Ellenbarrie Industrial Gases Ltd Guidance Report - SOIC x StockScans Report

as of Nov 2026

  1. BHEL 1,200 TPD ASU contract - executed over eight quarters, commissioned FY29 On track - At the Q2 FY27 call, management said the ₹480 crore BHEL contract (design, engineering, supply, erection, commissioning and handover of a 1,200 TPD cryogenic ASU in Odisha) will be executed over eight quarters, with commissioning expected in FY29. The ₹480.7 crore order was awarded towards the end of September 2026, with quarter 1 of execution being Q3 FY27 and more revenue to be booked in quarters 5 to 8.
  2. Net-cash balance sheet - preserve for capex flexibility Delivered - At the Q4 FY26 PPT, management stated a strategic objective to preserve a net-cash balance sheet for capex flexibility, reiterated in the Q1 and Q2 FY27 PPTs. Net cash stood at ₹355 crore in Q3 FY26 and cash & equivalents were ₹469.4 crore at FY26 end, ₹424 crore as on 30 September 2026, with Net Debt/Equity 0.03.
  3. ROCE >15% - strategic objective for organic projects Delivered - At the Q4 FY26 PPT, management stated the objective of reinvesting in high-return organic projects with ROCE >15%, reiterated across Q1 and Q2 FY27 and in the FY26 annual report. FY26 ROCE was 15.4% excluding cash and investments, and Q2 FY27 annualised ROCE was 17%.
  4. Specialty gases - a few more solar/speciality contracts in coming quarters Delivered - At the Q3 FY26 call, management expected "a few more contracts" in solar/speciality gases to be concluded "in the coming quarters", with a couple of solar companies already signed. The FY26 annual report discloses multiple contracts secured in the solar segment supplying Nitrogen, Oxygen and Silane at 99.9999% purity, and Q2 FY27 outlined a central India plan offering four to five solar gases.
  5. Western India expansion - announcement expected "fairly soon" On track - At the Q1 FY26 call, management said it was actively looking at expansion into Western India and "you should expect an announcement from us fairly soon", at drawing-board stage. The plan evolved into two merchant plants of about 450 to 500 tons combined, construction on the West plant started by Q1 FY27, and both plants are now expected online around the middle of next financial year with revenue in H2 FY28.
  6. Revenue growth - \~25% YoY annual growth for next 2-3 years On track - At the Q1 FY26 call, management guided \~25% year-on-year annual revenue growth over the next two to three years, later reset to a 20-25% CAGR in the core gases segment over four to five years, and to 20% core gases CAGR. FY26 core gases revenue grew 14.2% and total revenue 9.3%, but Q1 FY27 core growth was 20% YoY, Q2 FY27 \~27%, and H1 FY27 revenue from operations up 23% YoY.
  7. EBITDA margin - maintain \~37% with potential upside Partial - At the Q1 FY26 call, management guided to at least maintain the \~37% EBITDA margin, with the target later raised to \~40% in the medium to long term across Q2 FY26 through Q2 FY27. Margins were 37% in Q1 FY26 and 38% in Q2 FY26, then fell to 31% in Q3 FY26 and \~30% in Q4 FY26, closing FY26 at 34%, before recovering to 39% in Q1 FY27 and 36% consolidated in Q2 FY27 with the gases segment at 39%.
  8. Capex - ₹250 crore over next 1.5 years (FY26-FY27) Pending - At the Q1 FY26 call, management committed to spend around ₹250 crores of capex over the next 1.5 years (CWIP \~₹52 crores), later restated as ₹250 crore for FY27 and ₹200 crore for FY28. The Uluberia-II 220 TPD ASU had utilised ₹62.36 crore against an ₹88.83 crore estimate by Fiscal 2026, with the balance to follow in the subsequent fiscal, and no FY26 full-year capex actual is disclosed against the ₹250 crore target.
  9. Company capacity - 1,910 TPD by end of FY26, 2,130 TPD in FY27 Partial - At the Q1 FY26 call, management guided company capacity from 1,370 tons per day at FY25 end to 1,910 tons per day by end of FY26 and 2,130 tons per day in FY27. FY26 end capacity was 1,609 TPD (Bulk 911 + Onsite 698) against the 1,910 TPD guided, and as of 30 September 2026 total stood at 1,933 TPD (Bulk 915 + Onsite 1,018), short of the FY27 target.
  10. Argon revenue - reach \~15%+ of total gas revenue On track - At the Q1 FY26 call, management guided Argon revenue to reach "somewhere in the region of about 15 odd percent... 15% plus" of total gas revenue when all new capacity kicks in, later refined to a mid-teens 14-16% contribution. Argon ran at 9-13% through FY26 (10% for the full year) and 10% in Q1 FY27, before reaching 16% in Q2 FY27.
  11. North India merchant plant (220 TPD) - operational by end of Q1 FY27 On track - At the Q1 FY26 call, management guided a merchant plant in North India to be up and running by end of Q1 FY27, subsequently pushed to H2 FY27, then FY27, and finally to around the middle of the next financial year with revenue in H2 FY28. As of Q2 FY27 the 220 TPD plant is not yet operational, with postponement of about one year to H2 FY28 mainly due to land allotment and statutory approvals.
  12. East India on-site plant (Forest Steel Mill / Durgapur, 320 TPD) - commissioned by March 2026 Partial - At the Q1 FY26 call, management guided the 320 tons per day Forest Steel Mill on-site plant to commence operation in March 2026, moved to Q1 FY27 at the Q3 FY26 call, then to "next month" and an August 2026 start. The 320 TPD Durgapur plant was commissioned in September 2026 with commercial operations and revenue starting that month, under a 15-year take-or-pay agreement, with a full-quarter benefit expected from Q3 FY27.
  13. IPO object - repayment/prepayment of borrowings ₹210 crore Delivered - The IPO prospectus listed repayment/prepayment of certain outstanding borrowings at an original cost of ₹2,100.00 million as an object, with no revision. In the first week of July 2025, the company repaid about ₹210 crores of borrowings, most of it long-term, from proceeds received that week; debt now stands at ₹184 cr with D/E 0.19.
  14. East India merchant plant (Uluberia 2, 220 TPD) - commissioned by end of November 2025 Partial - At the Q1 FY26 call, management guided the East India merchant plant to commence operation in October 2025, revised at the Q2 FY26 call to end of November 2025 with about a one-month delay acknowledged. The 220 TPD Uluberia 2 plant in West Bengal was commissioned in Q4 FY26, roughly one quarter late, with ramp-up continuing through Q1 and Q2 FY27.