Eldeco Housing & Industries Ltd Q1 FY2026 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/w3ngdec64vlw6d7ia895uvjs.pdf

Key Takeaways


The Launch Unlock & Booking Surge

Pankaj Bajaj: "It is not something which has changed suddenly. It was just that we have not been able to launch significantly in the last some quarters. But now, that has got unlocked."

Margin Mechanics: The 17.6% Quarter

Pankaj Bajaj: "We will go back to that when we start recognizing revenue in a big way. Right now we are recognizing revenue only for scattered inventory and expensing many of the costs as period expenses. So, it looks pretty low, but actually they are in the range of 30%-40%, this will start coming soon."

Revenue Recognition: The Three-to-Four-Year Lag

Pankaj Bajaj: "Generally, it happens that your booking numbers start translating into your revenue recognition with a lag of three to four years."

Lucknow Concentration & Market Opportunity

Pankaj Bajaj: "I think not because of lack of demand, it is because of lack of proper supply. But as supply is getting de-bottlenecked, I expect the market size to expand sharply."

Bareilly Unwinding & Capital Recovery

Pankaj Bajaj: "We had a floor return and then we had unlimited upside. That upside did not come through."

Disclosure & Transparency Gaps


Guidance & Commitments

CommitmentSpecificsTimeline
Construction cost ramp-upExecution cost to rise gradually from ₹30 Cr/quarter to ₹50-60 Cr/quarterBy end of FY26
Imperia Phase-II revenue recognitionApply for completion certificate, then offer possessions, triggering revenue recognitionQ3/Q4 FY26
Solano Gardens Phase-I launchPlots and villas with ₹300-400 Cr GDVWithin FY26
Trinity relaunchRelaunch with show home ready, expecting much better numbersNext quarter or so
Bareilly transaction unwindingGet money back with minimum committed returnNext couple of quarters
Related party loan recoveryLoan to get unboundNext couple of quarters
EBITDA margin normalizationReturn to 30-40% range when core project revenue recognition beginsWhen revenue recognition starts in a big way
Trinity project completionCompletion timeline revisedFrom Jan'27 to Jan'28

Key Metrics

MetricQ1 FY26
Booking value₹221 cr, +274% YoY
Collections₹78 cr, +41% YoY
Construction expenditure₹39.3 cr, +10% YoY
Revenue₹12.3 cr (per an analyst's math), recognized largely from scattered inventory of Regalia, Twin Towers, EWS Saksham, and Eldeco Imperia Phase-I
EBITDA margin17.6%, depressed by mix of EWS/low-income housing revenue recognition and front-ended marketing expenses for Hanging Gardens and Skywalk launches
Weighted average EBITDA margin (normalized)30% to 40%, depending on project mix; Hanging Gardens and Skywalk both in this range
Deliveries~85,000 sq ft, comprising 101 homes handed over, mostly EWS and smaller homes
Average realization~₹6,500 per sq ft, up from ₹3,500 in FY20 and ₹4,500 in FY23; management views this as the new normal
Eldeco Hanging Gardens inventory sold~84% within a week of launch on 15 April 2025
Eldeco Solano Garden GDVOver ₹1,000 cr, spread over 50 acres; first phase (plots and villas) GDV of ₹300-400 cr expected within FY26
Lucknow market shareLess than 10% of an estimated ₹5,000 cr annual market
Land bank for forthcoming projects~35 acres under aggregation across three locations
Construction cost guidance (quarterly run-rate)₹50-60 cr expected by end of FY26, ramping from ₹30 cr in Q1
Imperia Phase II value of area booked reduction₹275 cr (from ₹299 cr earlier), a reduction of ~₹25 cr or ~10% due to cancellations from chronic defaulters