Key Takeaways
- Muted quarter, copper-driven disruption: Revenue grew only ~2% YoY as extreme copper price swings (~20% intra-quarter) froze channel orders and forced price cuts of ~10%, compressing electrical cable margins.
- E-beam facility nears commercial launch: Both accelerators are installed, commissioned, and trial production quality exceeds standards; only AERB consent to operate stands between Finolex and a new ~₹200 cr incremental revenue stream.
- OFC margins have a floor, recovery path set: Optic fiber volumes rose ~10% but realizations remain depressed industry-wide; management targets a return to double-digit margins (from roughly half that today) over two steps, contingent on volume recovery.
- FMEG approaching breakeven: The new-products segment (fans, water heaters, appliances, conduit pipes) showed healthy volume and value growth; at the current quarterly run rate of ~₹68 cr, the business is near breakeven barring blips.
- What to watch next quarter: Whether AERB grants consent to operate the E-beam facility, the outcome of BharatNet Phase 3 price bids (expected by end-September), and any stabilization in copper prices that unfreezes channel inventory.
Copper & Commodity Headwinds
- Price swing paralyzed the channel: Copper swung ~20% within the quarter, peaking before tumbling; in April and May, unsatisfied demand built large channel stocks, and when prices fell, orders froze as distributors sat on higher-cost inventory.
- Price cuts hit in June: Management acknowledged price reductions of about 10% from June onward, which pressured electrical cable margins; the segment posted turnover of ₹1,031 cr with margin slightly over 11%, down from ₹1,200 cr in the preceding quarter.
- Recovery conditional on copper stability: If copper sustains around March average levels (~$8,800), management expects conditions to improve; yesterday copper was at roughly that level, but the recent history of false bottoms tempers conviction.
Viswanathan: "I had explained the reasons why prices were going up at that point in time, but I had also said, not very sure how long this would last. And, well, within a couple of weeks after I said that the price has bottomed out. It has still not."
E-Beam Facility: The Next Growth Vector
- Facility ready, awaiting regulatory green light: Both accelerators are installed and commissioned at the new E-beam facility; trial production has been completed and quality far exceeds standard requirements. An inspection by the Atomic Energy Regulatory Board has been called; consent to operate is the final gate before commercial sales begin.
- Product roadmap sequenced by approval speed: Solar cables will be the first application, targeting a 15-20% market share in a market driven by 50 GW of solar energy targets. Automotive cables are next, with designs under discussion with a few OEMs. Railway cables require RDSO approval and are in the sample-testing phase. Instrumentation cables will come last.
- Revenue and asset-turn math: Management estimates incremental full-year revenue of ~₹200 cr once the facility ramps, likely starting in Fiscal '26. The initial asset turn is pegged at ~2x, scaling to 4-5x over time. EBITDA margins are still being worked out.
- Competitive positioning in solar: The solar cable market is served by both chemical-process and irradiation-process products; the chemical route is less environment-friendly. Competitors include Polycab, APAR, and possibly Universal Cables and Vindhya Tele. Finolex has not yet released its solar cable product into the market.
Optic Fiber: Depressed Prices, Volume Waiting on Policy
- Industry stuck in a demand drought: No major fiber rollout has materialized; telecom players completed technical 5G rollouts over a year ago but have consumed little fiber since. BSNL has bought nothing of significance in the last year. Most players are running suboptimal capacities, and that oversupply is reflected in prices.
- Finolex's own utilization split: The Goa factory is running full on orders from Bharti; the Urse (Pune) facility still has available capacity. A new factory building has been constructed to house additional machines but will not be populated until BSNL tender results provide demand visibility.
- Margin recovery is a two-step journey: OFC margins were once 9-10% but have roughly halved. Management aims to regain double digits, acknowledging it may take two steps rather than one; if volumes return, the target is achievable by FY26 or FY27.
- Preform plant for backward integration: A preform plant is being set up to gain control over fiber raw material, with capacity equivalent to 0.4 cr km of fiber; it should be operational by December or January at the latest.
- BharatNet Phase 3 as a catalyst: Finolex participated through a consortium; technical bids are opened, and price bids are expected to be opened by end-September after evaluation of 21-22 bids. Other states are yet to come up for their piece of the third phase, and the total opportunity is expected to be as big if not slightly bigger than earlier phases.
Viswanathan: "Yes, if you went back a few years ago, we were close to double digits. We were about 9% or 10%. The aim is to reach there. We may not be able to reach there in one go. It might take two steps before we reach there. But definitely double of where we are today."
EHV & Infrastructure: Opportunity Meets Funding Reality
- EHV JV now tender-ready: The factory is functional and the business has cleared the long gestation period for certifications; it is now qualified for a substantial portion of utilities and can participate in roughly 7 out of 10 tenders floated.
- Revenue target and breakeven: The target for this year is ₹240 cr, up from approximately ₹130 cr last year. Breakeven for the JV is pegged at around ₹230-240 cr.
- The real bottleneck is utility funding: Projects get announced with six-month or one-year timelines but routinely push out to multiple years because money flow is not smooth. Utilities are funded through REC or Power Finance Corporation, but not all are rated equally, and the funding constraint is true for most infrastructure projects in India.
Viswanathan: "The difficulty so far has been in the utilities being able to fund themselves, to be able to handle all these CAPEXs and that is where the project gets announced today. You expect it to be done in six months or one year, but then it pushes over to a couple of years because money flow is still not as smooth."
Capex & Capacity Build-Out
- Overall envelope unchanged: Total capex outflow until next year remains ~₹500 cr, with the bulk being spent this year; no change from the plan shared last quarter.
- Auto cable expansion at Roorkee: Equipment is landing imminently; the facility is expected to be ready by mid-October to mid-November, with trial production hoped for by December or January at the latest.
- Goa compounding plant: Permissions to construct have been obtained from local bodies; the tendering process is on for finalizing a contractor; the plant is expected to be operational by May or June next year.
- OFC capacity expansion on hold: Plans exist to double fiber draw capacity from 0.4 cr km to 0.8 cr km over two stages, but the decision to populate the new factory building with machines waits on BSNL tender outcomes.
Segment & Margin Snapshot
| Segment | Trend | Commentary |
|---|---|---|
| Electrical Cables | ▼ Margin pressure | Turnover ₹1,031 cr (vs ₹1,200 cr QoQ); margin slightly over 11%; price cuts of ~10% from June onward compressed profitability. |
| Communication Cables (Metal) | ▼ Soft | Coaxial and LAN cables hit by the same metal price pressure as electrical cables. |
| Optic Fiber Cables | ▬ Volume up, price down | Volumes up ~10% but realizations remain low due to global fiber price weakness; margins roughly half of historical double-digit levels. |
| FMEG & New Products | ▲ Healthy growth | Fans, water heaters, appliances, and conduit pipes showed strong volume and value growth; LED lights had good volume but continued price erosion. At ~₹68 cr quarterly run rate, the segment is near breakeven. |
| EHV JV | ▲ Ramping | Revenue target ₹240 cr for FY25, up from ~₹130 cr last year; breakeven at ₹230-240 cr; now qualified for most utility tenders. |
- Long-term margin guide: Excluding dividends from the associate, investors should work with an EBITDA margin of 13-13.5% over the long term.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| E-beam commercial launch | Consent to operate from AERB; solar cables first product to market | Inspection called; hoped within this quarter |
| E-beam incremental revenue | ~₹200 cr full-year revenue | Starting Fiscal '26 |
| Auto cable trial production | Roorkee facility ready; trial production begins | December or January at latest |
| Goa compounding plant operational | Contractor being finalized; construction to follow | May/June next year |
| Preform plant operational | Backward integration for OFC raw material | December or January at latest |
| OFC margin recovery | Return to double-digit margins (9-10%), from roughly half that today | FY26 or FY27, contingent on volume recovery |
| EHV JV breakeven | At ~₹230-240 cr revenue | Implicit in FY25 target of ₹240 cr |
| FMEG breakeven | At current quarterly run rate of ~₹68 cr (annualized ~₹250+ cr) | Near-term, barring blips |
| BharatNet Phase 3 price bid outcome | Consortium bid submitted; price bids to be opened | End of September, after technical evaluation |
| Long-term EBITDA margin | 13-13.5% excluding dividends from associate | Ongoing |
Key Metrics
| Metric | Q1 FY25 |
|---|---|
| Revenue | ₹1,031 cr (electrical cables), +2% YoY and -14% QoQ |
| Overall company margin | ~13% |
| Electrical cables segment margin | Slightly over 11% |
| Profit after tax | ₹122 cr, down from ₹132 cr YoY and ₹146 cr QoQ |
| Communication cables — optic fiber volume growth | ~10% YoY |
| FMEG quarterly revenue | ₹68 cr, annualized run-rate above ₹250 cr breakeven threshold |
| EHV segment revenue (FY24) | ~₹130 cr (or ₹123 cr) |
| EHV segment target (FY25) | ₹240 cr |
| EHV order book | Close to ₹300 cr |
| OFC market share | ~13%–14% |
| Electrical cables capacity utilization | ~60% |
| Communication cables capacity utilization | ~70% overall (Goa plant full, Urse has spare capacity) |
| Wires vs cables mix — B2C share | ~70% of total electrical segment |
| Price cuts in electrical wires (June to date) | ~10% |
| Copper price range during Q1 | $10,857 high to $8,809 low on LME, ~20% swing |
| Fiber price (current) | ~$4, down from $5.5 earlier |
| Overall CAPEX spend (till next year) | ~₹500 cr, bulk in FY25 |
| E-beam CAPEX | Slightly under ₹100 cr |
| E-beam incremental revenue expectation | ~₹200 cr, starting FY26 |
| BharatNet tender — cable portion revenue potential | ~₹450 cr (10% of ₹50,000–55,000 cr total spend) |
| BharatNet additional annual revenue potential (at ~50% hit rate) | ₹250–300 cr per year over current ~₹550 cr run rate |