Godawari Power & Ispat Ltd Q4 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/n58fmzgedbpbbsle5rc5bipv.pdf

Key Takeaways


Margin Drivers & Cost Structure

Dinesh Gandhi: "See, overall our operating margins have increased by 4%. There was an average about 10% to 12% fall in the sponge iron prices throughout the year. The average realization for the FY24 and 8% increase was there in the pellet. So, if you take all these, the 4% increase in operating margin, which is about closer to about Rs. 200 crore on 5000 crores sold is as a result of higher operating efficiency because of the solar power plant, new turbine and higher capacity in the steel plant."

Expansion Pipeline & Timelines

Abhishek Agrawal: "As of now, we are firm on our thought process after a lot of due deliberation. We have no intention of setting up a coke oven in the phase-1... commercially also, it doesn't make sense to invest in coke oven right now, where you're able to get import cheap coke and using the blast furnace."

Commodity Price & Market Dynamics

Abhishek Agrawal: "I would say pellet prices and iron ore prices domestically will remain higher compared to the export market for at least a couple of quarters."

Segment & Volume Trends


Capital Allocation & Balance Sheet

Dinesh Gandhi: "we don't think that we'll be able to require to take more than Rs. 1,500 crore kind of debt in order to complete the new project. So, that's everything should go from the internal accrual."

Guidance & Commitments

CommitmentSpecificsTimeline
Rolling mill commissioningModification complete, trial production underway; full commissioning expectedCurrent quarter (Q1 FY25)
20 MW solar project commissioningPart of the 173 MW total solar capacity; to be operationalBy June 2024
Public hearing for Ari Dongri mine expansionPlanning to hold the hearingJune or July 2024
Beneficiation plant at Ari Dongri0.6 crore ton capacity; construction starts after environmental approval and consent from State Pollution Control BoardWithin 15 months of receiving approvals
New pellet plant and 70 MW solar plant0.2 crore ton pellet capacity with dedicated solar powerQ1 FY26
Environmental approval for steel plant expansionHopeful to receive clearanceEnd of Q2 or early Q3 FY25
Integrated steel plant commissioning0.2 crore ton HR coil greenfield project; 30-36 months from environmental approvalH2 FY28 partial revenue; FY29 full capacity
Mining production ramp-upTarget 0.3 crore tons in FY25, ramping to 0.6 crore tonsFY26 for full 0.6 crore tons
EBITDA marginMaintain healthy range of 20%-25%; FY24 margin of 24% is the minimum floor if current prices sustainOngoing
Boria Tibu mine restartNo iron ore expected before FY28 at the earliestFY28 or later
South32 manganese mine restartForce majeure declared; mine expected back in productionProbably by end of Q3 FY25
Domestic pellet/iron ore price premium over exportsExpected to persistAt least a couple of quarters
Hira Ferro Alloy volume recoveryFurnace modification shutdown complete; volume growth expectedFrom Q1 FY25
FY25 revenueNo additional revenue from new capacity or CAPEX; maximum capacity reached across all operationsFY25
Integrated steel plant long-term EBITDA₹10,000 per ton on a conservative longer-term average basisFY29 and beyond

Key Metrics

MetricQ4 FY24
Revenue₹1,530 cr, +16% YoY
EBITDA₹329 cr, +19% and +29% YoY against ₹220 cr
EBITDA margin22%, vs 20% in Q4 FY23
PAT (full year FY24)₹937 cr, +18% YoY
Full-year revenue₹5,455 cr, -5% YoY due to lower trading sales and pellet production
Full-year EBITDA margin24%, up from 20% in FY23
Net cash balanceOver ₹1,000 cr
Cash flow from operations (FY24)₹1,044 cr, +5% YoY
Shareholder distribution (FY24)₹355 cr, 45% of FY23 net profit, via FY23 final dividend and ₹250 cr buyback
Captive iron ore landed cost₹2,800/tonne, vs market price of ₹6,800/tonne
Iron ore pellet realizationOver ₹10,000/tonne, +8% YoY
Pellet production (FY24)-7% YoY, due to Q1 maintenance shutdown
Iron ore mining production (FY24)-11% YoY, due to Boria Tibu mine closure
FY25 iron ore mining production guidance0.3 cr tons, vs 0.24 cr tons in FY24
FY25 steel billet production guidance0.05 cr tons
FY25 ferro alloy production guidance80,000 tons
Integrated steel plant expansion CAPEX₹6,000 cr, for 0.2 cr tons via blast furnace route, commissioning 36 months from environmental approval
Pellet plant Phase-1 expansion CAPEX₹600 cr, adding 0.2 cr tons to reach 0.47 cr tons total capacity
Beneficiation plant CAPEX₹200 cr, ₹24 cr already spent, 15 months from environmental approval
Solar power capacity commissioned (FY24)145 MW out of 173 MW proposed, including 45 MW in FY24
Additional solar power capacity approved70 MW, to meet pellet plant power requirement
High-grade pellet price (current)₹12,500/tonne
63Fe pellet price (current)₹11,300/tonne, up from ₹8,800 in July and ₹10,500 in December
Silico manganese price (current)₹85,000-87,000/tonne, up ~30% from ~₹65,000 last month
Rolled product capacity target (FY25)3.5 lakh tons, full capacity of 4 lakh tons post-debottlenecking
Employee expense annual increment10-11% on average, plus ₹3 cr one-time provision for senior-level ESOP in Q4
Pellet sales mix50% lower grade (56 Fe), 50% higher grade (63 Fe)
Premium for high-grade pellets$20/tonne or ₹1,500/tonne yearly average