Dilip Buildcon Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/o3esbqyfsnq0x8hy2jkuji84.pdf

Key Takeaways


Order Inflow & the Revenue Reset

Suryavanshi: "This increased competitive intensity was what had caused significant damage to the industry. And I think the government has finally woken up to that because progress and quality has both suffered."

Debt: Peak, Drivers & the Path Down

Suryavanshi: "This is the peak debt level. If you see in the last few years, we've only kept on reducing. And if the external environment had been supportive if we had not seen a reduction in our top line in the last 2 years, we would have obviously made strides and been able to make even a larger sort of reduction in our debt."

The Long-Term Asset Pivot

Suryavanshi: "So while EPC will continue to fire, but year after year, our profitability, even if not in terms of revenue but in terms of profitability and the amount of free cash that DBL is generating, 75% plus will come from long-term assets."

Cost Structure & Margin Mechanics


New Bets: Solar & Beyond


Guidance & Commitments

CommitmentSpecificsTimeline
Order inflowINR15,000 crores total, possibly higherFY26 full year
Revenue~INR8,000 crores (revised from INR8,500 crores)FY26 full year
Revenue~INR10,000 crores, driven by this year's INR15,000 crores of ordersFY27
Standalone net debt~INR1,500 croresEnd-FY26
Standalone net debt~INR1,000 croresEnd-FY27
Standalone net debtNet debt-freeFY28
Consolidated debtRange-bound INR6,000-7,000 crores, only reducingOngoing from peak
InvIT debt transfer~INR1,500 crores debt reduced via four asset transfersQ1 FY27
InvIT debt transferBalance ~INR3,000+ crores debt reducedBy March 2027
Coal production3.2 crore metric tons (Siarmal 2.5, Pachhwara 0.7)FY26
Coal production3-3.5 crore tons from SiarmalFY27
Coal production4.2 crore peak rated capacity from SiarmalFY28
Coal production5 crore tons from Siarmal~FY31 (3 years after peak)
Mining fee100% (from current 78%)FY29
Interest & finance costs~INR450 croresFY26
Interest & finance costs~INR350 croresFY27
Working capital daysCloser to 90 days (from 114 in H1)End-FY26
EBITDA margin~10-11% maxFY26
Solar awards1 gigawattNext 2 years
Solar IRRMid-teen returnsOn awarded projects
Long-term profit mix75%+ of profitability and free cash from HAM InvIT and coal MDOSteady-state goal

Key Metrics

MetricQ2 FY26
Standalone revenue₹1,417 cr
H1 FY26 standalone revenue₹3,427 cr
Standalone EBITDA margin10.80%, up 60 bps QoQ; absolute EBITDA ₹153 cr
H1 FY26 standalone EBITDA margin10.40%; absolute EBITDA ₹356 cr
Profit after tax₹214 cr
H1 FY26 profit after tax₹485 cr
Full year FY26 revenue guidance₹8,000 cr, revised down from ₹8,500 cr
FY27 revenue guidance₹10,000 cr
Full year FY26 EBITDA margin guidance10% to 11%
Order inflow guidance for FY26₹15,000 cr
Year-to-date order inflows secured₹5,500 cr
Order book₹18,600 cr
Net debt (standalone)₹2,102 cr
Net debt increase from March to September₹526 cr, driven by ₹450 cr reduction in creditors
Full year FY26 interest and finance cost target₹450 cr
FY27 interest and finance cost target₹350 cr
Siarmal MDO H1 FY26 sales volume1 crore metric tons; full year target 2.5 crore metric tons
Pachhwara MDO H1 FY26 sales volume0.36 crore metric tons; full year target 0.7 crore metric tons
Total coal production target for FY263.2 crore metric tons
Expected coal production by 20295.7 crore metric tons, 8% to 9% of India's total coal output
HAM assets transferred to InvIT7 of 18 assets transferred; balance to transfer over next 2 years
InvIT units held by DBL₹1,332 cr worth units at ₹100 issue price, valued at ~₹1,400 cr
Consolidated debt reduction from InvIT transfer in Q3₹2,961 cr precisely will be reduced
Consolidated debt as of 30 September₹9,097 cr
Consolidated debt expected range₹6,000 cr to ₹7,000 cr
Employee count~18,000, reduced from peak of 38,000 during COVID
Annual capex₹50 cr to ₹100 cr, down from earlier ₹500 cr range, only replacement capex
Working capital days~114 days this quarter, expected to come closer to 90 days