Key Takeaways
- Pre-sales on track, guidance held: H1 FY26 cumulative sales of over ₹15,750 crores are in line with the full-year commitment, but management declined to raise the ₹20,000-21,000 crore target despite the strong first half.
- Mumbai entry validates brand: The maiden launch of The Westpark drove new sales booking of over ₹4,300 crores for the quarter, while super-luxury momentum continued with Dahlias crossing 55% sold on an invitation-only basis.
- Rental income inflection is imminent: Three retail malls and Atrium Place office are receiving occupancy certificates now, setting up a cumulative retail rental exit run rate of ₹450-460 crores by FY27 and office rental commencement from December.
- One-time settlement dents reported PAT: Consolidated PAT of ₹1,171 crores includes a ~₹600 crore Tulsiwadi project settlement charge, partly in other income and exceptional items.
- What to watch next quarter: Goa launch timing (Q3 or Q4), the pace of construction-linked collections ramp in H2, and any update on the Kolkata IT SEZ monetization now about three and a half months away.
Pre-Sales & Launch Pipeline
- H1 delivery: Cumulative sales of over ₹15,750 crores in H1, led by the Mumbai Westpark launch and sustained super-luxury demand. Management is sticking to its FY26 guidance and explicitly declined to overcommit on an upside.
- Dahlias strategy: Over 55% of Dahlias is already sold on an invitation-only basis. The main sales push begins after the experience center opens post-April, at which point price points will substantially increase. One more invitation tranche is planned in Q4 FY26 before the formal Q1 FY27 launch.
- Goa launch: All approvals are in hand; a court case unrelated to DLF is ongoing in Goa. The company is launch-ready and hopes to bring the project in Q3 FY26, otherwise definitely in Q4.
- Next 18-month pipeline: Goa, Arbour Senior Living, one round of Privana, one round of Hamilton 2, the next phase of The Westpark, and Panchkula are lined up. Exact timing depends on approval cycles and underlying demand.
- IREO land parcel: Not expected in FY27; possibly toward the end of it or within the next 18 months. Final licensing and other prerequisites are still in process.
- Long-cycle mindset: Management emphasized it does not pitchfork itself into optimizing any single quarter on the development side, calling it a long-cycle business where launch timing is a function of readiness, not quarterly pressure.
Tyagi: "We are a business which frankly does not pitchfork ourselves disproportionately on the Devco side into how a particular quarter is looking or not looking frankly. It is a long cycle business."
Collections & Cash Generation
- Q2 collections: ₹2,672 crores, in line with demands raised based on construction and payment milestones. This excludes approximately ₹240 crores of JV collections for The Westpark. Collection efficiency remains extremely high across all launch projects.
- H2 trajectory: Collections are payment-linked and dependent on construction milestones. As construction progresses, an uptick is expected in H2 FY26.
- Next-year outlook: Management indicated collections of ₹13,000-14,000 crores broadly going forward for next year.
- Surplus cash potential: As of September 30, 2025, surplus cash potential stood at over ₹44,000 crores, with gross margin potential at over ₹40,000 crores. Focus areas beyond pre-sales remain gross margins and surplus cash generation.
- DLF-level debt: The stated endeavor is to bring DLF-level gross debt to zero.
- Dividend growth: ₹1,485 crores of dividend paid in the quarter, implying ₹6 per share, a 20% year-over-year increase, consistent with the strategy of higher shareholder returns.
Rental & Annuity Business
- Operational portfolio: 4.9 crore square feet, with value-based occupancy at around 96% and area-based at almost 94%. Non-SEZ office is over 98% occupied; retail continues at 97-98%.
- DCCDL performance: Rental income grew 15% YoY to ₹1,362 crores; PAT grew 23% for the same period. Net debt stood at ₹17,335 crores with net debt-to-EBITDA at 3.1x on an annualized basis.
- Atrium Place ramp: Occupancy certificate received for 0.21 crore sq ft out of the total 0.32 crore sq ft development. Rental income from this portion is expected to start from December. For all three towers together, income is expected by about April next year. The remaining 0.11 crore sq ft under construction is slated for completion by May/June next year, already leased, with rentals starting 6-7 months after handover.
- Retail mall inflection: Three retail assets are nearing income commencement. Midtown Plaza OC has been received (85% pre-leased); Summit Plaza OC is expected this quarter; Promenade Goa OC is expected in Q4. After OC, typically 4-5 months for tenant fit-outs before income starts. Cumulative rental income for the three malls is expected at about ₹400 odd crores plus ₹60 crores for Summit Plaza, implying an exit run rate of ₹450-460 crores in FY27.
- Next CAPEX assets: DLF Limited will begin identifying potential assets to take on once the three plazas are commissioned, with serious work possibly beginning by early next year. The five-year projection in the analyst presentation lays out some of those assets.
- DCCDL REIT: Not on the table for at least the next three years. Timing and form will be driven by what partners want; DLF is not in any hurry to monetize. If the partner wants a public way out at some stage, DLF will honor their wishes.
Tyagi: "REITs are looking good today. They were looking bad nine months back. Who knows what the situation is in 18 months down the line."
Construction & Execution
- Construction ramp-up: Construction is witnessing a ramp-up, leading to an increase in outflow for construction expenses to ₹925 crores in the quarter. The main focus right now is strengthening construction capabilities to ensure customer commitments stay on track.
- Gurgaon Downtown: Expected to complete by mid-2028.
- Chennai Downtown: Construction finish by beginning of 2028.
- Kolkata IT SEZ: State government approval and development commissioner go-ahead have been received. The matter now goes to the board of approvals for final approval, then another round for de-notification. Monetization is about three and a half months away. A delay benefit of ₹2.5 crores per month has been accumulating since August.
- Cancellations as upgrades: What appears as cancellations are actually customers upgrading to larger apartments as product evolves and handovers start. DLF takes back the released stock and sells it at present price points. Management characterized this as minor in the context of ₹16,000 crores of sales.
Tyagi: "We do not create any artificial impediments in retaining him with any unnecessary encumbrances... we do not use the contract to basically, as I said, we will obviously recover the unnecessary deposit, etc., But we do not like to unnecessarily keep the customers artificially encumbered because of contract."
Brand, Demand & Market Position
- Demand resilience: Management does not see a slowdown in demand for DLF. The brand is strong and has become a good source of investment. Top equity brokers have invested in super-luxury real estate, which management views as validation of the residential business.
- Mumbai entry: The successful maiden launch of The Westpark was extremely well received. The company is now preparing for its phase-II launch in Mumbai and will pursue other opportunities as they arise.
- Noida intent: DLF is prepared for Noida and wants to secure a reasonably clean deal before getting involved.
- Dahlias pricing: Per sq ft is now over a lakh; on carpet, about 1.25 to 1.50 depending on location, comparable to Camellias pricing.
Ohri: "I am happy to tell you that the top equity brokers have also invested in the super luxury real estate today. So, I think that itself is a fantastic validation of what the residential business is doing today of DLF."
Balance Sheet & Credit Profile
- Credit rating upgrade: CRISIL upgraded DLF Limited to AA+ with a Stable Outlook, reflecting strong balance sheet, healthy cash flow generation, and sustained business performance.
- Tulsiwadi settlement: A one-time impact of approximately ₹600 crores was booked on account of the Tulsiwadi project settlement entered into in July of the previous quarter. This has been accounted partly in other income and exceptional items.
- DCCDL ESG recognition: DCCDL was awarded a Five-Star Rating by GRESB for its ESG initiatives and named Global Sector Leader in the space.
- Disclosure commitments: Management agreed to provide a one-pager on Atrium Place operating performance from the quarter ending March, and to disclose Westpark details separately including collections and construction spend.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY26 pre-sales | ₹20,000-21,000 crores; H1 at over ₹15,750 crores is in line | FY26 full year |
| Goa launch | Launch-ready; hopes to bring in Q3, otherwise Q4 | Q3 or Q4 FY26 |
| Dahlias next invitation tranche | One more invitation round before formal launch | Q4 FY26 |
| Dahlias formal next-phase launch | Post experience center opening; price points to rise substantially | Q1 FY27 |
| Atrium Place rental start (first tower) | 0.21 crore sq ft with OC; income from December | December 2025 |
| Atrium Place all-tower rental start | All three towers together | ~April 2026 |
| Atrium Place remaining tower completion | 0.11 crore sq ft under construction, already leased | May/June 2026 |
| Retail mall rental exit run rate | ₹450-460 crores cumulative for three malls | FY27 exit |
| Kolkata IT SEZ monetization | Approvals in final stages; delay benefit accumulating | ~3.5 months |
| DLF-level gross debt | Endeavor to reach zero | No date; working toward it |
| Gurgaon Downtown completion | Construction finish | Mid-2028 |
| Chennai Downtown completion | Construction finish | Beginning of 2028 |
| Total launch pipeline | ₹1,15,000 crores over 4-5 years; ₹48,000 crores already launched | Next 2-3 years for remaining |
| DCCDL REIT | Not looking at anything serious | At least 3 years |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| New sales bookings | Over ₹4,300 cr, led by maiden Mumbai launch, The Westpark |
| Cumulative H1 FY26 sales bookings | Over ₹15,750 cr, in line with full-year guidance |
| Collections | ₹2,672 cr, excludes JV collections of approx ₹240 cr for The Westpark |
| Consolidated revenue | ₹2,262 cr, includes one-time impact of approx ₹600 cr from Tulsiwadi settlement |
| Consolidated EBITDA | ₹902 cr |
| Consolidated PAT | ₹1,171 cr, includes one-time impact of approx ₹600 cr from Tulsiwadi settlement |
| Gross margin potential | Over ₹40,000 cr, as on September 30, 2025 |
| Surplus cash potential | Over ₹44,000 cr, as on September 30, 2025 |
| Overall gross cash balance | Over ₹9,200 cr, of which approx ₹8,350 cr in RERA accounts |
| Outstanding debt | ₹1,487 cr, after repaying ₹963 cr in the quarter |
| Dividend paid | ₹1,485 cr, ₹6 per share, 20% growth YoY |
| DCCDL rental income | ₹1,362 cr, 15% growth YoY |
| DCCDL PAT growth | 23% YoY |
| DCCDL net debt | ₹17,335 cr, net debt-to-EBITDA at 3.1x annualized |
| Operational rental portfolio occupancy (value basis) | Around 96%; area basis almost 94% |
| Non-SEZ office occupancy | Over 98% |
| Retail occupancy | 97%-98% |
| Dahlias cumulative sales | Over 55% sold; 18 units sold in Q2, 221 units cumulative |
| Dahlias per sq ft realization | Over ₹1 lakh per sq ft; on carpet approx ₹1.25-1.50 lakh depending on location |
| Atrium Place pre-leasing | 93% for 0.31 cr sq ft |
| Midtown Plaza pre-leasing | 85% |
| Atrium Place gross rental income potential | ₹600-650 cr, when all four towers fully rented |
| Cumulative rental income for three malls | ₹450-460 cr, including established Summit Plaza |
| Atrium Place total cost | About ₹17,000 per sq ft, including land, approvals, construction, capitalized interest |
| Construction expense outflow | ₹925 cr, reflecting ramp-up in construction activity |
| Total launch roadmap | ₹1,15,000 cr over next four to five years; ₹48,000 cr already launched between last year and this year |
| Gurgaon Downtown completion timeline | Mid-2028, total development of about 0.75 cr sq ft |
| Chennai Downtown completion timeline | Beginning of 2028, Towers 4 and 5 ahead of Gurgaon by six to eight months |