Godawari Power & Ispat Ltd Q2 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/pu9783yoczs1do8vj4drxl9m.pdf

Key Takeaways


Margin & Cost Performance

Abhishek Agarwal: "once the entire plant is commissioned and with our efforts of debottleneck we can see additional EBITDA of 700 Crores going forward annually on the power side itself."

Boria Tibu Mine: Suspension & Restart Plan

Abhishek Agarwal: "So we can expect the Boria Tibu can come back into production with beneficiation say next 24 to 30 months. We are looking at FY2027 probably."

Growth Capex & Capacity Expansion

ProjectCapacity IncreaseCapexTimeline
Ari Dongri mine expansion0.24 → 0.6 crore tonnes₹200 crores~15 months from approval
Pellet plant0.27 → 0.57 crore tonnes₹800 crores~30 months; full volume in FY2026
Integrated steel plant0.05 → 0.15 crore tonnes₹2,500 crores~30 months from groundwork
Steel billet (commissioned)0.4 → 0.05 crore tonnesCompletedConsent awaited; Q4 FY2024
Solar plant (20 MW captive)New₹80 croresJune 2024

New Integrated Steel Plant: Strategy & Product Choice

Abhishek Agrawal: "we are not looking at the long product side, we are mainly looking at the flat product side. We realize that additional margins are there and because of the demand of automobile going up so we will start the right way to go forward still transition will be made probably next three to four months."

Market & Demand Outlook

Abhishek Agarwal: "till the time licensing does not come at par with domestic we are happy selling domestic. So we are always open but then it is not guaranteed when you start exporting because for us licensing is the topmost priority."

Capital Allocation & Balance Sheet

Abhishek Agarwal: "I think on the cost indication side I would say we are very much covered because of iron ore and we want to utilize our money probably making high value added steel other than going backward and making coal captive." [20-21]

Guidance & Commitments

CommitmentSpecificsTimeline
Pellet plant environmental approvalFinal approval expectedQ4 FY2024
Pellet plant full productionEntire new capacity producingFY2026
Ari Dongri mine expansion approvalApproval in handNext 3-4 months
Ari Dongri mine expansion completionCapacity to 0.6 crore tonnes~15 months from approval
Steel billet additional capacity operational125,000 tonnesQ4 FY2024
20 MW captive solar plant completionCommissioned and saving ₹3/unitJune 2024
Boria Tibu beneficiation restartMine back in productionFY2027 (24-30 months)
New steel plant product freezeFinal product mix announcedEnd of FY2024 or Q4 call
New steel plant constructionGroundwork to commissioning~30 months from approvals
FY2024 volume guidanceFerro alloys and pellets on trackFY2024
EBITDA sustainabilityMaintain current levelsConditional on market sustaining

Key Metrics

MetricQ2 FY24
RevenueMarginal decrease QoQ
Operating margin25%, led by reduction in power and fuel cost
Iron ore pellet production+21% QoQ, -1% YoY
Iron ore sales volume432,697 metric tonnes, +45% QoQ
Iron ore realization₹9,955 per tonne, +22% YoY and -2% QoQ
Iron ore pellet realization (H1 FY24)₹10,055 per metric tonne, +4% YoY
Steel billet sales growth (H1 FY24)+30% YoY
MS Round sales growth (H1 FY24)+9% YoY
HB wire sales growth (H1 FY24)+64% YoY
Galvanized product sales growth (H1 FY24)+39% YoY
Sponge iron production growth (H1 FY24)+71% YoY
Steel billet production growth (H1 FY24)+28% YoY
MS Rounds production growth (H1 FY24)+27% YoY
Capacity utilization95–100% across plants
Captive power share98–99% of total requirement
Thermal coal cost~₹12 per tonne average in Q2
Ferro alloy margins₹2 to ₹3 per unit, at rock bottom
Pellet price (domestic, October)~₹10,000 per tonne
Sponge iron price (October)~₹30,000 per tonne
Billet price (October)~₹42,000–43,000 per tonne
HB wire / MS Round price (October)~₹48,000 per tonne
Iron ore mining guidance revisionLowered ~20% for FY24 due to Boria Tibu grade issues
Ari Dongri mining expansion capex₹200 crores, completion in ~15 months from approval
Pellet capacity expansion capex~₹800 crores, completion in ~30 months
Integrated steel plant capex₹2,500 crores, capacity from 0.05 to 0.15 crore tonnes
Additional steel billet capacity125,000 tonnes, operational expected in Q4 FY24
Solar power capacity addition20 MW captive plant approved, investment ₹80 crores, completion by June 2024
Additional EBITDA from solar and debottlenecking₹700 crores annually going forward
EBITDA per tonne (current)~₹6,099
Incremental EBITDA from pellet-to-steel conversion₹8–10 per tonne; at current market, ₹10,000 per tonne above pellet EBITDA
Cost saving from mine beneficiation plant₹150 per tonne, ~₹100 crores annually at 0.6 crore tonne volume
Global iron ore price (CIF China)$125–127 per tonne currently
NMDC iron ore price₹4,460 per tonne currently, up from ₹3,660 in January
Pellet price trend₹8,800 in July 2023, ₹9,000 in September, ~₹10,000 currently
World Steel demand growth forecast+2.3% in 2023, +1.7% in 2024
India steel demand growth forecast+7.3% in 2023
Government capex push+33% capital outlay, +75% railways outlay
Credit rating upgradeCRISIL AA- / Stable (long term), CRISIL A1+ (short term)
Coal imports~1.5 lakh tonnes per quarter
High-grade pellet production share65% of production; merchant sale ratio 50:50 high-grade to normal
New pellet plant grade mix~80% high grade, 20% normal grade
Premium on 65% Fe pellets~₹50 per tonne yearly average
Net debt₹600 crores plus currently, down from ₹2,000 crores in 2017
Debottlenecking capex remaining in FY24~₹71 crores
Boria Tibu beneficiation plant timeline24–30 months, production expected by FY2027