Key Takeaways
- Legacy projects still dragging margins: EBITDA margin stayed depressed as older projects extended 50% in time, doubling manpower and equipment overheads, while input prices rose ~50%.
- Order book rebuilding after eligibility restored: Won two HAM projects worth ₹2,931 crore after March 2022, and the NHAI bidding suspension was lifted from October onward.
- Balance sheet strengthening: Net debt/equity fell to 0.63 from 0.73 QoQ, debtors dropped ₹466 crore, and working capital days improved to 89 from 102.
- FY23 guided for ₹10,000 crore revenue at 13–14% margin, but Q1 and Q2 will be tepid as legacy projects complete; normal execution expected only from Q3.
- What to watch next quarter: Whether the ₹700–800 crore legacy order book actually closes out in 2–3 months, the pace of margin recovery toward 13–14%, and closure of the Cube deal in June.
Legacy Project Overhang
- The margin drag: Older projects awarded from 2018 onward got extended by 50% in time period, causing manpower and equipment costs to rise 50%, with these additional overheads hitting EBITDA margin directly. Material prices for cement, diesel, steel and aggregates also increased by almost 50% on average.
- Remaining exposure: ₹700–800 crore of legacy order book remains; in Q4 these projects ramped up and reached near-breakeven at ₹0 to ₹3 crore profit. Management expects them to complete in 2–3 months, meaning margin impact persists through Q1 and Q2 FY23, with normal execution from Q3 onwards.
- No quarter-on-quarter margin roadmap: Management declined to give quarterly margin guidance or quantify the cost-to-completion shortfall at current commodity prices, citing volatile material prices and stating the numbers were not available.
Management: "because of the legacy projects there will be obviously till they complete our slate will not clean up. This challenge will always be there."
FY23 Guidance & Revenue Build-Up
- Topline target: FY23 revenue guided at around ₹10,000 crore, subject to no further COVID-related lockdowns or other large disruptions. Q1 and Q2 will be tepid because older projects are still completing; improvement should become visible from Q3 onward.
- Margin target: EBITDA margin guided at 13–14% for FY23, subject to raw material prices and other factors. Normal execution and profitability expected only from Q3 once legacy projects are fully closed.
- Order inflow target: ₹8,000 to ₹10,000 crore of new orders across all sectors, similar to last year.
- Five projects awaiting appointment date: Management declined to give project-wise or group-wise revenue contribution guidance for FY23, calling it "very difficult," but stated the ₹10,000 crore revenue target is expected to be met based on the current situation.
Management: "we actually have zero control how it will pan out. So, whatever we tell you is based on our expectation of how things should pan out."
Competitive Intensity & Bidding Environment
- HAM competition easing: Competitive intensity in HAM has reduced recently, with 6 to 8 players now versus 15 to 18 previously, because securities and qualification criteria have been brought back after COVID-era relaxations.
- EPC still crowded: EPC continues to see more competitive intensity, but high order books of smaller players are expected to keep it from reaching last year's levels.
- Win rate reflects the intensity: DBL bid for almost 105+ projects during the year while winning only five or six, illustrating the competitive pressure that built up when the government reduced guarantees and qualification criteria during COVID.
- Bidding strategy: Target continues to be EPC, but the company will make the call based on competitive analysis; HAM and equity decisions may alter the bidding strategy.
Rohan Suryavanshi: "even DBL on its part, we have been for almost 105 plus projects, while we won only five or six projects, so, you can imagine the kind of competitive intensity that the market had."
Balance Sheet & Working Capital
- Debt reduction: Net debt/equity ratio decreased to 0.63 in Q4FY22 from 0.73 in Q3FY22, an absolute decrease of ₹406.8 crore. Standalone debt reduction for FY23 expected in the range of ₹300 to ₹400 crore from the current ₹3,072 crore.
- Debtors improvement: Debtors decreased to ₹1,038 crore from ₹1,504.1 crore QoQ on better collection. Debtor days expected to keep moving in the 40 to 50 day range.
- Working capital: Working capital days decreased to 89 as of Q4FY22 from 102 as of Q3FY22.
- Inventory target: Quantity reduced but average price around ₹3,400 crore; target to reduce to ₹2,900–3,000 crore by financial year-end.
- Finance cost: Decreased by 4.99% YoY in Q4FY22.
- CAPEX: Only ₹5–10 crore of normal CAPEX planned for FY23; no other capital expenditure planned.
- DBL Infra debt: Remains at ₹702 crore, same as last quarter; no further debt raising.
Asset Monetisation & Equity Events
- SREI InvIT: ₹450 crore already received from SREI InvIT during the quarter. Company will start receiving InvIT units from June end or early July; out of 10 assets being transferred, 5 are already completed and NOCs from respective lenders are being obtained before approaching NHAI.
- InvIT units as liquidity: A non-binding agreement has been done for InvIT units of around ₹1,800 crore. These units can be sold at any time to reduce debt, functioning as near-cash.
- Cube deal: NACA approval already received for transfer of remaining equity in one SPV; in process of receiving approval for the other two SPVs. Final closure expected in June after completing six months from COD of each project, with balance ₹145–150 crore to be received.
- CPPIB drawdown: At company's discretion, linked to equity investment in underlying subsidiary; open but not obligated to draw.
Management: "We have already done the agreement with the SREI and we will get the unit of around Rs. 1800 crores. So, at any time if you want to reduce the debt you can sell them because 1800 is like the cash."
Project Completion & Regulatory Status
- Completed projects: 12 projects completed in FY22 worth ₹815.9 crore across different geographies.
- Order wins: Won 5 new projects in three sectors worth ₹781.1 crore till March 2022, plus two more HAM projects worth ₹2,931 crore won after March 2022 and not included in the March 2022 order book.
- Anandapuram-Anakapalli project: The project where an accident occurred has been completed and received a provisional completion certificate (PCOD) from the agency.
- Bidding eligibility restored: The suspension on bidding for new NHAI projects was lifted from October onward; the company has been winning projects from NHAI since then.
- Bharuch irrigation project: Was lagging because of excessive rainfall with the rainy season extending till end of November; revenue normalized starting Q4 and the situation is expected to normalize in Q1 FY23.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY23 revenue | ~₹10,000 crore, subject to no COVID lockdowns or large disruptions | FY23 |
| FY23 EBITDA margin | 13–14%, subject to raw material prices | FY23 |
| FY23 order inflow | ₹8,000–10,000 crore across all sectors | FY23 |
| Standalone debt reduction | ₹300–400 crore from current ₹3,072 crore | FY23 |
| Legacy project completion | ₹700–800 crore order book to complete | 2–3 months |
| Normal execution resumption | Legacy impact to go away, normal profitability | From Q3 FY23 |
| Cube deal closure | Final closure, balance ₹145–150 crore to be received | June 2022 |
| Inventory reduction | From ~₹3,400 crore to ₹2,900–3,000 crore | By FY23 year-end |
| Debtor days | Maintain in 40–50 day range | Ongoing |
| CAPEX | Only ₹5–10 crore normal CAPEX | FY23 |
Key Metrics
| Metric | Q4 FY22 |
|---|---|
| Revenue | ₹2,506.2 cr, lower than last year's performance |
| EBITDA | ₹236.8 cr |
| EBITDA margin guidance (FY23) | 13–14%, subject to raw material prices |
| Profit after tax | Decreased on account of decrease in EBITDA; near breakeven at ₹0 to ₹3 cr profit |
| Finance cost | Decreased 4.99% YoY |
| Order book | ₹25,594.5 cr, 45% road sector and 55% other sectors |
| Order inflow (FY22, ex-GST) | ~₹6,500 cr (₹7,800 cr including GST) |
| Order inflow guidance (FY23) | ₹8,000 to ₹10,000 cr |
| Revenue guidance (FY23) | ~₹10,000 cr |
| Net debt equity ratio | 0.63, improved from 0.73 in Q3FY22; absolute debt reduced by ₹406.8 cr |
| Working capital days | 89 days, improved from 102 days in Q3FY22 |
| Debtors | ₹1,038 cr, decreased from ₹1,504.1 cr in Q3FY22 |
| Inventory | Increased marginally by ₹34.6 cr from Q3FY22; total ~₹3,400 cr with target to reduce to ₹2,900–3,000 cr by FY23-end |
| Retention money | ~₹774 cr |
| Mobilization advance | ~₹1,080 cr |
| Unbilled revenue | ~₹1,100 cr |
| Legacy project balance (won in 2018) | ₹700 to ₹800 cr, expected to complete in 2–3 months, impacting Q1 and Q2 FY23 |
| Projects completed in FY22 | 12 projects worth ₹815.9 cr |
| New projects won (till Mar 2022) | 5 projects worth ₹781.1 cr |
| HAM projects won post Mar 2022 | 2 projects worth ₹2,931 cr (EPC ex-GST ~₹2,000 cr), not in Mar 22 order book |
| Amount received from SREI InvIT | ₹450 cr |
| InvIT units to be received | ~₹1,800 cr |
| DBL Infra debt | ₹702 cr, unchanged from Q3FY22 |
| Standalone debt reduction expected (FY23) | ₹300 to ₹400 cr from current ₹3,072 cr |
| CAPEX (Q4 FY22) | ₹12 cr; full year FY22 ₹145 cr |
| CAPEX guidance (FY23) | ₹5 to ₹10 cr normal CAPEX only |