Key Takeaways
- Profitability hit by input costs and mining constraints: Margins fell sequentially as elevated market iron ore costs, higher coal prices from the West Asia crisis, and lower captive mining output compressed pellet and DRI spreads.
- Mining ramp-up is the single biggest catalyst: Tree-cutting approval is expected imminently, unlocking overburden dumping space; management targets 70–80% mining capacity from Q1 FY28, which would slash external ore purchases and restore high-grade pellet merchant sales.
- BESS project nearing first revenue, with first-mover advantage: The 20 GW line is on track for June–July '27 commissioning; management acknowledged alarming industry capacity announcements but stressed its 18–24-month lead over paper plans.
- Guidance revised down on mining and pellets: Full-year mining and pellet production targets were cut, and Q3 margins are guided flat to Q2; a meaningful recovery is pushed to Q4 and, more substantially, FY28.
- What to watch next quarter: Whether the tree-cutting permission actually arrives and converts into Q4 mining volumes, the pace of BESS container dispatches, and any update on the stalled steel plant approvals.
Mining: The Bottleneck and the Unlock
- Overburden dumping constraint: Mining production in Q2 was lower because of space constraints for dumping overburden; the new land allotment is exclusively for dumping, and once dumping at higher capacity begins, mining output will automatically improve.
- Tree-cutting approval: Expected "anytime this week" (week of Nov 16, 2026); management is confident the permission is at the last stage of a long-drawn process, though it holds no official document to share.
- Ramp-up timeline: After permission, ~4 weeks for land clearing, with use starting from 2nd December; Q4 will see slight improvement, and from Q1 FY28 the company expects to achieve close to 70–80% of mining capacity.
- Ari Dongri exploration: 80% of exploration is complete; the remaining 20% is possible only after reaching a certain mining level in the next 12–18 months, and reserves may increase from 8 crore tons to 9–9.5 crore tons, not more.
- Mine life: The 8 crore ton base case supports full-capacity operation for the next 15 years.
- Boria Tibu expansion: Capacity to increase from 0.07 crore tons to 0.4 crore tons by FY31; purchases and TOR filing for environmental clearance have already started, with a 0.4 crore ton beneficiation plant planned at ~40% recovery, yielding a 15–17 year mine life post-expansion.
Abhishek Agrawal: "The tree cutting approval is expected anytime soon this week. It can come today also, maybe tomorrow also. So as I mentioned earlier, we will be getting all the clearances by Q3, so we are very much on track."
Pellet & Steel Margin Dynamics
- Pellet margin compression: Operating margins fell due to higher input iron ore costs and energy costs; high-grade pellet merchant sale was zero because mine production was used captively for steelmaking, forgoing a ₹1,000+/ton premium on 50k–1 lakh tons that was previously sold.
- Current pellet EBITDA: Only ₹500–₹700/ton because market fines are expensive and fuel cost is high due to the war situation.
- Coal and power cost impact: Coal cost up ₹1,000–₹1,500/ton in DRI and power cost up ₹0.50–₹0.75/unit due to the war, causing roughly ₹15 crores quarterly loss from DRI coal and ₹25–₹30 crores from the power side.
- Finished price offset: Finished prices also rose substantially (pellet from ₹36,000–₹38,000 to ₹43,000; DRI from ₹24,000 to ₹29,000), so management does not call it a straight EBITDA loss on the DRI/power side, except for pellet where lower mining volume and high-grade sale caused a straight loss.
- Pellet EBITDA at full mining: At a ₹10,000/ton pellet price and full mining capacity, EBITDA would exceed ₹4,000/ton (~50% margin), with production cost not exceeding ₹5,500–₹6,000/ton.
- Pellet price outlook: Management sees a sustainable band of ₹9,500–₹10,500 ex-Raipur in today's market conditions, and believes iron ore imports will not affect domestic pellet prices.
- External ore sourcing trajectory: H2 FY27: ~0.2 crore tons full-year; FY28: ~0.05 crore tons max; FY29 onwards: 100% captive. From October '27, the company expects to start mining at 0.6 crore capacity after the monsoon.
- SMS integration benefit: The steel melting shop started commercial production with enhanced capacity from 5.25 lakh MT to 5.75 lakh MT, enabling almost 100% captive use of sponge iron in billet manufacturing, driving higher value addition and improved operating margins.
- Steel supply chain (ex-pellet): All other units are producing at desired capacity; the entire supply chain from DRI to billets is doing well, getting a healthy premium on billets because of PGCIL approval, barring energy costs which are up due to the war.
Abhishek Agrawal: "Our production cost of pellet will not be more than ₹5,500–₹6,000. At ₹10,000, we will be doing EBITDA margins of ₹4,000, which is almost about, yes, 50%, yes."
BESS: Execution, Margins, and Competitive Risk
- 20 GW line: First lot of machines dispatched from China after all testings; first container expected by end of Q1 or early Q2 (June–July '27).
- 3 GW line (B2C): A new smaller-container product line (261 kWh and 418 kWh) targeting commercial and industrial backup power as a DG replacement; commissioning targeted by December '27, with capex of ₹135 crores and no additional land required.
- First-year utilization: Should reach 10–20% by March '28, producing 5 GW in the first year.
- Captive consumption strategy: Target of 40–50% of 20 GW line output consumed via own tender bidding through the newly formed subsidiary Godawari Energy Solutions Limited; also exploring tying up with big tender participants on back-to-back guarantees.
- Long-term margins: 5–7% only, with high volume turnover; on 80% capacity (15 GW), turnover of ~₹13,000 crores and EBITDA of ~₹600 crores annually, with a payback of 3–3.5 years on the maximum side.
- Margin discrepancy flagged: An analyst noted the annual report stated 12–13% margin, while management had earlier said 7–8% and now says 5–7%. Management acknowledged the discrepancy but did not explain or reconcile the figures.
- 628 Ah cell technology: Expected to deliver 4–5% saving on operating cost, adding ~1.5% additional EBITDA by using high-capacity cells for the 5 MW container.
- Overcapacity risk: Management admitted that the capacity announced by different players in the last six months is "alarming" on paper, but stressed that announce-to-execute is 18–24 months, and GPIL's proximity to commissioning secures a first-mover advantage for at least the next couple of years.
Abhishek Agrawal: "On paper it is. If you ask me very honestly, yes, in last six months, the amount of capacity has been announced by different players. It is alarming, but as again I'm saying, it's still on paper to announce and execute a project is a good 18-months to 24-months of timeline. And we are very close to commissioning our plant. So that first mover advantage we will definitely get for at least next couple of years."
New Projects and Strategic Shifts
- CRM complex relocation: The 0.07 crore ton CRM complex shifted from Chhattisgarh to Maharashtra (Bidkin) to avail incentives under the state's Mega status policy, including discount in duty tariffs, interest subvention, and a gross SGST refund of 9% on sales within Maharashtra; Bidkin is a plug-and-play model with infrastructure delivered to doorstep.
- Container manufacturing line: Board approved ₹100 crores capex for a container manufacturing line alongside the CRM complex, shifted from an earlier proposal with the BESS project for operational synergy; commissioning expected by March '27.
- CRM commissioning: Envisaged for December '27, might stretch to March '28.
- Steel plant on hold: Plans remain on hold; the company is still waiting for approvals, especially on the water side, and has not succeeded in getting the desired approval.
- Group captive solar investment: Approved ₹26 crores investment for a 26% stake in SolarCraft Power India 32 Limited for a 50 MW solar project under a group captive arrangement, a diversion from the existing strategy of setting up solar on GPIL's own balance sheet.
- EV dumpers: Capex of ₹100 crores approved for deployment of 50 EV dumpers across iron ore mines and plant operations.
- Inter-corporate loans policy change: All inter-corporate loans are being called back as per agreement; no further disbursement going forward due to large capex plans, with all loans to be returned within the next 9–12 months.
Abhishek Agrawal: "Since we have started investing now, and our capex plans are huge going forward, we have decided to call back all the loans as per the agreement, and after that, there will be no disbursement of corporate loans anymore."
Balance Sheet and Funding
- Cash position: ~₹900 crores of free cash as on date; management does not foresee any cash crunches or problems going forward.
- Funding strategy: Management has ensured enough free cash flows and generation, and has taken long-term bank loans to keep funding projects; no further delays in execution due to cash deployment are expected.
- BESS financial closure: Achieved with credit facilities aggregating ₹2,795 crores sanctioned.
Sanjay Bothra: "We have around INR900 crores of free cash flow, free cash as on date. So we do not foresee any cash crunches or cash problems going forward."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Tree-cutting approval | Permission expected at last stage of process | "This week" (week of Nov 16, 2026) |
| Mining ramp-up | Slight improvement in production | Q4 FY27 |
| Mining ramp-up | Achieve close to 70–80% of capacity | Q1 FY28 |
| Q3 margin | Similar to Q2 | Q3 FY27 |
| Margin recovery | Marginal improvement | Q4 FY27 |
| Full margin recovery | Back on track | Q1 FY28 |
| Beneficiation plant commissioning | Strengthen captive iron ore security, improve pellet quality | Q3 FY27 |
| High-grade pellet merchant sale | Resume once mining production ramps up | Q4 FY27 |
| Pellet volumes | All pellet plants running at full capacity with substantial jump | Q1 FY28 |
| External iron ore sourcing | ~0.05 crore tons max | FY28 |
| External iron ore sourcing | 100% captive | FY29 onwards |
| 20 GW BESS commissioning | First container dispatch | June–July '27 |
| 3 GW BESS commissioning | New B2C product line | December '27 |
| BESS first-year utilization | 10–20%, producing 5 GW | By March '28 |
| CRM complex commissioning | May stretch | December '27 to March '28 |
| Container line commissioning | Alongside CRM complex | March '27 |
| 100 MW solar project | Delayed by couple of months | December 2026 |
| Inter-corporate loans | All loans returned, no further disbursement | Next 9–12 months |
| Boria Tibu expansion | Capacity increase from 0.07 to 0.4 crore tons | FY31 |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue | ₹1,632 cr, up 25% YoY |
| H1 FY27 revenue | ₹3,382 cr, up 29% YoY |
| EBITDA margin | 12%, down from ~20% in prior quarters due to elevated iron ore sourcing cost and higher coal prices, and lower pellet realization |
| PAT margin | 5.2% |
| H1 FY27 EBITDA margin | 15.7% |
| H1 FY27 PAT margin | 9.1% |
| Iron ore mining production guidance (FY27) | 0.25 cr tons, revised down from 0.34 cr tons |
| Iron ore pellet production guidance (FY27) | 0.35 cr tons, revised down from 0.44 cr tons |
| Pellet EBITDA per ton | ₹500–₹700, down from normalized levels due to market iron ore sourcing and zero high-grade merchant sales |
| High-grade pellet premium forgone | ₹1,000-plus per ton, merchant sale of high-grade pellets completely zero in recent months |
| Steel melting shop capacity | 5.75 lakh metric tons, enhanced from 5.25 lakh metric tons; expanded capacity now operational |
| Benchmark iron ore price (early Nov) | $90–$92 per ton, expected to average ~$90 per ton in near term |
| Domestic crude steel production growth (H1 FY27) | 2.9% YoY |
| Finished steel consumption growth (H1 FY27) | 7.6% YoY |
| 20 GW BESS project credit facilities sanctioned | ₹2,795 cr, comprising term loan of ₹700 cr for BESS project, working capital fund-based limit of ₹100 cr, non-fund-based limit of almost about ₹2,000 cr |
| 3 GW BESS project capex | ₹135 cr, targeted commissioning by March '28 |
| BESS long-term margin expectation | 5%–7% |
| Free cash as on date | ~₹900 cr |
| Inter-corporate loans outstanding | ~₹120 cr, at 12%–15% interest; all to be returned within 9–12 months |
| Captive power capacity expansion | 190 MW to 290 MW; 25 MW solar commissioned May '26, 100 MW solar expected Dec '26, 45 MW BESS storage for captive solar power plant expected Dec '26 |
| EV dumpers capex approved | ₹100 cr for deployment of 50 EV dumpers across iron ore mines and plant operations |
| Ari Dongri iron ore reserves | ~8 cr tons, mine life ~15 years at 0.6 cr tons/year full capacity |
| Boria Tibu iron ore reserves | ~7.5 cr tons (low grade BMQ), usable reserves ~2.5–3 cr tons at 35%–40% recovery; mine life ~15–17 years after expansion |