Ecosis: Timeline, Approvals & Ramp-Up

Kapil Kumra: "Any of these customers has the capacity to take over the entire 27,000 tons of production. Their requirements are -- the people we have talked about, the Decathlon, H&M, IKEA, A&E, they are market leaders, number 1 or number 2 in their particular..."

Core Business: Margin Triggers & Profitability

Madhu Sudhan Bhageria: " I never said the percentage-wise, it will be same. The number -- total number-wise, it will be similar. So we might not go to 14%, 15%. We might go to 11%, 12%, but the volumes have increased and with Ecosis coming in place, steam project coming in place, everything, this will help us in surpassing that target as a total number."

Steam, Automation & Renewable Energy


Brownfield, Volume & the Demand Environment


Ecosis Economics & the T2T Demand Picture

Madhu Sudhan Bhageria: "Recycled polymer is not a premium over the virgin. It has its own price base and it works on that. Even if the prices of the virgin fall, I don't think there will be significant fall in the recycled."

Expansion, Trade Policy & Competitive Positioning

Madhu Sudhan Bhageria: " They buy a lot of fabrics and yarns from China and then do the job work and send it. So they were thriving on the basically custom duty difference, which goes away, I think it will be difficult for them to sustain that kind of export."

Guidance & Commitments

ComitmentSecificsTimline
Dahej brownfield completionRemaining FDY extruder lines commissioned23 November 2026
Eosis polymerization startPolymerization to beginLatst by first week of December 2026
Eosis first commercial productFirst commercial product shipped10–15 December 2026
Eosis Q4 FY27 utilization40–50% capacity utilization, EBITD-positiveQ4 FY27
Eosis full productionFull production achievedMid-FY28
Eosis FY28 EBITDMinimum ₹85–90 croresFY28
Stem supply start22–24 tons per hour to customers20 November 2026
Stem full capacityFull 65 tons per hourJanuary-end 2027
Stem EBITD gain₹60–65 crores reducing conversion costVisible from Q4 FY27
Atomation second partSemi-dull section fully commissionedMid-December 2026
Rnewable energyPower supply commencesMid-January 2027
Brwnfield FY28 target₹400 croresFY28
Nw Ecosis capacitiesTwo plants of 150,000 tons each (India + Vietnam)Q1 calendar 2029
Core business per-kg profitability₹10–12 per kgOnging

Key Metrics

MetricQ2 FY27
Revenue₹1,304 cr, +21.2% YoY and +13.9% QoQ
EBITDA₹91.03 cr, +2.4% YoY and +16.8% QoQ
PAT₹53.48 cr, +12.4% YoY and +8.8% QoQ
EBITDA per kg₹9.79, +11.6% YoY and +13% QoQ
Sales volume92,998 metric tons, -8.3% YoY and +3.5% QoQ
Core business per kg profitability target₹10 to ₹12 (FY28 expectation)
Comprehensive capex program₹690 cr, in final stage
Dahej expansion capacity~55,000 tons annual, across POY, FDY, DTY; 67% commissioned, balance FDY lines by 23 Nov 2026
Ecosis project capacity~27,000 tons annual, ₹300 cr capex; depolymerization and purification started 15 Nov, polymerization expected first week of Dec
Ecosis volume commitments7,000 to 8,000 tons from Decathlon, A&E, IKEA and others combined
Ecosis expected utilization Q4 FY2740% to 50%; full production by mid-FY28
Ecosis EBITDA guidance FY28₹85–90 cr minimum
Ecosis chip margin expectation₹30–35 per kg
Steam distribution project42 tons offtake signed; 22–24 tons from 20 Nov, full 65 tons per hour by Jan end; stated EBITDA gain ₹60–65 cr
Renewable energy program₹30 cr capex; captive renewable share to increase from ~26% to 55%, power supply expected mid-Jan 2027
GAIL PTA plant commissioning0.12 cr tons per annum, commissioned 5 Nov 2026; Indian Oil PTA likely Apr 2027; combined capacity 0.25 cr tons vs India imports of ~0.22 cr tons