Godawari Power & Ispat Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/auogombpl4dmg269rqpvav52.pdf

Key Takeaways


Mining Constraints & Input Costs

Abhishek Agrawal: "I would say it's very unfortunate key there have been enormous delays at different stages when it comes to approval from the state government. But that is something which is not in our hand. And hopefully whatever pending approvals are still there we would should get it, as soon as possible. That's all I can say. It's very unfortunate, but it's really not in our hands, to be honest."

Pellet Operations & Market

Abhishek Agrawal: "The delta in pellet is almost INR4. So commercially doesn't make sense to sell iron ore in the near term. Unless pellet prices really, really crash to below INR8,000, then probably, we can think of selling iron ore in the market, but I do not see that happening very soon."

Beneficiation & Captive Ore Roadmap

Abhishek Agrawal: "And from Q4 gradually, it should come down below 10%, and finally in FY28, it should be 100% captive. That is the target."

Strategic Reset: Steel Plant Hold & CRM Relocation

Abhishek Agrawal: "So, we feel shifting CRM is actually a boon to us by shifting to Maharashtra rather than Chhattisgarh."

BESS & New Growth Engines


Financial Position & Capital Allocation

Abhishek Agrawal: "Since it's on hold now, so we don't need to borrow any money for funding our current projects. We are very much -- we have sufficient free cash flows to fund the entire projects now."

Guidance & Commitments

CommitmentSpecificsTimeline
Mining production ramp-upFull capacity from Q4 or early Q1 next financial yearQ3 FY27 start, Q4 FY27 full
Captive iron ore shareBelow 10% market purchase from Q4; 100% captiveFY28
Mining costBelow ₹2,700 per tonFY28
Pellet productionFull capacity of ~0.45 crore tonsFY28
Margin improvementFrom beneficiation plant commissioningQ4 FY27
CRM land allotmentExpected by end of August 2026August 2026
CRM construction startOctober 2026October 2026
CRM commissioningDecember 2027Q3 FY28
BESS first containerRollout expectedQ1 FY28
100 MW solar commissioningSeptember 2026September 2026
45 MW storage commissioningQ3 FY26Q3 FY26
Carbon capture projectCompletion targetedEnd of FY27
Government land approval for dumpingExpected by end of SeptemberSeptember 2026
Third pellet plant restartPossibility of restarting operationsSeptember 2026
Boria Tibbu expansionFull capacity of 0.07 crore tonsFY31
DR pellet market entryOnce 100% mining capacity achievedFY28

Key Metrics

MetricQ1 FY27
RevenueGrew YoY and sequentially, supported by healthy sales volume and improved realization
EBITDA margin19.1%, broadly stable YoY; softened sequentially on elevated input cost
PAT margin12.7%, broadly stable YoY; softened sequentially on elevated input cost
Q1 volume vs full-year guidance16% to 29% of FY27 guidance achieved
Iron ore mining volumeDeclined YoY, due to space constraints for overburden dumping from delayed tree-cutting permission
Pellet capacity utilization77% in Q1 for the 0.47 crore ton expanded pellet capacity; expected to ramp to 80%-85% in FY27
Iron ore mining costINR3,000 to INR3,500 per ton, up approximately 10% YoY on lower production; target below INR2,700 from FY28
Market iron ore purchase25%-30% of requirement expected in Q3, declining below 10% from Q4, and 100% captive targeted in FY28
Pellet priceINR9,000 to INR11,000 per ton range; current levels around INR10,000 a ton
Iron ore priceINR5,500 per ton ex-mine, broadly stable; global prices at $95 to $105 per ton
Imported coal costINR13,000 per ton, up from INR10,500 in Q4 and early Q1, a 25% impact from the West Asia crisis
Gas purchase costUp 40%-45% under new PNGRB guidelines, making one pellet plant commercially unviable
CBAM emission intensity3.180 CO2 ton, improving 1.9% QoQ and 4.2% YoY from 3.244 ton
WSA emission intensity2.485 ton CO2 per ton of steel, broadly stable QoQ and YoY, against Government of India target of 2.4920
EV fleet15 EV dumpers, 24 EV loaders, 15 EV excavators; EV adoption reduced operating cost by nearly 75% and CO2 emission by around 88%