT Data. Management expressed astonishment at the power consumption growth data center clients exhibit once AI chips are deployed, noting each AI building consumes 10x the power of the next building.
- Repeat business anchors growth: 74% of new volumes came from existing clients, a function of serving the biggest and best corporates who keep coming back as their power needs scale.
- Conventional industry demand continues: Contracted volumes were also signed across cement, auto components, tire manufacturing, and chemicals, showing the model is not solely dependent on tech sector growth.
Kuldeep Jain: "2 years ago, i.e., on 1st April 2024, this number was about 14%. So in 2 years, it is grown from 14% to 42%. But our overall business has grown and as a result, in MW terms, this has grown nearly 10 times from about 260 MW to 2,400 MW."
Curtailment Risk and Grid Exposure
- The Bikaner situation: At the Bikaner 2 substation, curtailment runs about 30% of power injected, a known fact for that substation and not specific to CleanMax. The plant was commissioned around the cusp of the fiscal year, so FY26 company-level grid uptime remained 99.24% with almost no curtailment.
- Run-rate EBITDA is not curtailment-adjusted: The INR1,870 crores run-rate EBITDA assumes up to 1-1.5% grid downtime for standard maintenance, not the active curtailment now occurring at Bikaner.
- Quantified downside is modest: Management laid out the math: if backdowns continue six months at 40%, the risk is on 13% of EBITDA for six months (6.5%), and 40% of that equals ~2.5% of EBITDA. If it runs a full year at 50% backdown, the risk remains 6.5% of EBITDA.
- Diversification is the structural defense: As of April 2026, 87% of the portfolio is STU-connected or rooftop, with CTU at only 12-13% of run-rate EBITDA. Karnataka concentration fell from ~60% (April 2023) to 33% (April 2026), with other states at 14% and CTU becoming a growth segment.
- Grid's timeline is not the company's: The grid has forecasted an end to backdown by September of this year, but management urged conservatism, calling it an externality beyond their control.
Kuldeep Jain: "Because of just diversification of risk and a predominantly or 100% C&I, 87% STU or rooftop portfolio as of 1st April 2026. These backdown issues impact us less."
Capacity Pipeline and Execution
- FY27 capacity guidance: Management guided to a minimum of 1,500 MW of RE Power Sales capacity addition in FY26-27 and expressed high confidence in achieving it. The contracted pipeline stands at 2,600 MW under execution at an average tariff of INR3.85/unit (70% solar, 30% wind, minuscule battery storage), to be commissioned across FY26-27 and FY27-28.
- 100% of FY27 capacity already contracted: At the start of the fiscal year, every MW expected to come up this year is already contracted. Management does not see any real reason for the wind/solar mix or Data and AI share within the pipeline to change materially.
- Execution capability scaled ahead of need: The organizational effort to move from 500 MW/year to 1,500 MW/year began in January/February 2024. Management is hopeful the number will grow over time but is not projecting or forecasting further scaling.
- New states under construction: Projects are underway in Rajasthan, Andhra Pradesh, and Uttarakhand, with plans to add a number of new states this year.
- Revenue stabilization lag: Post-COD, it takes 3-6 months for revenue to stabilize due to technical plant stabilization, documentation, regulatory approvals, and ramp-up.
Kuldeep Jain: "when we were doing 500 MW every year and thought about doing 1,500 MW every year it felt like a real stretch, but I am hopeful that the number will grow over time but again that is not something which we are either projecting or forecasting right now."
Margins and Operating Leverage
- RE Power Sales margin expansion: EBITDA margin improved from 82% to 83.5%, driven entirely by operating leverage as capacity grows while SG&A does not grow at the same pace. Gross margin remained consistent at 92-93%.
- RE Services margin jump: EBITDA margin improved from 14.4% to 19.6%, with both gross margin and EBITDA margin expanding in what management called a very healthy year.
- SG&A compression is the engine: SG&A fell from 18% to 9% of total income, reflecting operating leverage as the company reaches what management believes is critical mass.
- Longer-term margin ambition: Management sees EBITDA margin on RE power sales rising from ~83% today to nearly 86% over 3-4 years, though it may remain a couple of percentage points below very large pure utility players due to genuinely higher operating costs of selling and building at 13 MW average PPA sizes.
- EBITDA per MW superiority: On a per MW basis, CleanMax is 30-35% superior on EBITDA per MW compared to peers who may calculate on an AC basis, per an analyst's math that management confirmed.
Kuldeep Jain: "2% to 3% of EBITDA margin that you sacrifice in half slightly higher operating cost is more than made up in a fantastic tariff you get in this business model."
Financing and Balance Sheet
- Cost of financing trending down: Reduced from 9.4% to 8.5% over three years through refinancing of matured portfolios and a strategy of moving debt to fixed rate. As of March 2026, 40% of the portfolio is fixed-rate financing.
- Interest cost outlook is uncertain: Management sees some potential upside from refinancing new projects on a company-specific basis, but flagged the macro environment of uncertainty and potentially rising interest rates given the global and India macroeconomic environment including FX rates. They declined to give a prediction.
- Negative minority interest explained: At the SPV level, the average age of assets is less than two years, and profitability (PAT) only comes after the fourth or fifth year. In initial years, SPVs show negative PAT due to interest and depreciation, so minority interest is negative at that stage.
- Cash flow hedge mechanics: An accounting entry sits against VPPA or I-REC contracts (contract for difference), based on power curve analysis and 25-year power price projections. It sits on both sides of the balance sheet (financial assets and hedge reserves) with zero P&L impact.
- Apple co-investment, not a PPA: A joint venture with Apple for 150 MW across three projects, with Apple investing INR104 crores of equity for a 49% stake. CleanMax owns 51%. These projects do not supply power to Apple; it is a financial investment and the second JV with Apple. Management declined to disclose the entry multiple.
Regulatory and Procurement Uncertainty
- DSM rules unresolved: New Deviation Settlement Mechanism rules came in a few weeks ago and have been taken to court. The MNRE Minister has stated there are constant meetings between MNRE and the Ministry of Power to find a solution. The matter is sub-judice and not settled. Management said internal calculations of the impact are not mature enough to share externally.
- ALMM creates solar module procurement gap: The company has not yet started buying solar modules for contracts commissioning after June 2026, waiting for a government decision on ALMM implementation (whether to immediately implement or give an extension). They planned around this by keeping solar commissioning light in the July-September rainy quarter and expect to start taking module deliveries from September or October.
- Energy storage announcement pending: Management expects in three or four months to make a proper announcement to investors on what they are doing in storage and its impact on DSM, curtailment, and the revenue side.
- ALCM-driven accelerated buying: Some accelerated buying is expected to reflect in the April to June 2026 quarter capacity addition numbers, with customers who miss that window still signing contracts later in the year.
Guidance and Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Capacity addition | Minimum 1,500 MW of RE Power Sales capacity added | FY26-27 |
| Contracted pipeline delivery | Of 2,600 MW contracted, at least 1,500 MW commissioned; remainder in next fiscal | FY26-27 and FY27-28 |
| CTU backdown risk | If backdown runs 6 months at 40%, impact ~2.5% of EBITDA; if full year at 50%, impact 6.5% of EBITDA | FY27 (conditional on grid behavior) |
| Energy storage strategy disclosure | Proper announcement to investors on storage plans and impact on DSM, curtailment, revenue | Within 3-4 months |
| EBITDA margin trajectory | RE Power Sales EBITDA margin to rise from ~83% to nearly 86% | 3-4 years out |
| Solar module procurement | Begin taking module deliveries for post-June 2026 contracts | September or October 2026, pending ALMM decision |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Revenue | ₹1,295 cr (FY26 EBITDA), +28% YoY |
| EBITDA | ₹350 cr (Q4), 32% EBITDA CAGR over last 3 years |
| Consolidated PAT | ₹45 cr (Q4), vs ₹17 cr in Q4 last year |
| Run-rate EBITDA | ₹1,870 cr as of 31 Mar 2026, up from ₹1,140 cr as of 1 Apr 2025 |
| RE Power Sales EBITDA margin | 83.5% (FY26), improved from 82% in FY25 |
| RE Services EBITDA margin | 19.6% (FY26), improved from 14.4% in FY25 |
| Operational capacity (RE Power Sales) | 3,100 MW, up from 1,700 MW at start of FY26 |
| Contracted capacity (RE Power Sales) | 5,700 MW as of 1 Apr 2026, with 2,600 MW under execution |
| New capacity added (FY26) | 1,471 MW across both segments, vs less than 500 MW last year |
| Capacity addition guidance (FY27) | At least 1,500 MW of RE Power Sales capacity |
| Data and AI share of contracted capacity | 42%, up from 14% two years ago; 2,400 MW vs 260 MW |
| Repeat business rate | 74% of new volumes contracted in FY26 |
| Average PPA tariff (under execution) | ₹3.85 per unit, 70% solar, 30% wind, negligible storage |
| Average PPA tenor | 23.17 years |
| Net debt | ~₹9,600 cr at end of FY26 |
| Cost of financing | 8.5%, reduced from 9.2% in FY25 and 9.4% three years ago |
| Grid uptime | 99.24% (FY26), indicating no curtailment |
| Receivable days | ~25 days, broadly same as prior year |