Key Takeaways
- Margin explosion on lower revenue: EBITDA jumped 80% YoY to ₹331 Crores while revenue fell 11%, lifting EBITDA margin from 13% to 25%, driven by higher pellet realizations and solar-powered cost savings.
- Pellet exports opened a new valve: Exports to China began in December, with another order imminent and European 66-grade discussions underway, offering a release for surplus production that domestic markets alone could not absorb.
- Greenfield plan locked after deliberation: The integrated steel plant is now fixed at 0.2 crore tons of flat products (HR coil), with coke oven scrapped and captive thermal power dropped, slashing the capex estimate to ₹3,000 Crores.
- Solar is the margin engine: 145 MW commissioned, energy cost already down ₹1/unit to ₹3.75, with another 65–75 MW planned; mining operations are now near-100% green-powered.
- What to watch next quarter: Whether Q4 books the pellet export volumes shipped in January, the trajectory of steel demand once elections pass, and the Supreme Court hearing on iron ore exports at month-end.
Pellet Strategy & Exports
- Realization drove the quarter: Pellet selling price rose from ~₹8,500 to ~₹10,200 per ton YoY, the single largest contributor to the EBITDA surge, while other product realizations declined.
- Export channel activated: All exports currently go to China, with one more order closing at month-end and ongoing discussions for future deliveries; European buyers are being courted for 66-grade pellets, with supply expected to begin after March.
- Captive-first policy: Pellets are consumed captively in steelmaking first, with only the surplus sold; management stated they never reduce steel production to free up pellet sales.
- Sales volume dip is temporary: Q3 pellet sales volume dropped 15% QoQ because inventory piled up at the plant and port; that inventory was exported in January and will reflect in Q4 volumes.
- Capacity expansion re-phased: Pellet capacity was cut from 0.3 crore tons at once to 2+0.1 crore tons in phases, because buying market iron ore for pellet-making is no longer commercially viable long-term given India's iron ore supply constraints.
Agrawal: "Buying iron ore from the market and then making pellet in the long term I do not see it is commercially viable anymore, the capacities of iron in India and the supply of iron ore, so to integrate the iron ore mines with the pellet plant capacity we decided to reduce the capacity."
Greenfield Steel Plant: The Final Blueprint
- Capacity frozen at 0.2 crore tons: After extended deliberation, the company settled on 0.2 crore tons focused on flat products (HR coil), dropping the earlier idea of expanding into long products.
- Coke oven scrapped entirely: Instead of building a coke oven, the company will directly import coke for the blast furnace, citing Indonesia's 2-crore-ton coke capacity and the capex savings from avoiding oven construction.
- No captive thermal power: The plant will not include a coal-based captive power plant; power will be sourced via a group captive solar arrangement, which management says is both cheaper (~₹3.5/unit vs ₹4–5/unit for coal) and lower in carbon emissions.
- Capex halved: The combined effect of scrapping the coke oven and dropping captive thermal power brings the projected cost to ₹3,000 Crores, down from the earlier ₹6,000 Crores.
- Funding from internal accrual: Both the ₹1,000 Crores for mining/debottlenecking/pellet plant and the greenfield capex are expected to be funded from internal accruals; the company remains debt-free.
- Timeline: Environmental approval is awaited after the completed public hearing; commissioning is expected 36 months from receipt of that approval, with a start likely in FY2026.
Gandhi: "Today operating a coal-based power plant that you do not have any captive coal mines and you have seen a picture everything from the open market the power cost varies from anything between Rs.4 to Rs.5 unit on the yearly average and when you do the solar plant the yearly average is not more than Rs.3.5, so commercially also will be saving on the operating cost and on the carbon side also will be saving on the emission side."
Mining: The Cost Moat
- Captive cost advantage is structural: Captive iron ore landed cost is ₹2,800/ton versus a market price exceeding ₹6,000/ton, a gap that widened post-COVID as merchant mining supply contracted under the new MMDR auction regime, leaving OMC as the dominant merchant supplier.
- Ari Dongri expansion is the near-term catalyst: The revised mining plan has been filed and the public hearing is expected to conclude in Q1 FY2025, with environmental approval to follow; production will then ramp gradually to 0.5 crore tons in FY2025 and 0.6 crore tons in FY2026.
- Boria Tibu on a longer fuse: The mine was closed due to commercial viability and lower-grade ore; the company plans to beneficiate low-grade ore for plant use, but the bare minimum timeline to commence operations is 30–36 months, with the environmental approval application yet to be filed.
- Mining is going green: Solar has been installed at mining operations, making them close to 100% captive on green power.
Solar: The Margin Multiplier
- Energy cost already falling: 145 MW of solar is now commissioned; the average energy cost per unit has dropped from ₹4.75 to ₹3.75, a ₹1/unit saving, with further reduction expected as pending capacity comes online.
- Full impact from Q1 FY2025: The 25 MW commissioned in Q3 partly impacts Q4, but the full quarterly benefit of all commissioned solar capacity will only be visible from Q1 of the next financial year.
- More solar in the pipeline: Another 65–75 MW will be installed to power the new pellet capacity, and the greenfield plant will use a group captive solar model.
- Balance capacity delayed by land: Some solar capacity could not be commissioned due to non-availability of contiguous land; the company is working to purchase land and will install it in due course.
Steel & Ferroalloy Operations
- Sponge iron going fully captive: With steel capacity increased via new furnace commissioning, all sponge iron produced will be consumed captively for value-added steelmaking; sponge iron sales will drop to zero in the next financial year.
- Ferroalloy market at rock bottom: Prices are subdued and the international market is weak; the only support to profitability is the reduction in power cost from solar. Management sees no recovery unless export demand picks up, since India produces surplus ferroalloys for export.
- Steel demand soft near-term, positive structurally: Demand is currently weak with elections approaching, but Indian steel consumption and production are rising month-on-month and year-on-year, and the government's 11% infrastructure capex increase supports long-product demand.
- Coal price benefit deferred: Because the company holds 45–60 days of inventory and transit material, the impact of lower coal prices will only appear in Q1 FY2025 financials, not Q4.
Company Speaker: "The only caveat is how the steel market and the prices would behave is the prediction. Otherwise definitely it is sustainable."
Regulatory & Approvals Pipeline
- Consents received: Consent to operate the sponge iron plant at an enhanced 595,000 tons (up from 495,000) and the steel melting shop at 525,000 tons (up from 400,000) have been secured; the enhanced billet capacity is already operational.
- Environmental approval for pellet expansion: Received; phase one completion is estimated for Q1 FY2026.
- Integrated steel plant: Public hearing completed; environmental approval awaited, with commissioning expected 36 months from receipt.
- Ari Dongri mine expansion: Public hearing expected to conclude in Q1 FY2025, followed by environmental approval; a beneficiation plant will be set up within 15 months of that approval.
- Supreme Court case on iron ore exports: The next hearing is scheduled at the end of this month, introducing a binary regulatory risk to the export strategy.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Ari Dongri mining capacity ramp | Production to reach 0.5 crore tons | FY2025 |
| Ari Dongri mining capacity ramp | Production to reach 0.6 crore tons | FY2026 |
| Pellet plant phase one completion | Phase one commissioned | Q1 FY2026 |
| Integrated steel plant commissioning | 36 months from environmental approval receipt | ~FY2028 (approval awaited) |
| Greenfield project start | Construction begins | FY2026 |
| Coal price impact on financials | Lower coal costs visible in P&L | Q1 FY2025 |
| Solar power full quarterly impact | All commissioned capacity reflected in results | Q1 FY2025 |
| Boria Tibu mine operations commence | Bare minimum timeline | 30–36 months from now |
| Sponge iron external sales | Sales drop to zero | Next financial year (FY2025) |
| Dividend or buyback increase | Open to increase once profitability improves and capex need declines | No near-term date; conserving cash for capex |
Key Metrics
| Metric | Q3 FY24 |
|---|---|
| Revenue | ₹1,309 cr, +1% QoQ and -11% YoY |
| EBITDA | ₹331 cr, +80% YoY |
| EBITDA margin | 25%, vs 13% in Q3 FY23 |
| Profit after tax | ₹229 cr, +79% YoY |
| PAT margin | 17.5% |
| Net cash on balance sheet | ₹768 cr as of December 2023 |
| Revenue (9M FY24) | ₹3,926 cr, -12% YoY |
| EBITDA (9M FY24) | ₹999 cr, +13% YoY |
| EBITDA margin (9M FY24) | 25%, vs 20% in 9M FY23 |
| PAT (9M FY24) | ₹717 cr, +15% YoY |
| Iron ore mining production | 565,000 tons, +9% QoQ and -13% YoY |
| Captive iron ore landed cost | ₹2,800/ton vs market price of over ₹6,000/ton |
| Pellet realization | ₹10,500/ton, +27% YoY and +6% QoQ |
| Pellet realization (9M FY24) | ₹10,205/ton, +11% YoY |
| Sponge iron production guidance (FY24) | 590,000 tons, increased from earlier guidance |
| Steel billet production guidance (FY24) | 475,000 tons, increased from earlier guidance |
| Solar power capacity commissioned | 145 MW out of 173 MW planned |
| Average energy cost per unit | ₹3.75, down from ₹4.75 average; saved ₹1/unit |
| Pellet sales volume target (Q1 FY25) | 4 to 4.5 lakh tons |
| Integrated steel plant capex | ₹6,000 cr for 0.2 crore ton capacity |
| Total capex over next five years | ~₹7,000 cr |
| Ferroalloy prices | ₹63,000 to ₹65,000/ton |
| Pellet margin (longer-term average) | ₹7,000 to ₹7,500/ton |