Godawari Power & Ispat Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/1q7mmf9rk78n1n4ytrtl16mi.pdf

Key Takeaways


Operational Performance & the Pellet Plant Incident

Management: "I still wonder currently what happens. But I hope demand comes back because the period has been extended now for almost 5 to 6 months. I hope as an industry, the demand comes back and the prices do go up. Otherwise, it will be a tough time for -- as an industry it will be tough time to survive this phase."

Pellet Market Dynamics & Pricing Outlook

Management: "If you speak to any DRI guys, they would say pellet prices should be at least INR1,000 less from here on. But because of the shortage of iron ore in India and the production going up every year by 8% to 9%, the raw material prices in India are on the higher side and will remain elevated unless the supply starts improving from the iron ore side."

Capacity Expansion: Pellet & Mining

Management: "Today also, if I start working on Boria Tibu, the next expansion can only happen a minimum of 3 to 4 years from now on. I'm looking at April '29 minimum from here to increase some."

Downstream Projects: CRM, BESS & Solar

Management: "We have no intention of going back into that. We are very much happy in moving forward because sooner or later, I'm very sure with new government norms, new carbon tax mechanisms which India has proposed, things will get beneficial for us in the longer run."

Integrated Steel Plant & Strategic Positioning


Guidance & Commitments

CommitmentSpecificsTimeline
New pellet plant commercial production0.2 crore ton capacity; cold trials startedEnd of November '25
New pellet plant ramp-up80-85% utilization; ~0.09 crore tons in Q4Q4 FY26 (January '26)
Ari Dongri mine environmental clearanceFinal approvalEnd of December '25
Ari Dongri mine production ramp-up0.45-0.5 crore tons in FY27; full 0.6 crore tonsFrom April '26; full from January '27
Beneficiation plant expansionFull line up and running; full capacity from Q3June-July '26
FY27 pellet production0.4 crore tons bare minimumFY27
Sponge iron merchant salesReduced to zero as new furnace consumes all volumeFrom FY27 onward
CRM complex commercial production0.07 crore tons; 50-60% PLF year one, 80%+ year twoApril '27 (FY28)
BESS plant commercial production10 GW; 50-60% PLF year one, 80%+ year two; line up Jan-Mar '27April '27 (FY28)
Solar capacity commissioning375 MW total (125 + 250 MW) for captive useQ4 FY27
Boria Tibu mine capex startApprovals and EC preparation underwayNot before ~2 years from now
Boria Tibu next expansionMinimum 3-4 years from nowApril '29 minimum
Integrated steel plant Board approvalProposal to be taken up post Ari Dongri ECNext Board meeting (hoped)

Key Metrics

MetricQ2 FY26
RevenueDeclined YoY, driven by higher sales volume of pellet and rolled products; lower QoQ owing to reduced realization and seasonal weakness
EBITDA margin20%, healthy and stable
PAT margin12%, healthy and stable
H1 FY26 EBITDA margin22%
H1 FY26 PAT margin14%
Pellet sales volume growth71% YoY
Value-added steel products salesDeclined YoY
Pellet H1 average realization~INR9,000 per ton
DRI price~INR22,000 to INR23,000 per ton on the lower side
Pellet production target FY260.3 crore tons, confident of achieving despite incident
Iron ore mining production growth29% YoY
Pellet production growth31% YoY
Value-added products production growth5% YoY
Landed cost of imported coal (RB1, 6000 GCV)~INR11,000 per ton
Pellet plant incident volume loss~1.5 lakh tons, including 20–25 days of preponed planned annual shutdown within a 35–40 day closure
Ari Dongri mine expansion environmental approvalExpected by end of December '25
New 0.2 crore ton pellet plant commissioningTargeted by end of November '25
CRM complex project total costINR900 crores, INR600 crores debt, balance from internal accrual
BESS project total costINR700 crores, 60% debt, balance from internal accrual and equity
GPIL equity infused into BESS projectINR175 crores
Additional solar power capacity approved250 MW, in addition to earlier 125 MW, for captive use
Solar project internal rate of return~24% (per management)
FY27 iron ore mining target0.47 crore to 0.5 crore tons
FY27 pellet production target0.4 crore tons bare minimum
CRM and BESS commercial production targetApril '27 (FY28)
Preferential issueINR100 crores, majority taken by promoters