Godawari Power & Ispat Ltd Q3 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/zu9wkgv4ld9d6wf2142ngh0k.pdf

Key Takeaways


The Quarter: Accident, Oversupply and Resilience

Abhishek Agrawal: "Domestic demand is quite strong because in the last few weeks, the entire supply chain of domestic has gone up right from DRI to billets to steelmaking... sitting in February, we are almost booked till end of this quarter."

Mining: The Backward Integration Catalyst

Dinesh Gandhi: "This marks a significant milestone in strengthening GPIL raw material security, backward integration, while reinforcing its long-term visibility and competitive positioning."

The Battery Venture: A High-Stakes Diversification

Abhishek Agrawal: "No, no, no. We've got to be a little cautious because it's totally a different scene. There will be huge competition. So we will only invest into the second phase once we are able to stabilize the line for the first phase."

The Steel Plant Decision: Binary and Imminent

Abhishek Agrawal: "In best possible -- worst possible scenario, I think by end of -- so which will be the annual Board meeting, which will happen in April and May, we will have full clarity on that. So either we are going ahead or we're not going, we'll drop it. That's very clear."

Pellet, CRM and the Downstream Build-Out


Guidance & Commitments

CommitmentSpecificsTimeline
Ari Dongri mining ramp-upCommercial operations begin; reach 0.6 crore ton run rateFebruary 2026 start; run rate by October 2026
Beneficiation plant completion0.54 crore ton crushing and beneficiation plantEnd of Q2 FY27
CRM complex commissioningConstruction begins April 2026Commissioning March 2027
Solar expansionPhased completion of 165 MW to 540 MW expansionMarch 2026 to March 2027
BESS project commissioning45 MWh battery storage for captive mine powerQ4 FY27
BESS manufacturing first phase20 GW line, 40-50% utilization, ~INR5,000 cr revenue, ~7% marginApril 2027 to March 2028
Steel plant decisionGo or no-go decision at annual Board meetingApril/May 2026
Pellet production FY27Operate above 90% capacity, produce >0.4-0.42 crore tonsFY27
Ardent Steel stake saleDisinvestment of 37.85% stake for ~INR91 croresBy March 2026
Peak debtGross debt ~INR1,500 croresFY27
Carbon capture R&D project5 ton/day capture pilot with IIT BombayBy Diwali (~10 months)
Boria Tibbu beneficiation plantNew EC filing, plant erectionEC filing Q1 next FY; plant by FY30

Key Metrics

MetricQ3 FY26
RevenueNot stated for Q3 standalone; 9M FY26 revenue dipped slightly YoY due to softer realization
EBITDA margin20%, expanded from 17% in Q3 FY25
PAT margin13%, sustained despite softer realization and lower pellet volumes
9M FY26 EBITDA margin22%
9M FY26 PAT margin14%
Iron ore mining production growth+46% YoY in Q3
Value-added steel products sales growth+15% YoY
Pellet sales volumeDeclined temporarily due to pellet plant accident in late September 2025; plant shut for ~40 days in October
Pellet production volume guidance FY26~0.3 crore tons, plus/minus 5%
FY27 capex guidance~₹2,000 cr, plus/minus ₹200 cr
FY26 capex spent (till Q3)~₹600–700 cr
Iron ore mining capacity (Ari Dongri)EC received to expand from 0.24 crore tons to 0.6 crore tons; CTO expected in February 2026
Pellet capacityExpanded to 0.47 crore tons (from 0.27 crore), 1.7x increase; new 0.2 crore ton plant commissioned December 2025
FY27 pellet production target>0.4 crore, 0.42 crore tons, operating at >90% utilization
FY27 mining volume target0.5 crore tons; run rate of 0.6 crore tons expected by October 2026
BESS manufacturing capacity20 gigawatt initial capacity; capex of ₹1,025 cr; commissioning targeted Q4 FY27
BESS first-year utilization assumption40–50% plant load, 8–10 gigawatt production
BESS first-year margin assumption~7% operating margin
CRM complex capacity0.07 crore tons; capex ~₹800 cr; commissioning targeted March 2027
CRM margin expectation8–10% EBITDA margin initially
Captive solar capacityExpanding from 165 MW to 540 MW (over 3x); phased completion March 2026 to March 2027
Battery energy storage (captive)45 MWh capacity being set up for iron ore mine power
Disinvestment of Ardent Steel stake37.85% stake divested for ~₹91 cr; expected completion by March 2026
Global iron ore price outlook$95–$110/ton range in calendar 2026; currently ~$102
NMDC iron ore priceRange-bound at ₹4,500–₹5,500/ton; current ₹3,900/ton (statutory levies excluded from January 2026)
Pellet price₹8,500–₹10,000/ton during calendar 2026; currently ~₹10,000/ton
Pellet price increase QoQ (Q4 vs Q3)Up ~10–12%
DRI price increase QoQUp ~20%
Semifinished/finished steel price increase QoQUp ~12–13%
Ferro alloy priceHovering ₹70,000/ton ±5%; currently ~₹74,000/ton
Imported coal cost (Q4)~₹11,000/ton absolute value
DRI per ton contribution (Q1 FY27)₹8,000
Carbon intensity2.4–2.45 levels currently
ESG rating (CARE Edge)76.6 score
FY30 turnover target~₹25,000 cr
Peak gross debt (FY27)~₹1,500 cr; net debt lower depending on cash flow
New labour law impact~₹7–8 cr annually, ~₹70–80 lakh per month