Coal India Ltd Q2 FY2024 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/joiwddyx708waj893bul2dsj.pdf

Key Takeaways


Volume & Operational Performance

Prasad: "Demand has never reduced or never stagnant. It is continuously — last 1 month, it is peaking up only, every month."

E-Auction & Realization Dynamics

Prasad: "We are using our platform and we are going to be independent of that. Partly MSTC right now, we are taking their help, but we are also developing from CMPDL, our — from Ranchi. By next year, we will be phasing out."

Cost Structure & Margins

Prasad: "It is not that only capex recovery are — this thing, but this environmental factors play a greater role."

Capex & Infrastructure Build-Out


Diversification & Long-Term Demand

Prasad: "Enough coal for this up to 2030. There is absolutely — there is no doubts. Future is very secured and there is a heavy demand."

Guidance & Commitments

CommitmentSpecificsTimeline
Production and dispatch target78 crore tons each for FY'24FY'24 full year
MCL volume target20.4 crore tons, back on track after July disruptionFY'24 full year
Power plant supply commitment61 crore tons to be fulfilledFY'24 full year
E-auction volume share15% of productionH2 FY'24
FY'25 production target84 crore tonsFY'25
FY'25 dispatch target~85 crore tons (85 crore tons)FY'25
Underground production targetScale from 2.5 crore tons to 10 crore tonsBy 2030
100 crore ton production targetIntact, contingent on demand and evacuationFY'27 (year not precisely specified)
FSA price hike (power sector)No increaseNext 1 year
FSA price hike (non-power)No increase seenNext 7-8 months
E-auction platform independencePhase out MSTC, move fully to own CMPDL platformBy next year
Solar capacity250 MW operationalBy end of current year
Five-year capex envelope~₹80,000 crores total, ₹18,000-20,000 crores annuallyNext 5 years
FMC capex₹24,700 crores (~₹5,000 crores/year)Next 5 years
Non-executive wage revisionDueFY'26
Executive cadre wage revisionDueFY'27

Key Metrics

MetricQ2 FY24
Production target (FY24)78 crore tons
H1 dispatches36.07 crore tons, of which power sector 29.54 crore tons (~80%) and non-power 6 crore tons
H1 e-auction volume3.2 crore tons, fully non-power
E-auction premium over notified price90% overall; BCCL 56%, ECL 71%, CCL 114%, NCL 114%, Mahanadi 107%
E-auction volume target (H2 FY24)15% of production
Power plant supply commitment (FY24)61 crore tons
Employee cost (FY24)₹46,000 crores, ~40% of total, less than last year
Total capex (FY24)₹16,500 crores; land ₹2,000–₹3,500 crores, equipment ₹1,965 crores
FMC investment₹24,700 crores over six to seven years; installed capacity 0.28 crore tons currently
Production target (FY25)84 crore tons
Dispatch target (FY25)~85 crore tons
Evacuation capability (FY25)85 crore tons
Underground production2.5 crore tons currently; target 10 crore tons by 2030
MDO incremental production (FY25)~2–2.5 crore tons; FY26 ~5.5–6 crore tons
Solar capacity target3,000 MW net zero; 250 MW by year-end FY24, 900 MW agreed at ₹2.64
Non-power FSA under old pricing mechanism1.1 crore tons