Key Takeaways
- Operational disruption, but preponed maintenance softened the blow: A fatal pellet plant incident cost ~40 days of production, yet the company used the shutdown to complete planned Q3 maintenance, limiting the net volume loss to roughly 1.5 lakh tons.
- Volume growth story intact despite soft realizations: H1 production rose 18% (mining) and 16% (pellet, value-added steel), while EBITDA and PAT margins held at 22% and 14%. The top-line was supported by higher pellet and galvanized product volumes even as realizations softened across most products.
- The capex cycle is accelerating on all fronts: A new pellet plant is weeks from commercial production, the Ari Dongri mine expansion is nearing environmental clearance, and major equipment orders are placed for both the CRM complex and the BESS project, with both targeting an April '27 commissioning.
- Pellet pricing has a structural floor, for now: An acute iron ore shortage in Eastern India is keeping pellet prices elevated despite weak steel prices, and management sees INR9,000/ton ex-plant as a practical long-term realization. The risk is that new merchant supply eventually closes the gap.
- What to watch next quarter: The ramp-up curve of the new pellet plant toward the 0.3 crore ton annual target, the timing of the Ari Dongri environmental clearance, and any Board approval for the integrated steel plant.
Operational Performance & the Pellet Plant Incident
- Fatal incident, fast response: A pellet plant incident on 26 September caused a ~40-day production halt. The company used the closure to prepone an annual maintenance shutdown originally scheduled for Q3 FY26, so 20-25 of the lost days were already planned downtime.
- Volume loss quantified: The incident cost roughly 1.5 lakh tons of pellet volume, split between late Q2 and the whole of October. Management expects the new pellet plant ramp-up to cover the lost volume by Q4.
- H1 production still grew: Despite losing 5 production days in September, H1 mining volumes rose 18% YoY and pellet plus value-added steel volumes rose 16%. Q2 specifically saw mining up 29%, pellet up 31%, and value-added products up 5%.
- Sales mix shifted toward pellets: Pellet sales surged 71% YoY in Q2, while value-added steel product sales declined. Sponge iron production also fell because a new 30-ton furnace will consume that volume internally from next year onward, taking sponge sales to zero.
- Billet sales dropped on planned maintenance: Steel billet sales declined 40% in H1 over H1 because a 2-month shutdown of one power plant was required to meet revised State Pollution Board norms, reducing power availability for billet production.
- Realization pressure was broad: Only ferro alloys and galvanized products held Y-o-Y stability. Revenue, EBITDA, and PAT all declined Y-o-Y and Q-o-Q, driven by softer realizations and the seasonal weakness in iron ore pellets and finished steel.
Management: "I still wonder currently what happens. But I hope demand comes back because the period has been extended now for almost 5 to 6 months. I hope as an industry, the demand comes back and the prices do go up. Otherwise, it will be a tough time for -- as an industry it will be tough time to survive this phase."
Pellet Market Dynamics & Pricing Outlook
- Iron ore shortage is the binding constraint: An acute shortage of iron ore in the Eastern belt (Bengal, Odisha, Jharkhand) is keeping pellet prices elevated despite weak steel prices. Indian iron ore production is growing 8-9% annually, but new mines take 3-4 years to begin operations and a couple more to ramp up, so demand continues to outstrip supply.
- Raipur is short pellets, not long: DRI capacity additions in the Raipur market (20-25 additional capacity requirements every month) have created a pellet shortage. Management argues that once the new plant comes online, it will balance the demand-supply gap rather than flood the market, and pellets imported from outside Chhattisgarh (e.g., Odisha) will stop first.
- NMDC price cuts are not a direct threat: Management believes it can maintain pellet realizations despite NMDC price cuts because NMDC's supply is limited and additional DRI capacity is generating incremental demand. The company sells within a ~100 km radius of Raipur, a geography it expects to defend even with expanded capacity.
- Long-term pricing anchor: Management sees INR9,000/ton ex-plant as a "very, very practical" long-term realization, with H2 FY26 expected to average around that level, plus or minus 8-10%.
- Merchant iron ore purchases are coming: With new pellet capacity starting before mining capacity ramps up, the company will buy additional iron ore from the market. Management notes that other merchants buy 100% of their iron ore and still make money, so the incremental pellet volume should add to the bottom line.
Management: "If you speak to any DRI guys, they would say pellet prices should be at least INR1,000 less from here on. But because of the shortage of iron ore in India and the production going up every year by 8% to 9%, the raw material prices in India are on the higher side and will remain elevated unless the supply starts improving from the iron ore side."
Capacity Expansion: Pellet & Mining
- New pellet plant imminent: Pre-commissioning trials are underway for the 0.2 crore ton pellet capacity expansion, with cold trials already started. Commercial production is expected by end of November '25, pending consent to operate from the State Pollution Control Board.
- Ramp-up to 80-85% utilization by Q4: Management expects a 4-6 week ramp-up period and close to 80-85% capacity utilization from Q4 (January '26) onward, targeting ~0.09 crore tons in that quarter. The company remains confident of achieving the initially declared 0.3 crore ton annual pellet volume target.
- Ari Dongri mine expansion delayed slightly: Environmental approval is now expected by end-December '25 (a couple of months' delay, with clearance anticipated around Diwali). Ramping up begins from April '26, targeting 0.45-0.5 crore tons in FY27, with the full 0.6 crore tons from January '27. The delay does not impact current-year production but may overlap with the June monsoon.
- Beneficiation plant expansion: The expanded beneficiation line (to 0.6 crore tons from 0.06 crore) is expected up and running by June-July '26, reaching full capacity from Q3 FY27 onward.
- Boria Tibu is a FY29 story: The mine will produce about 5 lakh tons annually, yielding ~3 lakh tons of concentrate, but capex is at least 2 years away and the next expansion is not expected before April '29. The mine will support the new steel complex's additional capacity requirement.
- No surplus iron ore sales: Management stated clearly that all captive iron ore will feed internal requirements; there is no intention of selling surplus in the market.
Management: "Today also, if I start working on Boria Tibu, the next expansion can only happen a minimum of 3 to 4 years from now on. I'm looking at April '29 minimum from here to increase some."
Downstream Projects: CRM, BESS & Solar
- CRM complex taking shape: Major equipment orders were placed in Q2 for the 0.07 crore ton cold rolling mill complex. Commercial production is targeted for April '27 (FY28), with 50-60% PLF assumed in year one and 80%+ from year two.
- BESS project advancing: Godawari New Energy Private Limited (a wholly-owned subsidiary) is planning a 10 GW BESS project in Maharashtra. 112 acres of land have been acquired in the Aurangabad industrial area (AURIC), and an industrial policy MoU is signed with the Maharashtra government. Machine orders have started being placed and should complete in the next 6 months.
- BESS cell sourcing from China: The company will import cells from China and is in advanced-stage negotiations with top suppliers (CATL, EV, lithium) for long-term supply. Management cited 8,000 cycles for 2-hour charging applications, roughly 8-10 years of life, but did not specify a warranty period.
- BESS customer discussions not yet started: Management will begin discussions with 3-4 large developers when closer to commencing operations, roughly 12-13 months from now. The line is expected up between January and March '27.
- Solar capacity doubled: The Board approved an additional 250 MW of solar power capacity (on top of an earlier 125 MW) for captive use in the CRM project and integrated steel plant. Commissioning is expected by Q4 FY27, coinciding with the CRM project, with surplus power used for existing operations by temporarily suspending thermal generation.
- No new thermal investments: Management explicitly ruled out investing in fossil fuel thermal plants, citing future carbon tax mechanisms and a commitment to renewable energy, even when an analyst suggested thermal would be cheaper.
Management: "We have no intention of going back into that. We are very much happy in moving forward because sooner or later, I'm very sure with new government norms, new carbon tax mechanisms which India has proposed, things will get beneficial for us in the longer run."
Integrated Steel Plant & Strategic Positioning
- Steel plant proposal nearing Board approval: A proposal for a 0.1 crore ton integrated steel plant will be put to the Board once the Ari Dongri mining environmental clearance is received. Management is fine-tuning capex with key suppliers and hopes to take it up at the next Board meeting.
- Land secured: 452 acres have been acquired for the integrated steel plant and CRM complex.
- PGCIL approval unlocks the value chain: GPIL received PGCIL approval for supply of steel billets for transmission-grade galvanized steel structures, with billet quality recognized as comparable to India's leading steel producers. The company remains the only one in India providing a fully integrated end-to-end solution for galvanized steel structures, from iron ore to finished product.
- Rolling mill ramp-up ahead: With all PGCIL approvals in hand, the company is ramping up rolling mill capacity and has started taking strips for the pipe segment because of billet quality. Management is hopeful of a substantial volume jump in rolled products for strips and billets from Q4 onward.
- Funding approach: The INR100 crore preferential issue (over 50% taken by promoters) partially funds BESS and CRM requirements. The steel plant will require debt financing.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| New pellet plant commercial production | 0.2 crore ton capacity; cold trials started | End of November '25 |
| New pellet plant ramp-up | 80-85% utilization; ~0.09 crore tons in Q4 | Q4 FY26 (January '26) |
| Ari Dongri mine environmental clearance | Final approval | End of December '25 |
| Ari Dongri mine production ramp-up | 0.45-0.5 crore tons in FY27; full 0.6 crore tons | From April '26; full from January '27 |
| Beneficiation plant expansion | Full line up and running; full capacity from Q3 | June-July '26 |
| FY27 pellet production | 0.4 crore tons bare minimum | FY27 |
| Sponge iron merchant sales | Reduced to zero as new furnace consumes all volume | From FY27 onward |
| CRM complex commercial production | 0.07 crore tons; 50-60% PLF year one, 80%+ year two | April '27 (FY28) |
| BESS plant commercial production | 10 GW; 50-60% PLF year one, 80%+ year two; line up Jan-Mar '27 | April '27 (FY28) |
| Solar capacity commissioning | 375 MW total (125 + 250 MW) for captive use | Q4 FY27 |
| Boria Tibu mine capex start | Approvals and EC preparation underway | Not before ~2 years from now |
| Boria Tibu next expansion | Minimum 3-4 years from now | April '29 minimum |
| Integrated steel plant Board approval | Proposal to be taken up post Ari Dongri EC | Next Board meeting (hoped) |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue | Declined YoY, driven by higher sales volume of pellet and rolled products; lower QoQ owing to reduced realization and seasonal weakness |
| EBITDA margin | 20%, healthy and stable |
| PAT margin | 12%, healthy and stable |
| H1 FY26 EBITDA margin | 22% |
| H1 FY26 PAT margin | 14% |
| Pellet sales volume growth | 71% YoY |
| Value-added steel products sales | Declined YoY |
| Pellet H1 average realization | ~INR9,000 per ton |
| DRI price | ~INR22,000 to INR23,000 per ton on the lower side |
| Pellet production target FY26 | 0.3 crore tons, confident of achieving despite incident |
| Iron ore mining production growth | 29% YoY |
| Pellet production growth | 31% YoY |
| Value-added products production growth | 5% YoY |
| Landed cost of imported coal (RB1, 6000 GCV) | ~INR11,000 per ton |
| Pellet plant incident volume loss | ~1.5 lakh tons, including 20–25 days of preponed planned annual shutdown within a 35–40 day closure |
| Ari Dongri mine expansion environmental approval | Expected by end of December '25 |
| New 0.2 crore ton pellet plant commissioning | Targeted by end of November '25 |
| CRM complex project total cost | INR900 crores, INR600 crores debt, balance from internal accrual |
| BESS project total cost | INR700 crores, 60% debt, balance from internal accrual and equity |
| GPIL equity infused into BESS project | INR175 crores |
| Additional solar power capacity approved | 250 MW, in addition to earlier 125 MW, for captive use |
| Solar project internal rate of return | ~24% (per management) |
| FY27 iron ore mining target | 0.47 crore to 0.5 crore tons |
| FY27 pellet production target | 0.4 crore tons bare minimum |
| CRM and BESS commercial production target | April '27 (FY28) |
| Preferential issue | INR100 crores, majority taken by promoters |