Gujarat Industries Power Co Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/zpzo69afjrwmo45m158w9oxh.pdf

Key Takeaways


The Khavda Solar Ramp

The 600 MW Khavda solar plant, commissioned in December 2025, achieved a 33.24% CUF in Q1 after resolving teething issues that had capped it at 23% in the March quarter. Full evacuation allocation received in November 2025 means the plant faces no curtailment, unlike other developers in the Khavda region who are waiting on KPS 2 readiness.

The 500 MW expansion is at an advanced commissioning stage, with capacity being added in phases. The first 200 MW is expected post-monsoon, followed by another 200 MW and 100 MW in subsequent months, contingent on CTUIL evacuation facility readiness. Full commissioning is targeted by end of calendar 2026.

Bhatt: "We have been given the full allocation in November 2025 and we are evacuating the full load from the 600 MW Khavda. That is why our CUF is 33%."

Profitability Bridge: Why EBITDA Growth Is Deferred

The 600 MW plant's full-year contribution will nearly double solar EBITDA, but consolidated profitability faces a heavy drag from financing costs that are only now hitting the P&L. The one-year moratorium on Khavda debt ended in June 2026, so principal repayment and full interest charges begin next quarter.

The debt repayment schedule is structured as a step-up: lower in the first five years, then topping up in subsequent five-year blocks. Management declined to share specific repayment percentages. Peak debt across all projects is expected to reach ₹6,000–₹6,500 crores at one point.

Bhatt: "This year, you will not see the EBITDA of INR950 crores to INR1,000 crores. Once the 500 MW Khavda gets commissioned for the full operational year, hopefully, next year, you will see these figures on the paper."

Thermal & Gas: The Old Fleet

The two lignite-based thermal stations (SLPP 1 and SLPP 2) continue to perform reliably, crossing 75% and 80% PLF thresholds respectively. Both are debt-free and sit at the top of the merit order in South Gujarat, where industrial power demand remains heavy, insulating them from any curtailment risk even if a surplus were to emerge.

The 310 MW Baroda gas-based station remains idle, with a cost of production around ₹10/unit. All capex has already been recovered through PPA tariffs over the years. Management sees no revival given the current geopolitical situation and is instead repurposing the site.

Bhatt: "See, the gas-based stations looking at the current geopolitical situation, I think it is not going to be revived now."

The Next Growth Legs: Thermal, Storage & Solar

750 MW lignite thermal expansion: GUVNL has given in-principle approval under a Section 62 cost-plus basis. The tender has been floated and is under observation by BHEL and other parties. The order is expected by the last quarter of this financial year, with three 250 MW units to be commissioned in 2031, 2032, and 2033. Capex will phase from 2027 through 2032–33.

Storage strategy: GIPCL's approach is reactive to GUVNL's requirements. If the off-taker requires storage for grid stability at existing renewable sites, GIPCL will implement it. Beyond the Baroda BESS, the company is also in the race to secure pump storage allocations from the Government of Gujarat and is identifying locations.

Incremental solar: Management is planning to add 200–300 MW of solar in the next couple of years, subject to land availability. When pressed on a medium-term vision for 500–1,000 MW annual additions, management pushed back, calling the gap between ambition and "actual reality" significant.

Bhatt: "That is one thing and actual reality is another thing. So we are thinking to add certain capacity of solar in the next couple of years around 200 to 300 megawatts."

Financial Position & Other Items


Guidance & Commitments

CommitmentSpecificsTimeline
500 MW Khavda commissioningFirst 200 MW post-monsoon, then 200 MW and 100 MW in subsequent months; full capacity by end of 2026Phased through Q3 FY27
600 MW Khavda revenue~₹420 crores (±5–10%) for FY26-27FY26-27
600 MW Khavda EBITDA₹350–₹360 croresFY26-27
Consolidated EBITDA run-rate₹950–₹1,000 croresFY27-28 (full year of 500 MW operations)
750 MW lignite thermal orderOrder expected from GUVNLBy last quarter of FY27
750 MW lignite commissioning3 × 250 MW units2031, 2032, 2033
Baroda BESS first phase (20/120 MW)Fully operational~1 year
Additional Khavda solar (200 MW)From optimized land"Next couple of months"
Incremental solar capacity200–300 MW"Next couple of years"
Gas plant hive-off decisionDecision on hiving off gas-based stations"Next couple of years"
Peak consolidated debt₹6,000–₹6,500 croresAt one point during capex cycle
Quarterly disclosuresConference calls, presentation, PLF data on exchangesStarting next quarter

Key Metrics

MetricQ1 FY27
Revenue from 600 MW Khavda solar₹420 crores expected for FY26-27
Revenue from RE Park (O&M)₹55–₹60 crores at peak
Revenue from RE Park net of expenditure₹20–₹25 crores expected
Solar division EBITDA (FY25-26)₹332 crores
Solar division EBITDA (FY26-27 expected)₹600 crores
Solar division PBT (FY25-26)₹62 crores
Consolidated EBITDA (FY26-27 expected)₹950–₹1,000 crores once 500 MW fully operational
PBT (FY26-27 expected)₹220 crores
600 MW Khavda CUF33.24% in Q1 FY27, up from 23% in Q4 FY26
600 MW Khavda expected annual CUF30%+
SLPP 1 PLFcrossed 75%
SLPP 2 PLFcrossed 80%
Raghanesda solar CUF28–29%
Non-current borrowings (31 Mar 2026)₹3,250 crores
Projected total debt after 500 MW commissioning₹4,500 crores
Peak debt (including thermal expansion)₹6,000–₹6,500 crores at one point
Average borrowing cost7.8%, floating
Interest cost (FY26-27 expected)₹250–₹260 crores
Depreciation (FY26-27 expected)₹425–₹450 crores
Interest cost (FY27-28 expected, post 500 MW)₹400–₹450 crores
Depreciation (FY27-28 expected, post 500 MW)₹550–₹600 crores
750 MW lignite thermal capex₹6,500–₹7,000 crores
750 MW lignite commissioning timeline2031, 2032, 2033
Baroda BESS capex₹250–₹300 crores
Baroda BESS revenue model~₹6 per unit
Khavda additional 200 MW project cost₹800–₹1,000 crores
Khavda additional 200 MW additional debt₹200–₹300 crores
Capital work in progress (31 Mar 2026)₹2,065 crores, entirely for 500 MW project
Revenue breakdown FY25-26: SLPP 1 & 2₹1,103 crores
Revenue breakdown FY25-26: Solar (ex-Khavda)₹152 crores
Revenue breakdown FY25-26: Wind₹86 crores
Revenue breakdown FY25-26: 75 MW solar₹38 crores
Revenue breakdown FY25-26: Khavda₹111 crores
75 MW group power plant revenue (9 months)₹38 crores
Khavda tariff₹2.73 per unit
PPA tenure for Khavda25 years
145 MW gas plant original project cost~₹150 crores (1993)
165 MW gas plant original project cost~₹250–₹300 crores