EMS Ltd Q2 FY2025 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/d8szbf3qpulkm2314zdx2xaa.pdf

Key Takeaways


Margin & Financial Performance

Tomar: "So, I think we are confident of maintaining this going forward."

Demand Environment & Order Pipeline


Order Book & Project Execution


Water Sector & Diversification

Tomar: "I think there is a huge scope for water business going forward in the country and we have already been maintaining this mix of executing works in other infrastructure sectors of 20% to 30% year on year since the start."

Land Acquisition & Other Corporate Actions

Tomar: "We have been maintaining that we are only going after the land part and we are not interested in running any industry."

Guidance & Commitments

CommitmentSpecificsTimeline
EBITDA marginMaintain ~29% with 1–2% fluctuation bandGoing forward
Revenue trajectoryMaintain and improve upon past CAGR performanceOngoing
Cash flowMaintain and improve positive cash flow from operationsOngoing
Order book executionMajority of ₹2,350 crores order book completedComing 2 years
Pipeline conversionResults for majority of ₹6,400+ crores bid pipeline declaredComing 2–3 months
Business mixMaintain 70–80% water, 20–30% other infrastructureYear on year
Land acquisitionClose NCLT deal; incorporate if acquired by MarchBy end of March (conditional)

Key Metrics

MetricQ2 FY25
Revenue growth (standalone)closer to 20% YoY
Revenue growth (consolidated)~10.9% / 11% YoY
EBITDA growth (consolidated)~9% YoY
EBITDA margin~29%-30%
Un-executed order book~₹2,345 cr, including ~₹170 cr O&M contracts
Bid pipeline~₹6,470 cr
New order win (Q2)~₹700 cr, Kolkata Municipal Corporation sewerage scheme
L1 status (post-Q2)~₹700 cr, Kolkata Municipal Corporation
HAM project in bid pipeline~₹2,200 cr
Typical project size₹200 cr to ₹500 cr, covers ~90% of projects
H1/H2 revenue split37%-40% H1, 60%-63% H2
Building sector project under execution~₹320 cr, RBI housing colony, Navi Mumbai
Power distribution project secured (FY25)~₹140 cr, Uttarakhand
Disputed debtor (as on 31 Mar 2024)₹34 cr, arbitration awarded in company's favour
Retention from customers (as on 31 Mar 2024)₹141 cr