Gujarat Industries Power Co Ltd Q4 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/z86sys7012wtx3niu8yxqukk.pdf

Key Takeaways


Khavda 600 MW Solar Project: The Growth Engine

Management: "That is correct, but somehow you have to take the opportunity and then you have to go ahead. Otherwise, if you miss the bus, then you will have next future development will be at stake. So, you have to take risk for your company and requirement of the current scenario."

Khavda Park Developer Role & Phase 2


Thermal & Gas: Steady State, No Expansion

Management: "Sir, current gas price is very volatile like every day, you will find different rate like today, it is trading around $9 per mmbtu. You take $9 plus taxes and everything $12 to $13, per unit tariff would be around more than INR10."

SLPP-1 R&M: Extending the Legacy Asset


Renewable Portfolio: Patience Required

Management: "You have to wait for 2-3 years once the interest goes down, depreciation goes down and revenue generation will remain as it is. But all this expenditure will go down, then the profitability portion will go up in next couple of years."

Capital Management & Disclosures

Management: "See, it is basically as I explained to you, this is a guideline. At least some profit has to be shared to the equity partner. So, the policy was published by the GoG, which is basically a guideline in nature. And looking to the government support which we are getting, being a GoG entity, we have also fallen in line with the GoG requirement and the guideline."

Guidance & Commitments

CommitmentSpecificsTimeline
Khavda 600 MW solar commissioningPlant operationalBy or before December 2024
Khavda Phase 1 tenders concludedStructural BOS and PV module tenders awardedBy end of monsoon (~August 2023)
Khavda Phase 1 site work beginsConstruction start at locationSeptember end 2023
Khavda Phase 1 park development startFirst phase 1,200 MW parkDecember 2024
Khavda Phase 2 completion deadlineRemaining 1,175 MW parkDecember 2026
Insurance claim recoveryLoss of material claim processed first, then loss of profitFY24
SLPP-1 R&M projectCapex to extend plant life and secure mining landNext 10 years (post-approval)
Renewable profitability inflectionProfit after tax to show higher positive cash flow as depreciation and interest declineNext 2–3 years
Disclosure upgradesPAF percentage on website; improved presentation with PLF, energy data, segment splitPAF within days; presentation timeline unspecified

Key Metrics

MetricQ4 FY23
Revenue (thermal division)₹1,082 cr (FY23)
Revenue (renewable division)₹266 cr (FY23)
EBITDA (thermal)₹226 cr (FY23)
EBITDA (renewable)₹231 cr (FY23)
Profit before tax₹253 cr (FY23)
Depreciation₹164 cr (FY23)
Finance cost₹37.54 cr (FY23)
Dividend per share₹3.75, up from ₹3.00 last year
Dividend payout ratio30% of PAT, in line with GoG guideline
Lignite production30 lakh metric tons (FY23)
Khavda solar project tariff₹2.73 per unit, PPA to be executed with GUVNL
Khavda Phase 1 capex (GIPCL share)₹3,780 cr total outlay (₹3,600 cr project + ₹180 cr park equity)
Khavda Phase 1 equity IRR (post-tax)~12%, conservative internal estimate
Khavda Phase 1 commercial startNovember 2024
Khavda park development cost (Phase 1)₹600 cr, of which GIPCL equity share 30%
Khavda project spend to date₹200 cr on park activities; ₹50–60 cr on project
Debt interest rate (in-principle approval)~8% from two or three large lenders
Gas plant viability thresholdPer-unit tariff above ₹10 at current gas price of ~$9/mmbtu plus taxes; viable below ₹8
Insurance claim expected₹3–4 cr material loss, ₹12–15 cr loss of profit, under process
Operating cash flow~₹400 cr per year, last few years
Cash in hand₹600–700 cr available