Cochin Shipyard Ltd Q4 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/476nlvbx97p6yrhr1hwl86aq.pdf

Key Takeaways


The Quarter’s Revenue Hole: Timing, Not Destruction

Madhu S. Nair: "the management is happy to report that the project is actually... on the revised estimates, there is going to be a significant profitability that will come in on the project."

Order Book & Pipeline: The Naval Backbone

Madhu Nair: "I can guide you towards overall profitability of more than Rs.800 crores on those projects."

Europe & Green Vessels: The Commercial Thesis

Madhu Nair: "Cochin Shipyard has always been more comfortable in a niche set of vessels, where we are not working directly into the competitive strength of some of the Chinese shipyards and some of the Korean shipyards. So that is not where we want to go."

Ship Repair: A Bump, Not a Breakdown

Madhu Nair: "We have seen a little bit of a jump by some of our competitors into ship repair. We have been in this business 45 years. We understand where the money comes from and where we can lose big time if that is the case."

Infrastructure Build-Out: Dry Dock & ISRF

Madhu S. Nair: "the company hopes while this is not a financial point at this stage, but from a technical point of view, the company would be among the leaders in this technology."

Margins: The New Normal

Madhu Nair: "That's a very, very tough thing to answer because that's actually really in the competitiveness. I will not be able to give an exact figure on that."

Guidance & Commitments

CommitmentSpecificsTimeline
ASW SWC main enginesShipment from GermanySecond week of June 2023
Hydrogen fuel cell vesselCompletion and pilot trials in Cochin backwatersSeptember 2023
ASW Corvettes first launchFirst 3 vessels launchedNovember 2023
New dry dock completionProject completed; fully commissionedDecember 2023; mid-2024
ISRF partial commissioningShip lift and first 2 workstations; full facilityDecember 2023; mid-2024
ASW Corvettes first deliveryFirst vessel delivered to NavyNovember 2024
NGMV first deliveryFirst vessel delivered48 months from March 2023
FY24 shipbuilding revenueAround ₹3,000 croresFY24
FY24 ship repair revenueAround ₹900 croresFY24
FY24 shipbuilding EBITDA marginAround 12–13%FY24
FY24 ship repair EBITDA marginAround 18–19%FY24
FY24 blended EBITDA marginAround 14–15%FY24
ISRF initial revenue rampIncremental ₹200–250 croresFirst 24 months from commissioning
ISRF full-capacity revenue₹500–600 croresFull-blown condition
Andaman & Nicobar vesselsNo further LD provision beyond ~20% already providedGoing forward
Vikrant residual revenue₹1,876 crores to be bookedOver current FY and next FY

Key Metrics

MetricQ4 FY23
Revenue₹3,000 cr guided for FY24 Shipbuilding, ₹900 cr guided for FY24 Ship Repair
EBITDA margin (Shipbuilding)12% to 13% guided for FY24
EBITDA margin (Ship Repair)18% to 19% guided for FY24
Blended EBITDA margin14% to 15% guided for FY24
Order book₹21,400 cr, firm orders
Order pipeline~₹35,000 cr, expected to turn into RFPs over next 12 to 18 months
Turnover impact from re-estimation₹275 cr to ₹280 cr reduction taken in Q4, shifted to future periods
One-off income (lease rent capitalization)~₹62 cr in Q4 from ISRF lease rent capitalization
ASW Corvettes contract profitabilityMore than ₹800 cr guided on the ₹6,400 cr contract
Next-Generation Missile Vessels contract₹9,805 cr, signed March 30, 2023, 6 vessels
IAC Vikrant pending revenue₹1,876 cr to be booked over FY24 and FY25
New dry dock completion76% fiscal completion, expected completion December 2023
ISRF facility completion78% fiscal completion, ship lift and 2 workstations by December 2023
ISRF incremental revenue target₹500 cr to ₹600 cr in full-blown condition, ₹200 cr to ₹250 cr in initial 24 months
Andaman & Nicobar vessels LD provision20% of contract price provided; pending order book value ₹295 cr