The CAPEX Cycle: Deployment, Selling, and the Next Leg

Tarun Dua: "In an ideal world, like we would like to end another \$100 million or about Rs.800 crores over the next 12 months."

Business Model & Competitive Moat

Tarun Dua: "That was not how we look at our business, we look at our business as a technology business, very focused on figuring out the various industry solutions. And over there eventually like, the asset turn doesn't matter, because it's like, very, very capability and technology and software driven business and it's not about being the cheapest on the market. It's about creating enough value for the customers."

AI/ML Platform & Technology Build-Out

Tarun Dua: "Now, which means that like earlier you were designing your storage and network and your entire internal bandwidth infrastructure for being able to process like very small amounts of data. Now you actually are building for like being able to handle like 20x, 100x or maybe even 1000 times the amount of the data in motion to be able to process it on like very fast, high speed, GPU processes."

Facility Transition & the Outage

Tarun Dua: "I would like to point out that, in case that the third party vendor had trained their processes better, we could have avoided a world of pain for us and for our customers, by putting up the power only after the UPS was charged, instead of trying to bring it up couple of times, which damaged some of our equipment."

Chip Supply & Industry Demand

Tarun Dua: "There is always going to be some queue. But it's not going to be the longest queue that we have seen in the past of that type okay, like we are looking at 52 weeks, 56 weeks, 60 weeks and so on. That is not going to be the future."

Financial Structure & Cost Dynamics


Guidance & Commitments

CommitmentSpecificsTimeline
MRR from current capacityAchieve ₹14-16 crore monthly recurring revenueNext couple of months
Growth rateGrow at higher than industry averageNext couple of years
CAPEX deployment ambitionDeploy another ~\$100 million (~₹800 crore)Next 12 months (ideal-world scenario)
Equity fundraiseComplete an equity raise as part of CAPEX funding mixNext couple of quarters
Customer migrationMigrate all customers from older facility to new facility without disruptionNext couple of years
Enterprise customer expansionExpand universe to include workloads from larger enterprisesNear future
International expansionBegin focusing on Southeast Asian market, alongside EMEA and USNot specified

Key Metrics

MetricQ4 FY24
Revenue from operations₹29 crore, +67% YoY
EBITDA₹15 crore, +68% YoY
Net profit₹4 crore, +39% YoY
FY24 revenue from operations₹95 crore, +43% YoY
FY24 EBITDA₹48 crore, +45% YoY
FY24 net profit₹22 crore, +121% YoY
FY24 CAPEX₹185 crore, vs ₹35 crore in FY23
MRR potential from current capacity₹14-16 crore over next couple of months
Ideal CAPEX plan for next 12 months~$100 million or ~₹800 crore
Asset turn lower bound0.55 to 0.6
Team size~140 to 150 people
Active customers~3,000
Depreciation methodChanged from WDV to straight line from April 2023