Godawari Power & Ispat Ltd Q1 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/ftv5f1snwulk3t4tu7b4wnu3.pdf

Key Takeaways


Margin Dynamics: Coal Tailwind vs Steel Headwind

Abhishek Agarwal: "Because of our captive mines, our strength is iron ore at a very lower cost compared to others. And secondly, because the entire India is making the same grade which is the 63 or 62 pellets. But in my case, since I am making a premium product which is 66 Fe now, I have a different market, I have a different target audience."

66 Fe Pellets: The Premiumization Bet

Abhishek Agarwal: "We are very focused. Our primary focus is to produce more of high-grade pellets and eventually realize the desired premium. Because going forward, with more initiatives towards green steel, the demand for high-grade iron ore will keep going up year on year, be it domestically or be it internationally."

Governance Reset: Loans, Promoter Entities, Stake Sales

Abhishek Agarwal: "I can assure you all the loans we have given are always unsecured, but they will come back to the company with the desired interest. And going forward, we have taken a management decision that we will not indulge in such practice any further."

The Growth Pause: No Volume Uptick Until Approvals Clear

Abhishek Agarwal: "We are still exploring because a lot of new technologies are coming into the picture. And since this will be our first project in terms of primary production, we need some more time to finally decide the product mix."

Capex, Funding & Capital Allocation


Segment & Market Context

SegmentTrendCommentary
Pellets▼ Volume, ▲ RealizationProduction down 21% QoQ on planned monsoon shutdown; 66 Fe launch lifted realizations 3% QoQ to ₹10,200/tonne. Q2 realization expected ₹10,000-10,500.
Sponge Iron, Billet, MS Rounds▲ Volume, ▼ RealizationProduction and sales rebounded sharply from a Q4 shutdown base; Q2 prices down 8-10% sequentially.
Ferro Alloys▼ WeakSilico manganese prices at rock-bottom ₹55,000/tonne; Hira Ferro at breakeven or slightly above. Solar plant at Hira commissioned and will aid margins from Q2.
Global Iron Ore▼ CorrectedPrices fell from $233 to $115 on increased supply and weaker-than-expected China demand; China's stimulus announcements may support a floor.
Domestic Iron Ore▬ StableNMDC prices rose from ₹3,650 to ₹4,210 but remain well below last year's ₹5,000. Pellet prices declined from ₹10,200 in March to ₹8,800 for 63 Fe.

Guidance & Commitments

CommitmentSpecificsTimeline
Pellet volumeAchieve 0.26 crore tonnesFY24
Solar capacity commissioning55 MW completedEnd of Q2 FY24 (September)
Residual capex completion₹125 crores (steel and power plant, ex-solar)FY24
Energy cost savings₹100-125 crores annualized at EBITDA levelFrom FY24, as solar and turbine projects commission
Environmental approvalsClearances for mining expansion and integrated steel plantEnd of Q3 or early Q4 FY24
Mining ramp-up0.36 crore tonne incremental capacity to full production12-18 months from approval date
Pellet plant (3 MT) constructionNew capacity online~18 months from approval date
Integrated steel plant constructionGreenfield plant online24-30 months from approval date
Hira Ferro Alloys EBITDAAbove ₹50 croresFrom next year onward
Inter-corporate loansNo new unsecured loans to be extendedEffective immediately
Dividend policyAdhere to board-approved policyOngoing
Capex fundingEntire ₹3,500 crore program funded via internal accrualsThrough project completion
Tax rate25% average rateGoing forward

Key Metrics

MetricQ1 FY24
Consolidated revenue₹1,326 cr, +1% QoQ, -20% YoY
Standalone revenue₹1,207 cr, -1% QoQ
Consolidated EBITDA₹305 cr, +14% QoQ
Standalone EBITDA₹300 cr, +9% QoQ
Standalone EBITDA margin25%, vs 22% in Q4 FY23
PAT attributable to owners₹231 cr, +36% QoQ
Exceptional income₹18 cr, from share purchase agreement for sale of Godawari Green Energy stake
Iron ore volume5,70,000 tonnes
Iron ore pellet production-21% QoQ and YoY, due to plant maintenance shutdown
Iron ore pellet sales2,97,000 tonnes, decreased due to higher captive consumption for sponge iron
Average pellet realization₹10,200 per tonne, +3% QoQ
66 Fe pellet premium over 63 Fe₹1,500 to ₹2,000 per tonne additional realization
66 Fe pellet premium over 65 Fe~₹800 per tonne currently; incremental cost ~₹300, net delta ₹500-600 per tonne
High-grade pellet production mix<50% in Q1 due to shutdown; expected to be 65% going forward
Volume guidance achievement (sponge iron, billet, roll products)30%, 25%, 28% of FY24 targets achieved in Q1
Pellet volume guidance for FY240.26 crore tonnes
Landed cost of thermal coal~₹12,500 per tonne currently; expected to decline by ~₹1,000 in coming months; Q1 average ~₹15,000-16,000, Q2 expected ~₹12,000-12,500
Coal as share of total raw material cost~35%
Renewable power share at Godawari level~30%
Solar capacity commissioned100 MW running (70 MW GPIL + 30 MW HFAL); additional 55 MW expected by end of Q2 FY24
Annualized EBITDA savings from energy projects (solar + turbine)₹100 cr to ₹125 cr
Normal CAPEX for steel and power plant (ex-solar)~₹125 cr, expected completion in FY24
Tax rate25%