Current Infraprojects Ltd Guidance Report - SOIC x StockScans Report
as of Nov 2026
- FY27 revenue from Jaipur Discom awards - \~₹90-94 cr to be booked
On track - In the June 2026 announcement, management stated that of the \~₹100 crore Jaipur Discom (JVVNL and JDVVNL) awards, only ₹5-6 crore was booked in FY26, with the remaining approximately ₹90-94 crore to be booked in FY27 per contract completion timelines (tenure \~15 months). No FY27 booking amount is disclosed yet; H1 FY27 total income was ₹53.60 crore, with the full year not yet complete.
- PM Surya Ghar rooftop project - 8,000 plants by FY27 or 10 April 2027
On track - At the Q2 FY27 call, management targeted completing all 8,000 plants (1.1 kW each) under the PM Surya Ghar (JVVNL) rooftop project by this financial year or by 10 April 2027 at the latest, at a run-rate of \~1,500 plants per month till end of the financial year. As of Q2 FY27, \~100 plants were installed, described as "ahead of the curve", with manpower and purchase orders placed and full-fledged execution starting within three-four days of the call.
- H2 FY27 operating cash flow - turn positive
Pending - At the Q2 FY27 call, the CFO said H1 FY27 negative operating cash flow will "definitely be turning into the positive" in H2, reiterating it would "definitely" turn positive in the upcoming six months. No H2 FY27 outcome is disclosed yet; FY26 operating cash flow remained negative.
- New bid margins - PAT 8-10%, gross margin 17-20%
On track - At the Q2 FY27 call, management expected PAT margin around 8-10% (pre-tax 10-12%) and gross margin around 17-18% to 20% for new bids, and said "we will try for increase" on FY27 margins. H1 FY27 PAT margin was 9.39%, within the 8-10% range; Q2 FY27 OPM was 18.73% with PAT of ₹5.01 crore.
- Electrical EPC (including solar) revenue share - 50-70% over next 2-3 years
On track - At the Q2 FY27 call, the CFO guided electrical EPC (including solar) to contribute 50-70% of total revenue over the next two-three years. In September '26, of standalone \~₹50 crore revenue, \~₹35-40 crore came from electrical and solar; FY26 solar EPC was \~60% of revenue.
- RESCO capacity expansion - additional 20-30 MW
Pending - At the Q2 FY27 call, management planned to expand RESCO/solar capacity by another 20-30 MW after successfully commissioning the existing \~10 MW across four SPVs. No outcome on new capacity additions is disclosed yet; the existing portfolio stands at four plants aggregating \~9.41 MW, all commissioned.
- RDSS order execution - \~60% of \~₹100 cr completed by end of FY27
On track - At the Q2 FY27 call, management expected \~60% of the \~₹100 crore RDSS order work to be completed by end of March (this fiscal year), dependent on government fund availability. As of Q2 FY27, approximately 23-25% of the \~₹100 crore orders were completed with payments received per project conditions; FY27 is not yet complete.
- IPO proceeds deployment - ₹30 cr working capital, ₹5.85 cr subsidiaries, remainder GCP
Delivered - At the Q4 FY26 call, management reiterated the IPO mandate of ₹30 crores for working capital, ₹5.85 crores for investment into subsidiaries and the remainder for general corporate purposes, with a certificate of consumption already submitted. Funds were fully utilised by 31.03.2026: ₹558 lakhs (₹5.58 crore) invested in Current Infra Dhanbad Solar for the 1800 KW RESCO plant and ₹3,027 lakhs toward working capital, with nil unutilised, against net proceeds of ₹38.54 crore.
- FY27 top line - ₹200-250 cr revenue, margins "almost the same" as FY26
On track - At the Q4 FY26 call, management guided FY27 top line of around ₹200-250 crores with operating margins "almost the same" (vs 14.5% in FY26), reiterated as around ₹250 crore in the FY26 annual report; at Q2 FY27 this was reaffirmed at ₹200 crore, narrowed from ₹200-250 crore, citing H2/Q4-heavy billing seasonality. H1 FY27 consolidated total income was ₹53.60 crore, up 19.46% YoY; Q2 FY27 revenue was ₹53.40 crore, up 20.03% YoY.
- FY27 solar project execution - ₹50-80 cr of solar projects
On track - At the Q4 FY26 call, management stated confidently it expected to execute around ₹50 to 80 crores of solar projects in FY27, contingent on results of \~₹200 crore worth of solar plus BESS tenders already bid. Of that pipeline, more than ₹100 crore converted into orders in the last six months, and H1 FY27 secured projects worth \~₹75 crore plus; no solar execution value for FY27 is disclosed yet.
- FY27 RESCO revenue - ₹6+ cr annual levelized revenue, first full year FY27
On track - At the Q4 FY26 call, management expected the full \~₹6 cr annual levelized RESCO revenue to reflect in the books in FY27, FY26 having been a partial year, reiterated in the FY26 annual report as FY27 being the first full year of RESCO generation at annual levelised revenue above ₹6 crore. H1 FY27 RESCO revenue contribution was \~₹3 crore, with all four plants (9.41 MW aggregate) commissioned and generation at 5.5+ units/kW/day at Rajasthan KUSUM plants and 4-4.5 units/kW/day at Dhanbad.