Key Takeaways
- Weak quarter, prices the culprit: EBITDA fell 34.5% Y-o-Y as cement prices remained soft, though December brought the first signs of improvement and January is holding.
- Volume story is cleaner than it looks: Reported volumes de-grew 2% Y-o-Y only because last year included tolling from JP plants; Dalmia's own plants grew 3.7% Y-o-Y.
- Cost-side levers are pulling: Power and fuel costs dropped 9% Y-o-Y, and management is sticking to its INR150–200/ton cost-savings target by FY27 through internal measures alone.
- Capacity expansion stays on track: Debottlenecking added clinker capacity, the 4.95 crore-ton target for FY25 is within reach, and the Phase 2 roadmap to 7.5 crore tons by FY28 will be detailed by July.
- What to watch next quarter: Whether the Q4 demand pickup of 6–7% materialises, how much of the December price gain sticks, and the competitive response as Penna and India Cements ramp up in the South.
Demand & Pricing Environment
- Macro drag, Q4 bounce expected: Cement demand undershot expectations through nine months as elections, heavy monsoons and weak government spending weighed on activity; management expects Q4 demand to grow 6–7% Y-o-Y as government capex improves ~20% in the December-to-March period.
- Full-year reset: Industry growth for FY25 is now pegged at just 3–4%, with Dalmia outpacing that at ~4% on a nine-month basis.
- Prices: green shoots, not a breakout: Some improvement came through in December and held into January, but management flagged that increasing competitive intensity may cap significant gains.
- East outperforming South: The East market has grown better than the South so far this year, a dynamic that matters as Dalmia balances its regional mix.
- South getting more crowded: Penna and India Cements are expected to ramp up volumes, and management warned prices there could be volatile depending on how demand shapes up.
- FY26 demand bet: If GDP growth picks up, industry cement demand should land in the 6–8% range next year.
Puneet Dalmia: "I think we are quite lucky that the timing of our investment is coming together with the likely surge in demand in Northeast."
Volume & Realisation Dynamics
- The tolling distortion: The 2% Y-o-Y volume decline is entirely explained by the loss of 0.04 crore tons of tolling volume from JP plants last year; Dalmia's own-plant sales grew 3.7% Y-o-Y.
- Q4 volume ambition: Management expects the company to grow much faster than the 6–7% industry rate in Q4, though it declined to give a specific quarterly number.
- NSR improvement in line with prices: Excluding the INR14 crores of first-half incentive accrual booked in Q3, net sales realisation growth tracked the price improvement seen during the quarter.
- Current realisations: In line with December levels, with no further colour on the trade vs non-trade or region-wise split.
- Long-term growth posture: The stated trajectory remains 1.5x the market, though management cautioned that quarter-on-quarter variations are inevitable.
Costs & Margin Levers
- Power and fuel: the big tailwind: Costs declined 9% Y-o-Y with a \$26/ton drop in fuel consumption cost; renewable energy share improved from 30% to 33%, though the benefit was partly offset by plant shutdowns that reduced WHRS output.
- Raw materials edged down: Marginal 2% Y-o-Y decline, driven by lower fly ash and limestone raising costs.
- Logistics: the offset: Costs rose 2.7% Y-o-Y as the end of the JP tolling arrangement forced supply to central markets from Eastern plants, and debottlenecking shutdowns pushed up clinker movement costs.
- Fixed costs kept tight: Hiring was held in check, marketing spend reviewed for productivity, and stores and spares consumption kept to a bare minimum; higher shutdowns in Q2 were reduced in Q3.
- The INR150–200/ton commitment: Management reaffirmed the target for FY27, driven entirely by internal initiatives: power consumption, heat consumption, raw-material mixing and logistics lead reduction, with no reliance on pet-coke or coal price movements.
- Lead reduction as a lever: A deliberate shift toward nearer markets is part of the logistics cost plan.
- Q4 power cost tailwind: Should decline further as RE share rises from 33% to 40–45%.
- Rajgangpur accident: A captive power plant incident will not hit production but may push power costs slightly higher while the plant stays shut for corrective measures.
Puneet Dalmia: "While we are one of the lowest cost cement producers, we are committed to further deepen our position by realizing the cost savings of INR150 to INR200 per ton through internal measures by financial year'27."
Capacity Expansion & Capital Allocation
- Debottlenecking delivered: Clinker capacity rose to 2.35 crore tons through debottlenecking at Kadapa and Rajgangpur.
- FY25 cement capacity target: On track to reach 4.95 crore tons by end of FY25.
- Phase 2 roadmap: The plan to reach 7.5 crore tons by FY28 will be detailed within the next six months, with a full roadmap promised by July.
- Northeast clinker unit: Expected to commission in Q2 of FY26, timed with what management sees as a likely demand surge in the region driven by hydropower, infrastructure and connectivity projects.
- Capex run-rate: FY25 capex expected at ~INR3,000 crores, with ~INR1,000 crores of that falling in Q4; next year's range is INR2,500–3,000 crores including land investment.
- Balance-sheet discipline: Net debt rose INR600 crores during the quarter, split evenly between an IEX price decline and capex not fully covered by internal accruals; the stated framework caps net debt to EBITDA at 2x unless a large acquisition or strategic opportunity arises.
- Incentive top-up: One plant received a two-year incentive extension effective April 2024, adding INR14 crores accrued for the first half to Q3; full-year incentive accruals and collections are expected around INR325 crores, normalising to INR90–100/ton in FY26.
Renewable Energy Build-Out
- Scale-up in Q3: 46 MW of RE capacity commissioned under group captive arrangements during the quarter, taking total operational RE capacity to 252 MW.
- Pipeline building: Signed group captive agreements for another 21 MW in Q3; total long-term RE agreements signed now stand at 299 MW.
- FY25 exit rate: Expect to end the year with 267 MW of operational RE capacity and a 40–45% RE share in the overall power mix on a consumption basis, up from 33% in Q3 as WHRS comes back online.
- Solar addition: Commissioned 4 MW of solar power capacity at Medinipur, West Bengal.
People, Safety & Culture
- Succession planning underway: Management is reviewing succession in every role, with the MD personally going deep into the organisation over the last 12 months; more colour promised as situations evolve.
- Safety push after Rajgangpur: The captive power plant accident has sharpened focus: safety champions are being built in each plant zone, training has increased for both internal staff and contractors, and unit heads now have KRAs linked to safety parameters.
- Mobile phone ban: A decision has been taken to ban mobile phone use inside plants, though management acknowledged that implementing it with rigour to the last level remains a challenge.
- Long-term culture bet: Management wants to build a culture over the next 3–5 years where the company competes on practices rather than price, and to bring more transparency to pricing anomalies.
Puneet Dalmia: "I still see people when they're working, they use mobile phones. And I think we have banned this, and we've taken a decision to ban this in our plants. But again, implementing this with that kind of rigor is sometimes just make sure that the safety culture penetrates to the last level."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Cement capacity | Reach 4.95 crore tons | End of FY25 |
| Phase 2 expansion roadmap | Full plan to reach 7.5 crore tons | By July 2025 (within 6 months) |
| Northeast clinker unit | Commission | Q2 FY26 |
| RE capacity | 267 MW operational | End of FY25 |
| RE power share | Exit at 40–45% of consumption mix | End of FY25 |
| Cost savings | INR150–200/ton through internal measures | By FY27 |
| FY25 capex | ~INR3,000 crores | FY25 |
| FY26 capex | INR2,500–3,000 crores (incl. land) | FY26 |
| Net debt to EBITDA | Not to exceed 2x (barring large acquisition/strategic opportunity) | Ongoing |
| Full-year incentives FY25 | ~INR325 crores accruals and collections | FY25 |
| Normalised incentive rate | INR90–100/ton | FY26 |
| Full-year depreciation FY25 | INR1,330–1,340 crores | FY25 |
| Industry demand growth FY26 | 6–8% (conditional on GDP pickup) | FY26 |
Key Metrics
| Metric | Q3 FY25 |
|---|---|
| Revenue | Not stated |
| Volumes | 0.67 crore tons, -2% YoY; sales from Dalmia plants grew 3.7% YoY |
| EBITDA | ₹511 crores, -34.5% YoY |
| EBITDA per ton | ₹765 |
| Raw material cost per ton | ₹765, -2% YoY |
| Power and fuel cost per ton | ₹1,005, -9% YoY |
| Fuel consumption cost | \$96 per ton, vs \$101 in Q2 FY25 and \$122 in Q3 FY24 |
| Fuel cost per Kcal | ₹1.31 |
| Logistic cost per ton | ₹1,120, +2.7% YoY |
| Lead distance | 269 km, reduced from 287 km in Q3 FY24 |
| Trade mix | 66%, up from 63% YoY |
| Premium product mix | 24.2%, up from 22.4% QoQ and 21% YoY |
| Blended cement ratio | 85.1%, up from 82.7% QoQ |
| Clinker-to-cement ratio | 1.70, improved from 1.64 QoQ |
| Renewable energy share | 33%, up from 30% YoY; expected to reach 40-45% by Q4 FY25 |
| Total operational RE capacity | 252 MW, with 267 MW expected by end of FY25 |
| Incentives accrued | ₹102 crores, including ₹14 crores for prior periods; full-year guidance ~₹325 crores |
| Incentives outstanding | ₹760 crores as of 31 December |
| Depreciation | ₹364 crores, +8.3% QoQ; full-year guidance ₹1,330-1,340 crores |
| Capex incurred (Q3) | ₹657 crores; 9-month total ~₹2,040 crores; full-year guidance ~₹3,000 crores |
| Gross debt | ₹5,457 crores as of 31 December |
| Net debt | ₹1,242 crores as of 31 December |
| Net debt-to-EBITDA | 0.55x |
| Cement capacity target | 4.95 crore tons by end of FY25; Phase 2 target 7.5 crore tons by FY28 |
| Cost savings target | ₹150-200 per ton by FY27, via internal measures |
| FY26 industry demand growth expectation | 6% to 8% |