Key Takeaways
- Normalized quarter after Q1 noise: PAT jumped 59% QoQ to ₹67 crores and EBITDA margin recovered to 80.7%, simply because Q1 carried a high-cost-basis land sale and a onetime tax charge.
- Million Minds leasing hit escape velocity: Tower 1 reached 68.4% let across 15 deals, rents rose with every cohort to above ₹122 per sq ft, and the fully-let rental estimate was revised up 20% to ₹84 crores.
- Malabar Retreat is the H2 bridge to guidance: The project is 87% complete with revenue recognition waiting on Q4 completion; bookings reached ~50% by units but velocity has been slow industry-wide and needs to accelerate.
- Tower 2 is now a live commitment: Plans submitted, Bhumi Pujan set for 24 November, and pre-leasing expected from late 2027, with a conservative target rent of ₹118 per sq ft that management believes could reach ₹130–140.
- What to watch next quarter: Whether Malabar Retreat booking velocity actually picks up post-monsoon as management expects, progress on the Godhavi monetization plan now delayed past September FY27, and the pace of Tower 1’s march to the 90% leased target by March 2027.
Million Minds: The Quarter’s Proof Point
- Leasing inflection: Tower 1 added ~25 percentage points of signed leases this quarter, moving from 43% to 68.4% let, because all previously reported discussions converted into signed deals. The signed book contracted rent roll now stands at ~₹55.7 crores.
- Occupier profile widened decisively: New LOIs with Airtel, Conga Software, Flagler Health, and iBase-t brought telecom, enterprise software, health tech, and aerospace & defense under one roof alongside existing GCCs, hybrid workspace providers, and technology firms.
- Co-working concentration fell: Co-working operators now hold 28.7% of space let, down from ~36% a quarter ago, because all three new deals are direct corporate tenants.
- Rental pricing power visible: Rents rose with every cohort: from ~₹90 for 2025 leases to ~₹115 in 2026 to above ₹122 this quarter; the building average now stands at ₹110.20 per sq ft.
- Fully-let estimate raised 20%: The estimate moved from ₹70 crores to ₹84 crores because the signed book already sits at ~₹56 crores and the potential on full leasing is higher than originally modeled.
- Upper floors held for scale: Management is deliberately holding ~1.95 lakh sq ft across four contiguous upper floors for one or two large tenants rather than piecemeal letting, betting that Vibrant Gujarat meetings in Jan–Feb will close those deals.
- Tower 2 is now a defined asset: Plans for 6.6 lakh sq ft of leasable carpet on ~14.5 lakh sq ft of construction have been submitted for approval; Bhumi Pujan targeted for 24 November; construction timeline is 24–28 months from approval and contractor appointment, putting the tower ready for fit-outs between May and November 2028.
- Combined rental ambition: Two towers together would generate ₹170 crores and above annually at full occupancy, with Tower 2’s conservative target of ~₹118 per sq ft (~₹94 crores annually) likely to come in at ₹130–140 per sq ft.
Ravi: "Three months on, I can tell you that Million Minds has not -- has just stopped being a plan on paper. It is now a place that tenants are walking through and that is the story of this quarter."
Malabar Retreat: The Guidance Bridge with a Velocity Question
- Revenue recognition locked to completion: Under Ind AS 115, revenue can only be recognized on completion; Malabar Retreat is 87% complete and expected to reach completion in Q4 FY27, making it the single largest contributor to H2 guidance.
- Possession timeline firming up: Soft possession for interiors expected by 15 January 2027, with Building Use permit expected by mid-February 2027, roughly six months ahead of RERA timelines that extend to September 2027.
- Booking progress is adequate but slow: Bookings reached almost 50% by units (76 units) and 53% by carpet area, up from 73 units last quarter, with pricing at the top of the micro-market without discounting. However, velocity has been slow across India and Ahmedabad for the last 3–4 quarters, with only premium properties selling.
- Velocity is the open question: About 30–40 units sold in the last four months; the rainy season traditionally slows under-construction project bookings, and management expects walk-ins to increase as the project reaches 90% completion and the look and feel becomes visible.
- Sales target is ambitious: Management expects to sell almost everything by March, or at least reach 75% of sales, implying a significant acceleration from current run-rate.
- Construction S-curve helps: External plastering is ~90% done, plumbing and electrical are 60–70%, and painting has commenced on one tower; the remaining 13% of construction will take much less time than the initial 24 months.
Ravi: "That we are confident of reaching as of now. Hope the government behaves along with us."
FY27 Guidance: Back-End Loaded and Reaffirmed
- Guidance stands despite slow H1: Revenue of ₹1,000–1,200 crores and PAT of ₹300–325 crores reaffirmed; H2 is expected to show much different and better performance because a large part of the income is likely to come in Q3 and Q4.
- H1 was always going to be thin: Q2 revenue of ₹121 crores consisted entirely of project land sales; the YoY decline versus Q2 FY26 (₹174 crores revenue, ₹108 crores PAT) reflects a high base, not deterioration.
- The H2 bridge has three legs: Malabar Retreat completion and revenue recognition in Q4, other pipeline projects, and land sales which are an integral part of the business plan.
- Quarterly lumpiness is structural: Reported quarterly numbers depend on which project reaches completion, because Ind AS 115 permits revenue recognition only on completion; this is not a business-quality issue but a reporting-timing one.
- Growth trajectory ambition: Only this year has seen lower growth than last year; the last four years saw 30–40% growth. Management believes that with projects on ground and rental income fully flowing in, growth should return to those levels in a couple of years.
Ravi: "We do believe with all the projects which we are having on ground executed as well as being executed and the rental income fully flowing in, we should be going back to the growth levels."
The Pipeline Beyond Million Minds
- Million Minds residential Phase 1: Expected launch in Q4 FY27 with roughly 9 lakh sq ft, 334 units across two towers, a GDV of ₹500 crores, and a 2–2.5 year timeline.
- Million Minds SEZ master plan: Planned for ~1.8 crore sq ft across seven office phases alongside residential, retail, and hospitality, targeting ~63,000 jobs at maturity.
- Commercial pocket defined: A mall (~4.5 lakh sq ft), hotel and convention center (~5 lakh sq ft), and service apartments will be built as one connected development, followed later by a members’ clubhouse.
- Godhavi monetization delayed but alive: The 405-acre parcel’s monetization plan, a mix of plotted development, land sales, and project development, was targeted for announcement by September FY27 but has been delayed because certain government announcements got delayed. More clarity is expected in the next six months, with an announcement towards the later part of this year.
- Land bank growing quietly: Fully paid land reserves now stand at 513 acres, including ~405 acres at Godhavi, ~65 acres at Million Minds, and balance parcels in and around Ahmedabad. New parcels, including some exceptionally large ones, are under negotiation or acquisition with partial payments already made and are not included in the 513 acres.
- REIT optionality embedded: Offices and commercial pockets are being built to be held as rental assets, giving the option for a REIT down the line.
Balance Sheet & Market Positioning
- Near-zero debt is a competitive weapon: The balance sheet is almost debt-free, and management frames the rate cycle that squeezes others as room to be selective.
- Leverage will rise but stay disciplined: Management will take a bit of leverage to ensure growth but states it will not match levels ever taken before in terms of ratios. Residential projects are well-funded via bookings and already-paid land; only construction costs need covering. Lease rentals are coming in, and land monetization will bring cash flows.
- Existing lending is non-disruptive: Current lending is against lease rentals that have been discounted, so normal day-to-day cash flow is not impacted by servicing. Remaining lease rental yet to be tied up can be explored for softer long-term loans.
- Residential-commercial flywheel: Profit from residential is ploughed back into construction of commercial projects, creating a self-funding loop on already-owned, fully-paid land.
- Ahmedabad market is resilient but supply-heavy: Housing sales were up 2% in the first nine months of 2026, the best January–September since 2018, with price appreciation at ~3.7% and demand described as end-user rather than speculative. Office supply, however, rose to ~0.34 crore sq ft of new completions, and rental growth at 3% was the lowest of the 8 markets.
- Infrastructure tailwinds accumulating: Metro Phase 2 linking Ahmedabad, Gandhinagar, and GIFT City was completed in January 2026; the Union Cabinet approved airport Phase 2A in June; and reported plans to speed up Metro links towards the Godhavi sports arena for the 2030 Commonwealth Games would directly benefit the company’s largest land parcel.
Ravi: "Our balance sheet, on the other hand, is almost debt free. So a rate cycle that squeezes others gives us room to be selective."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 revenue | ₹1,000–1,200 crores | FY27 |
| FY27 PAT | ₹300–325 crores | FY27 |
| Malabar Retreat possession | Soft possession for interiors | 15 January 2027 |
| Malabar Retreat BU permit | Building Use permit | Mid-February 2027 |
| Malabar Retreat revenue recognition | On completion (Ind AS 115) | Q4 FY27 |
| Malabar Retreat sales | Sell almost everything, or at least 75% | By March 2027 |
| Million Minds Tower 1 leasing | 90% let | By March 2027 |
| Million Minds Tower 1 rental commencement | Lease rentals begin | Q4 FY27 |
| Million Minds Tower 2 Bhumi Pujan | Groundbreaking ceremony | 24 November 2026 |
| Million Minds Tower 2 construction | 24–28 months from approval and contractor appointment | Tower ready for fit-outs between May and November 2028 |
| Million Minds Tower 2 pre-leasing | Open for pre-leasing | Late 2027 |
| Million Minds residential Phase 1 launch | ~9 lakh sq ft, 334 units, GDV ₹500 crores | Q4 FY27 |
| Godhavi monetization plan | Announcement of mix (plotted, land sales, project development) | Towards later part of this year (CY26) |
| FY28 guidance | Year-on-year guidance to be provided | Q4 FY27 or Q1 FY28 |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue | ₹121 crores, consisting all of project land sales; YoY lower vs high base of over ₹174 crores in Q2 FY26 |
| EBITDA | ₹98 crores |
| EBITDA margin | 80.7%, recovered from 39.3% in Q1 FY27 which carried high-cost land and a onetime tax charge |
| PBT | ₹89 crores |
| PAT | ₹67 crores, up 59% sequentially from ₹42 crores; YoY lower vs high base of ₹108 crores in Q2 FY26 |
| PAT margin | 55.1% |
| EPS | ₹8.02 |
| H1 FY27 revenue | About ₹402 crores |
| H1 FY27 PAT | About ₹109 crores |
| FY27 revenue guidance | ₹1,000 crores to ₹1,200 crores, reaffirmed |
| FY27 PAT guidance | ₹300 crores to ₹325 crores, reaffirmed |
| Million Minds Tower 1 leasing | 68.4% of leasable carpet area let across 15 deals, up from 43% in July |
| Million Minds Tower 1 area let | 4.21 lakh square feet of 6.16 lakh square feet total leasable carpet |
| Million Minds Tower 1 average rent | ₹110.20 per square feet per month; recent deals signed at ₹122.4 per square feet |
| Million Minds Tower 1 contracted rent roll | About ₹55.7 crores; fully let estimate ₹84 crores per year, 20% above initial estimate of ₹70 crores |
| Co-working concentration in Tower 1 | 28.7% of space let, down from about 36% a quarter ago |
| Malabar Retreat completion | 87% complete, up from 83% in July |
| Malabar Retreat bookings | Almost 50% by units (76 units); 53% by carpet area |
| Malabar Retreat collections to date | ₹132 crores |
| Malabar Retreat expected receivables | ₹305 crores (booked and unbooked) |
| Fully paid land reserves | 513 acres, comprising 405 acres at Godhavi, about 65 acres at Million Minds, and balance parcels in and around Ahmedabad |
| Ongoing projects expected sales value | About ₹1,500 crores on a capitalized basis |
| Planned pipeline sales value | About ₹21,000 crores across roughly 2.88 crore square feet |
| Planned pipeline expected free cash flows | ₹12,500 crores |
| Tower 2 target rent | About ₹118 per square feet per month, implying ₹94 crores annual rent at full occupancy |
| Tower 2 leasable carpet | 6.6 lakh square feet on roughly 14.5 lakh square feet of construction |
| Residential Phase 1 at Million Minds expected GDV | ₹500 crores, roughly 9 lakh square feet, 334 units across 2 towers |