Godawari Power & Ispat Ltd Q2 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/s0aghkb16kfc590nqfoiephn.pdf

Key Takeaways


The Shutdown: What Happened and What It Cost

Abhishek Agrawal: "Last time we did the annual shutdown was almost 10 years back. So that is how the plant works. So going forward, it doesn't happen every year."

Volume and Realization Dynamics


Mining Approval: The Critical Path

Abhishek Agrawal: "So usually, we are buying about 25% of our iron ore from the market, and that will continue till our mining expansion happens."

Pellet Capacity Expansion and Mix Shift


Greenfield Steel Plant and Other Projects

Abhishek Agrawal: "It's a very R&D stage. And hopefully, everything works out, we can start investing on a bigger model. That's the whole idea."

Market Outlook and Margin Recovery

Abhishek Agrawal: "To be honest, with the current increase in production in India for steel, the iron ore prices have been strong. And irrespective of how the international prices play, the pellet price should be in the same levels."

Guidance & Commitments

CommitmentSpecificsTimeline
Mining expansion approvalIron ore mining capacity from 0.24 to 0.6 crore tonsBy end of FY25 (Q4 FY25)
FY25 iron ore productionRevised to 0.24 crore tons (from 0.3 crore tons)FY25
Beneficiation plant commissioningWithin 6 months of receiving environmental approval6 months post-approval
New pellet plant commissioningCapacity increase from 0.27 to 0.47 crore tonsJune/July 2025
Pellet volume ramp-upFY26: +0.1 crore tons; FY27: +0.2 crore tonsFY26 and FY27
Mining production ramp-upReach 0.6 crore tons after approvalEnd of Q1 or Q2 FY26
Greenfield steel plant approvalEnvironmental clearance for 0.2 crore-ton integrated plantDecember 2024
Waste heat recovery project7 MW plant with Siemens at INR73 croresWithin 18 months
Capex guidanceINR800 crores FY25, INR1,000 crores FY26 (excluding steel)FY25 and FY26
Net Zero targetAchieve Net ZeroBy 2050
Boria Tibu mineMine online only after beneficiation plant installed2-3 years

Key Metrics

MetricQ2 FY25
Consolidated revenue₹1,268 cr, flat YoY
Consolidated EBITDA₹247 cr, margin declined from 28% to 20% YoY
Consolidated PAT (excl. exceptional item)₹158 cr
Impact on revenue, EBITDA and PAT from pellet plant shutdown₹65 cr
Pellet production loss due to shutdown150,000 tons
H1 FY25 consolidated revenue~₹2,600 cr, flat vs H1 FY24
H1 FY25 consolidated EBITDA (excl. exceptional item)₹654 cr, down 2% YoY
H1 FY25 consolidated PAT (excl. exceptional item)₹445 cr, down 5% YoY
H1 FY25 cash flow from operations₹564 cr
FY25 iron ore production guidance revised0.24 crore tons, from 0.3 crore tons
Pellet realization₹10,569, up 5% YoY
Q2 average pellet price~₹10,000
Q3 expected pellet price~₹10,000 average
Sponge iron sales volume growth (H1)56% YoY
Steel billet sales volume growth (H1)20% YoY
HB wires sales volume growth (H1)39% YoY
Blended landed coal cost for DRI (imported RB1)~₹12,000 per ton, up from ~₹11,500 QoQ
Domestic coal cost for power plant and gasifier~₹4,000 per ton
Solar power capacity commissioned165 MW
Additional solar capacity planned70 MW, capex of ₹200-225 cr
Waste heat recovery power plant capacity7 MW, cost of ₹73 cr, reduces carbon emission by 50,000 tons annually
Pellet grade mix50% high-grade (56% Fe), 50% normal grade (63% Fe)
Pellet capacity expansion target0.27 cr tons to 0.47 cr tons, commissioning June/July 2025
New pellet plant FY26 volume addition0.1 cr tons, FY27 full 0.2 cr tons
Iron ore mining capacity expansion target0.24 cr tons to 0.6 cr tons, approval expected Q4 FY25
Greenfield integrated steel plant capacity0.2 cr tons, approval expected December 2024
FY25 capex guidance₹800 cr, FY26 ₹1,000 cr
One-time cost for pellet plant shutdown₹25 cr
Net cash~₹970-990 cr
Ferro alloys consolidated EBITDA~₹40-45 cr
Cost of mining iron ore~₹3,000 per ton
Cost to convert mined iron ore to pellets₹1,800 per ton