Key Takeaways
- Resilient quarter in a storm: Revenue grew to ₹976 crore despite a confluence of headwinds: a 4.5-month monsoon, elections, and geopolitical export disruption. Management navigated to maintain the status quo.
- New plants are the growth story: The hydraulic tube plant is commissioned and the defense shell plant is on track for trials by April 2025, with management calling the latter a potential "game changer."
- Full-year revenue guidance held firm: Management is confident of reaching nearly ₹4,000 crore this fiscal year, implying a significant H2 ramp-up now that monsoon and election disruptions have cleared.
- EBITDA per ton stable, improvement promised: EBITDA per ton held flat at ~₹8,100, and management committed to improving it year after year, with a 5-10% jump expected once volatility subsides.
- What to watch next quarter: The pace of commercialization at the hydraulic tube plant, the start of commercial production at the auto tube plant in January, and whether the promised H2 demand recovery materializes to hit the full-year revenue target.
Performance & Headwinds
- Revenue and volume up: Total operating income grew to ₹976 crore from ₹885 crore in Q2 FY24, while H1 sales volumes surged ~9.4% to 2,00,489 metric tons.
- EBITDA improved despite conditions: EBITDA rose to ₹87.45 crore from ₹73.68 crore in Q2 FY24, driven by cost optimization and operational efficiencies.
- A quarter of stacked disruptions: The 4.5-month monsoon delayed all projects, stopped site work and supplies, and no new projects were declared after elections. Geopolitical tensions, the Red Sea problem, and US election uncertainty simultaneously hit exports.
- Other income spike unexplained: Other income jumped to ~₹18 crore from ~₹1 crore in the previous quarter. Management attributed it broadly to interest income, export rebates, and miscellaneous income but declined to give a specific breakdown, directing the analyst to email for details.
- EBITDA per ton held flat: Management stated EBITDA per ton remained approximately flat at ~₹8,100, similar to the previous quarter, and did not confirm an analyst's figure of ₹8,350 from the prior period.
Ram Agarwal: "Otherwise, it was very difficult because monsoon were almost point 4 and a 1/2 months. All the projects were delayed. There was no site was working, no supplies were going and geopolitical after election, no new projects have been declared. US election, all the export was down. But still in this difficult quarter, we have navigated our company to maintain, in your words, we have maintained the status quo."
New Capacity: The Growth Engine
- Hydraulic tube plant commissioned: The large-diameter, heavy-wall, thicker-pipe plant was commissioned in September 2024 with an investment of ₹200 crore and a capacity of 15,000 metric tons. It is the first plant of its kind in India and is meant to replace Chinese imports of similar size.
- Hydraulic tube ramp-up timeline: Trials are ongoing and equipment for many sizes is still arriving. Ramp-up will take three more months, with commercialization expected in 4-6 months as actual users must test and approve material before regular orders begin. Inquiries and orders are exceeding expectations.
- Hydraulic tube capacity expansion path: The company hopes to achieve the 50,000 metric ton capacity in 12 to 18 months. Once 80-90% utilization is reached, another CapEx will be needed to double capacity.
- Auto/ERW tube plant nearing start: The last tube plant is under trial, with commercial production starting from January 2025 and full ramp-up from April 2025.
- Defense shell plant on track: Machines are on the sea and erection will be completed by March 2025. Trial runs commence from April 2025, with revenue contribution expected from Q2 of the next financial year. Management says this may be ahead of schedule.
- Defense revenue and margin potential: At full capacity of 1,50,000 shells, the plant is likely to generate ₹300-350 crore, with management hoping for a margin of more than 20%.
- Defense fundraising deferred: Plans to raise funds for Goodluck Defense will be considered once the plant is stabilized, but no internal figures or timeline have been decided. Total focus is on starting the plant.
M C Garg: "I must tell you this is the first of its kind plant in India, there is no plant of this size. It is going to replace Chinese similar size imports."
Order Book & End-Market Visibility
- Bullet train order nearing completion: The company has an order of 22,000 metric tons for the bullet train project. Approximately 65% has been produced, and the order will be completed in the next 8-9 months, maximum 12 months.
- Solar support structure momentum: The company is already supplying for 200 MW and servicing almost all major players, with a good order book and visibility for at least the next one year.
- Defense demand backdrop: The Indian market has strong demand, with the nodal authority placing orders for over 2,50,000 shells with a requirement by 2027, up from very small quantities in prior years.
- Export growth expected: The company expects good growth in exports, with most products from the newly commissioned plant destined for export markets.
Guidance & Revenue Outlook
- Full-year revenue target held: The company expects to reach nearly ₹4,000 crore this financial year, up from ₹3,500 crore last year. Management is confident the 15-20% growth guidance is achievable despite Q2 headwinds.
- H2 must deliver the catch-up: Management expects H2 to be much better than H1. The monsoon has subsided, US election results are out, government projects have started coming up from October, and with the March year-end all funds must be spent, so procurement activity should normalize or improve.
- Guidance contradiction noted: When an analyst pointed out that Q2 recorded only 10% growth against the 15-20% guidance, management initially cited the 10% figure, then stated the guidance is "definitely achievable" and "likely to achieve it," without reconciling the gap.
- EBITDA per ton improvement expected: Management is fully confident it will not only maintain EBITDA but improve it year after year, with a 5-10% year-on-year improvement expected if volatility subsides.
- Margin inflection point ahead: Significant improvement in EBITDA margins is most likely visible in the next financial year, after defense CapEx is completed and the LDP plant is ramped up.
M C Garg: "We are fully confident. We will not only maintain EBITDA, we will improve it year after year."
Capital Allocation & Structure
- No demerger of CR coil business: Management stated they do not plan to demerge the CR coil business in the medium to long term, nor do they plan further expansion in it.
- Defense subsidiary focus: Goodluck Defense and Aerospace is advancing at a fast pace, and management called the demand for its product "very frantic," with the production output set to be a "game changer" for the company.
M C Garg: "the demand for the product which we are going to make is very frantic and the production coming out is going to be game changer to the company."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Full-year revenue | Reach nearly ₹4,000 crore (15-20% growth) | FY25 |
| Auto/ERW tube plant | Commercial production start, full ramp-up from April 2025 | January 2025 |
| Defense shell plant | Trial runs commence; revenue contribution begins | April 2025; Q2 FY26 |
| Defense production target | Achieve minimum 60-70% of production target | FY26 |
| Bullet train order completion | Remaining ~35% of 22,000 MT order delivered | 8-12 months |
| EBITDA per ton improvement | Improve 5-10% year-on-year | When volatility subsides |
| EBITDA margin inflection | Significant improvement visible | Next financial year (FY26) |
| Hydraulic tube capacity utilization | Achieve 50,000 MT capacity, then double via CapEx | 12-18 months; after 80-90% utilization |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Total operating income | ₹976 cr, up from ₹885 cr in Q2 FY24 |
| EBITDA | ₹87.45 cr, up from ₹73.68 cr in Q2 FY24 |
| PAT | ₹45.06 cr, up from ₹34.70 cr in Q2 FY24 |
| Other income | ₹18 cr, versus ₹1 cr in Q1 FY25 and ₹4 cr in Q2 FY24 |
| H1 FY25 standalone net profit | ₹79.53 cr, up 25.66% from ₹63.29 cr in H1 FY24 |
| H1 FY25 total income | ₹1,908.33 cr, up 9.25% from ₹1,746 cr in H1 FY24 |
| H1 FY25 sales volumes | 2,00,489 metric tons, up ~9.4% from 1,83,256 metric tons in H1 FY24 |
| Q2 FY25 volume | ~1,03,000 tons |
| EBITDA per ton | ~₹8,100 |
| Full-year FY25 revenue guidance | Nearly ₹4,000 cr, versus ₹3,500 cr in FY24 |
| Annual exports | Nearly ₹1,000 cr |
| Hydraulic tube plant investment | ₹200 cr, capacity of 15,000 metric tons |
| Bullet train order | 22,000 metric tons, ~65% produced |
| Defense shell plant full-capacity revenue potential | ₹300 to ₹350 cr at 1,50,000 shells, depending on market conditions |