Dilip Buildcon Ltd Q1 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/p67dz5fvhre83mvjc703i1ax.pdf

Key Takeaways


The Deliberate Order Book Reset

Suryavanshi: "We have chosen to uphold our threshold margin levels, which has led to a temporary decline in our order book."

InvIT: Structure, Timeline and Debt Impact

Bansal: "So that is why we have kept 0 distribution in FY '27."

Coal MDO: The Steady Anchor


Order Inflow and Revenue Outlook

Suryavanshi: "We don't want to take new orders at the cost of our profitability, at the cost of hitting our return ratios or just for the sake of taking orders."

Working Capital and Cash Flow


Guidance & Commitments

CommitmentSpecificsTimeline
Order inflow₹12,000–15,000 cr new ordersFY26
Revenue₹8,000–8,500 crFY26
EBITDA margin~11%FY26
Stand-alone debt reduction₹500 cr reductionBy 31 March 2026
Net debt freeNet debt freeBy FY27 end
InvIT listingLaunch with 8 completed assetsWithin this quarter (by September)
HAM project divestmentComplete and partially divest 4 of remaining 7 projectsThis financial year
Remaining HAM divestmentRemaining 3 projectsNext financial year
Siarmal MDO production2.5 crore metric tonsFY26
Siarmal MDO production3.5 crore metric tonsFY27
CHP capex startBegin coal handling plant capexWithin next 1–2 quarters
CPPIB debt prepaymentPrepay ₹285 cr outstandingWithin this financial year
JJM milestone payment~₹450 cr receiptQ3 FY26
Capex₹40–50 cr (replacement only)FY26

Key Metrics

MetricQ1 FY26
Revenue (standalone)₹2,010 cr, down 14.7% YoY from ₹2,358 cr
EBITDA (standalone)₹203 cr, down 22.5% YoY from ₹262 cr
EBITDA margin (standalone)~10.1%, down YoY; reduction in revenue from road and water supply projects
Profit after tax (standalone)₹123 cr, up 61% YoY from ₹47 cr
FY26 revenue guidance (standalone)₹8,000–8,500 cr
FY26 EBITDA margin guidance (standalone)~11%
FY26 order inflow guidance₹12,000–15,000 cr
Order book (projects bid, outcome awaited)~₹20,000 cr across sectors
Net debt (consolidated)₹8,266 cr as of 30 June 2025
Standalone net debt₹1,661 cr as of 30 June 2025
Standalone debt reduction target₹500 cr reduction by 31 March 2026, target intact
Net debt free targetFY27, target intact
Siarmal MDO production volume0.54 cr metric tons in Q1 FY26, full-year target 2.5 cr metric tons
HAM projects completed in Q12 projects worth ₹1,605 cr
HAM partial divestment completed3 projects to Alpha Alternatives for ₹125 cr
InvIT listing timelineExpected within Q2 FY26 (September 2025), in-principle approvals received
Net working capital days84 days, up from 75 days at March 2025