Key Takeaways
- Q4 delivered a sharp sequential rebound: Revenue jumped 41% QoQ as a new pellet plant ramped up, mining volumes expanded, and rolled product output surged after a mill upgrade.
- FY27 guidance embeds a margin reset: Management guided to 24–25% EBITDA margins at current market levels, down from 23% in FY26, as lower-margin new businesses begin contributing.
- The capex apology matters: Management admitted a wrong estimation on the integrated steel plant cost, now pegged at ₹7,000 crores, and issued a public apology, a rare admission that resets credibility expectations.
- The 2031 vision is a bet on volume over margin: A top line of ~₹30,000 crores and PAT of ₹3,000 crores implies a 10% PAT margin, reflecting dilution from BESS and CRM, which carry 7–10% margins.
- What to watch next quarter: Whether pellet exports actually begin if domestic demand stays weak, the pace of Ari Dongri mine ramp-up toward the 0.6 crore ton rated capacity, and any stabilization in steel prices after the recent 10% correction.
Q4 Performance: The Sequential Jump
- Volume-driven rebound: Q4 revenue grew 41% QoQ, supported by a production ramp-up across pellets, sponge iron, and structural rolled products, plus higher sales volumes and improved realizations.
- Three drivers of the EBITDA delta: Carryover inventory of 89,000 tons of iron ore pellets from Q3 was sold in Q4; the new 2-million-ton pellet plant reached 70% capacity; and mining production increased after EC approval in late February, enabling an extra 2–2.5 lakh tons of mining in March.
- Inventory gain added ~₹20 crores: Unsold pellet stock of roughly 90,000 tons carried from Q3 was sold during the quarter, contributing a one-time gain.
- Rolled products hit stride: The RR Ispat Rolling Mill modification completed at end of Q3; production increased substantially from Q4 onward, and the mill now carries a healthy order book of almost six months.
- Pellet pricing lagged the market: The EC delay prevented full-capacity mining of high-grade ore, forcing the company to make 63-grade commercial pellets instead of premium-grade pellets that command a >₹1,000 premium, so realized pricing did not move with the market.
- Cash flow strengthened: Operating cash flow improved 29% to ₹1,157 crores, driven by strong operational performance and efficient working capital management.
Mining & Raw Material Integration
- Ari Dongri expansion is the near-term catalyst: Environment approval and consent to operate received in February 2026 for increase from 2.35 to 0.6 crore tons; ramp-up has begun in a phased manner.
- FY27 mining guidance: Actual mining of 0.4–0.43 crore tons, yielding net usable iron ore of 0.34 crore tons after accounting for BMQ waste; rated capacity of 0.6 crore tons expected by end of Q3 or early Q4, with net usable rising to ~0.45 crore tons from FY28.
- Boria Tibu contributes modestly in FY27: About 0.05 crore tons mined, net usable about 0.03 crore tons; expansion to 0.4 crore tons with beneficiation targeted online by FY30, yielding ~0.15 crore tons usable.
- Iron ore purchases to fall sharply: Will buy roughly 0.15 crore tons (0.1 crore tons) for the pellet plant this year; that number will drastically come down post-Diwali once rated mining capacity is achieved after the monsoon.
- Landed cost of ore guided at ₹3,000–3,200/ton: Similar level for the full year, with substantial reduction expected from Q3–Q4 onward as captive mining scales.
- Mine-side beneficiation saves ₹150/ton: Previously beneficiation was done inside the pellet plant in Raipur, incurring freight on waste material; from Q3 onward, beneficiation inside the mine eliminates that freight cost on final concentrate sent to plant.
- Beneficiation economics: Average mine grade is 59–60 Fe; beneficiation upgrades to 67 concentrate for 65-grade pellets; about 15% of iron ore is wasted as fillings in the process, and for BMQ low-grade magnetite (35–38 Fe) recovery is only about 40%.
Agrawal: "So, the actual mining will be close to about 0.4 crore to 0.43 crore tons this year, because 0.15 crore will be BMQ, where the recovery will be less than 50%. So, about 0.8, 0.08 crore tons of iron ore will be wasted as fillings."
Pellet Business: Capacity, Pricing & Export Optionality
- New pellet plant is India's first gas-based grate-kiln: The 2-million-ton plant commissioned in December 2025 uses advanced natural gas-based technology, shifted from coal gas after signing a 7-year MoU with GAIL for natural gas supply.
- FY27 pellet production guided at 0.4 crore tons: With iron ore net usable at 0.34 crore tons; merchant pellet volume will be about 0.3 crore tons after captive consumption of 0.9–0.1 crore tons.
- High-grade pellet mix improves from Q3: Post-monsoon, as mining production scales up, the product mix of high-grade pellets will start going up drastically, showing a difference in pellet pricing versus the market.
- Export readiness is now explicit: With CBAM and export demand, the company wants to be export-ready; if domestic demand remains weak, management said exports may begin from next quarter, with export realizations only ~$10 below domestic.
- Merchant pellet players face margin squeeze: Management sees no overcapacity now but expects a challenge for merchant players solely dependent on market purchase of iron ore; companies with captive resources like Godawari and Lloyds face no pressure on margins.
- Lloyd's has not hit the Chhattisgarh market: 90% of Lloyd's pellets are going into the Chhattisgarh market; the current lull is due to overall weak steel demand, with prices correcting almost 10% in the last few weeks.
Agrawal: "So, whenever we see domestic demand is on the, for example, today the domestic demand is on the weak side, you might hear where Godawari start exporting pellets from the next quarter."
New Businesses: BESS & CRM
- BESS is a 20 GWh bet with first revenue by March 2027: Soil testing completed, compound wall construction underway; long-term agreements signed with EVE Power for Grade-1 628 Ah LFP cells and with Shanghai Shenyi Roche Energy Technology for BESS Balance of System supply; also tied up with FIMER for PCS and a Gujarat-based developer for EMS.
- Conservative ramp-up guidance: First line commissioning by end of Q4 March 2027; FY28 expected at 5–6 GWh (30–40% utilization); second year scaling to ~70% (12–14 GWh); third year onward ~90% capacity (17–18 GWh).
- Market entry delayed to build credibility: Management intends to go into the market only at end of Q2 (August/September), wanting to ensure delivery capability first before approaching customers.
- BESS margin profile is thin: Management pegs BESS at about a 7–8% margin business, which is why overall margins in the 2031 guidance come down even as top line grows exponentially.
- CRM Complex targets March 2027 commissioning: On-site construction underway; key equipment lines ordered with advance payments released; conservative guidance of 50% utilization in FY28 (about 3–3.5 lakh tons), ramping to ~90% from FY29.
- CRM margin profile also modest: About 7–10% margin business, contributing to the blended margin dilution in the 2031 outlook.
- Phase-2 of BESS is explicitly uncertain: Not included in 2031 guidance; management wants to establish Phase-1, run at full capacity, then decide on Phase-2, which could be capacity expansion or backward integration into cell manufacturing with a technology tie-up.
Agrawal: "We want to get into the market once we know we can deliver after a certain time period. So, we intend to go into the market end of Q2, which is say about September, August."
Integrated Steel Plant: The Capex Reset
- Board approved a 1-million-ton integrated steel plant: Will manufacture structural steel and wire rods; land acquisition and environmental approval in place, consent to establish awaited; discussions with equipment suppliers and project engineering underway; construction expected to begin October 2026.
- Capex revised to ₹7,000 crores after a wrong estimation: Management admitted the error publicly, citing two reasons: government restrictions on import of cokes forced investment in a coke oven plant not originally planned; and the product mix (value-added steel, not TMT or rebar) means the structure mill carries substantial cost compared to a similar-volume commodity mill.
- Blast furnace route chosen deliberately: No intention of using coal-based DRI as it becomes challenging to be cost-effective; gas-based DRI was considered but dependency on imported natural gas made the conventional blast furnace route preferable for Phase-1.
- Focus on long products and CRM, not HR coil: For a CRM complex, the minimum viable HR mill capacity is 0.2 crore tons; to feed a 0.2 crore ton mill, they lacked hot metal and capex would have crossed ₹12,000–13,000 crores; India's HR coil market is oversupplied and imports are always open, so the focus is on value-added steel and long products.
- EBITDA expectation of >20% at full capacity: Management cites the value-added steel product mix and currently limited competition from the Indian market as support for the margin expectation.
- Capex phasing is back-end loaded: FY27 steel capex will hardly be about 10%, mainly for ordering equipment and advances; major capex happens from FY28 onward, with total capex of ₹1,500–2,000 crores in FY27, ~₹3,000 crores in FY28, and ~₹3,000 crores in FY29.
- Debt taken only from FY28: Whatever debt is required will be on account of steel capex; everything else is self-funded from internal accruals.
Agrawal: "I had personally send an apology to all the stakeholders, because for us being in the first time in a blast primary route, we did a wrong calculation. There was a wrong estimation done by us on the CAPEX side. So, again, once again, sincere apologies."
Cost, Fuel & Logistics
- Coal sourcing is 100% imported but flexible: Currently using all imported coal to maximize DRI production; can switch to domestic coal anytime as availability is abundant; monitoring the war situation and may shift to some part domestic coal for DRI if the situation does not die down.
- Diesel cost exposure is being structurally addressed: Transportation cost currently about ₹900/ton, can go up to ₹1,150–1,200 if diesel prices continue to rise; management has invested heavily in EVs in mining (loaders and excavators) and is working on replacing road transportation with EV trucks.
- EV fleet investment already delivering results: Invested in 10 EV dumpers, 24 EV loaders, 15 EV excavators during the year; reduced operating costs nearly 75% and carbon emissions around 88% versus conventional diesel.
- Full EV truck fleet would require ~₹350 crores: At full capacity, need about 350 trucks, with full site capex including charging infrastructure; management is working on this transition and wants it done as soon as possible.
- Solar power expansion underway: Expanding captive solar from 165 MW to 540 MW; 25 MW commissioned yesterday, additional 100 MW expected by July 2026.
Agrawal: "We are carefully monitoring this war situation. And if we feel the situation is not dying down, so going forward, we might shift to some part of domestic coal for DRI."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 revenue | ₹6,000+ crores with new pellet plant at 80–90% capacity | FY27 |
| FY27 EBITDA margin | 24–25% at current market levels | FY27 |
| Ari Dongri rated capacity | 0.6 crore tons mining (net usable ~0.45 crore tons) | End of Q3 / early Q4 FY27 |
| Iron ore beneficiation plant | 0.6 crore ton capacity commissioned | Q3 FY27 |
| CRM Complex commissioning | First line operational | March FY27 / early Q1 FY28 |
| CRM utilization | 50% in FY28 (~3–3.5 lakh tons), ~90% from FY29 | FY28 / FY29 |
| BESS first line commissioning | First line operational | End of Q4 March 2027 |
| BESS ramp-up | 5–6 GWh in FY28, ~70% in year 2, ~90% in year 3 | FY28–FY30 |
| Integrated steel plant construction start | Construction begins | October 2026 |
| Steel plant capex | ₹7,000 crores total; ~10% in FY27, major from FY28 | FY27–FY29 |
| Total capex phasing | ₹1,500–2,000 crores in FY27; ~₹3,000 crores in FY28; ~₹3,000 crores in FY29 | FY27–FY29 |
| Debt drawdown | Debt taken only from FY28 for steel capex | FY28 onward |
| Boria Tibu expansion | 0.4 crore tons mining with beneficiation, ~0.15 crore tons usable | FY30 |
| 2031 PAT target | ₹3,000 crores (~10% PAT margin); excludes BESS Phase-2 | FY31 |
| Solar capacity addition | Additional 100 MW | July 2026 |
| Iron ore price outlook | Prices should remain above $100/ton for the entire year | FY27 |
| Landed cost of ore | ₹3,000–3,200/ton; substantial reduction from Q3–Q4 onward | FY27 |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Revenue | +41% QoQ, supported by production ramp-up, higher sales volume and improved realizations |
| EBITDA | ₹439 cr, +38% YoY and +91% QoQ |
| EBITDA margin (FY26) | 23%, stable |
| PAT | ₹280 cr |
| PAT margin (FY26) | 15%, stable |
| Cash flow from operations (FY26) | ₹1,157 cr, +29% YoY, driven by strong operational performance and working capital management |
| Cash position | ₹837 cr |
| FY27 revenue guidance | ₹6,000+ cr, with new pellet plant operating at 80–90% capacity |
| FY27 EBITDA margin guidance | 24–25%, at current market levels |
| Pellet production guidance (FY27) | 0.4 crore tons |
| Net usable iron ore guidance (FY27) | 0.34 crore tons, from actual mining of 0.4–0.43 crore tons |
| Rolled products volume guidance (FY27) | 3.75 lakh tons |
| BESS Phase-1 output guidance (FY28) | 5–6 Gigawatt hours, 30–40% utilization |
| CRM Complex utilization guidance (FY28) | 50%, about 3–3.5 lakh tons |
| FY27 capex guidance | ₹1,500–2,000 cr, including CRM, BESS and solar |
| Inventory gain in Q4 | ~₹20 cr, from 89,000 tons of unsold pellet stock carried over from Q3 |
| Exceptional loss (consolidated) | ₹17 cr net loss, after Ardent Steel stake sale gain and Godawari Energy write-off |