Key Takeaways
- Volume sacrificed for margin, again: Lead volumes were flat and aluminum volumes halved YoY, yet operating margin rose 200 bps to ~12% because management deliberately traded volume for higher realizations, keeping per-kg profitability at ₹23,000/tonne against its own ₹19,000–₹20,000/tonne guidance.
- Capacity expansion delayed, not derailed: Government licensing delays in Gujarat pushed the bulk of India’s ~125 KT lead capacity addition into Q4 FY26, meaning the major volume ramp will only begin in Q1–Q2 FY27.
- Aluminum is the swing factor: Volumes collapsed ~50% because high metal prices caused scrap aggregators to withhold material; recovery depends entirely on price stabilization and the long-awaited MCX aluminum contract, now cleared by regulators but awaiting an MCX business decision.
- Plastic and rubber are the quiet margin stories: Plastic margins have turned friendly despite ~40% utilization by targeting primary packaging, while the Romania rubber facility generated its first ~₹3.5 crores in revenue and will be disclosed separately from Q4.
- What to watch next quarter: Whether the Mundra and Jaipur lead expansions actually commission and start contributing volume, whether the lithium-ion consent to operate arrives, and whether aluminum scrap flow normalizes enough to reverse the volume collapse.
Volume & Capacity: The Delay Story
- Licensing bottleneck: The Gujarat state government’s consent to operate for new capacity was held up because officials were not regularly attending office during the “Vibrant Gujarat” event; the company already holds the Consent to Establish and calls the remaining step a formality, expecting resolution by end of January or February 2026.
- What gets added in Q4: An 80,000 MTPA lead expansion at Mundra and up to 45,000 MTPA at Jaipur, both targeted for completion by Q4 FY26; some volumes will start in Q4 itself, but the major incremental volume arrives in Q1 and Q2 of FY27, with full ramp-up by Q2.
- India utilization is tight: Domestic capacity is already running above 90% utilization, so the new capacity is needed to relieve the constraint and restore the normal ~45% domestic sourcing mix, which dropped to 25% in Q3 as the company stockpiled raw material ahead of expansion.
- CAPEX back-end loaded: Some CAPEX expected in Q2 and Q3 slipped due to plant setup and approval delays; the bulk now lands in Q4, with total FY26 CAPEX expected to cross ₹200 crores.
- Aluminum expansion on hold: The company is deliberately holding up aluminum capacity expansion until MCX approval for aluminum trading is received, now expected by Q1 FY27; only then will it start expanding aluminum capacities.
- Plastic capacity next year: Plastic capacity expansion will begin next year, with slow growth of ~8–10% expected for the next couple of quarters before an anticipated acceleration.
Yogesh Malhotra: “It is merely a formality, but because of this vibrant Gujarat theme, they are not regularly attending the office. So, that is why the delay is there. But we are very confident that it will happen now in this quarter itself.”
Margin Mechanics: Sacrificing Volume for Profitability
- The trade-off: Management explicitly sacrifices some revenue to maintain margins, shifting material from African plants to India when arbitrage opportunities arise; this quarter’s 200 bps operating margin improvement to ~12% came from better realization, not operational improvements, which take longer to materialize.
- Per-kg profitability above guidance: Realized margin was ₹23,000/tonne against guidance of ₹19,000–₹20,000/tonne; when pressed on whether the company would upgrade its guidance, management declined and reiterated the lower range, implying it expects normalization.
- Lead is hedged, aluminum is not: Lead is 100% hedged, so price fluctuations impact the top line but not the bottom line; aluminum (ADC-12) is not traded on any exchange, making it difficult to hedge, which is why the company has kept aluminum volumes low during price volatility.
- Raw material discount structure protects margin: The company buys scrap at a discount over LME prices; when absolute prices rise, the percentage discount remains the same, so the spread between selling and buying price stays intact.
- Long-term margin ambition: By FY 2028, management expects ₹0.50 to ₹0.75 per kg improvement across all three segments from better operational efficiencies, a better procurement network, and more value-added products.
Yogesh Malhotra: “Sir, I think the margin would remain at around Rs. 19 to Rs. 20, as we mentioned earlier that, we sacrifice some revenues to ensure that these margins are intact.”
Aluminum: The Collapse and the Recovery Bet
- What drove the 50% volume drop: When aluminum prices increase, scrap dealers withhold material and refuse to sell to recyclers, causing a sharp tightening of scrap availability; this is a recurring dynamic, not a structural demand problem.
- Profitability normalization YoY: Last year’s higher aluminum profitability of ~₹20/kg was specifically because the company imported a lot of material into India and rising aluminum prices boosted profitability; this year, profitability has normalized.
- The MCX catalyst: The key regulatory constraint (passing through the Security Contract Regulation Act) is now resolved after ~1.5 years, with clearance from the Ministry of Finance, Ministry of Mines, and BIS; the decision now rests with MCX, which has formed a specification committee, though a CEO change at MCX in November caused some delay.
- Recovery timeline: As prices stabilize and scrap flow normalizes, procurement is expected to improve, supporting recovery in aluminum volumes in coming quarters; management expects normalcy to continue and more aluminum scrap to become available going forward.
New Verticals: Plastic, Rubber, Lithium-Ion
- Plastic margins turn friendly: Despite low capacity utilization of ~40%, plastic segment margins have become attractive because the company is targeting primary packaging, a more profitable niche; the process is slow, requiring product development and customer-specific testing, but management is confident the direction is right.
- Rubber goes live: The Romania rubber facility started operations in Q3 with ~₹3.5 crores in revenue; the company plans to scale up the Romania facility, and the Mundra rubber project is slated for commissioning in Q1 FY27 with revenues expected from Q2 FY27.
- Rubber disclosure begins: From Q4 FY26 onwards, the company will start sharing separate numbers for the rubber segment; until now, rubber was only for in-house consumption with no external revenue.
- Lithium-ion imminent: Consent to operate for the lithium-ion facility is expected in the next couple of days and the facility is expected to become functional in Q4 FY26.
- New vertical discipline: Any new venture, including steel, paper, and lithium-ion recycling, must meet a 25% ROCE threshold; this is group policy applied to all expansions.
Yogesh Malhotra: “It is a slow process… But we are very confident we are making inroads into this, we are developing new products for new customers and… the direction is right but the moment it will start happening it will just take off.”
Regulatory Tailwinds & Structural Shifts
- BWMR and EPR enforcement tightening: Stronger enforcement of Battery Waste Management Rules and Extended Producer Responsibility frameworks has enhanced accountability, leading to more efficient collection channels, reduced leakages to the unorganized sector, improved traceability, and materially increased domestic scrap availability.
- NITI Aayog pushing further: NITI Aayog has recommended strengthening the EPR process and portal, linking all data from the GSTN portal, and further collection rules are being framed, suggesting the regulatory tailwind has more room to run.
- LME license in sight: The company has applied for an LME license and expects to receive it in Q4 FY26, which would enhance its ability to trade and hedge internationally.
- New labor law impact booked: The total impact of the new labor law was approximately ₹4.2 crores this year, with ₹3.5 crores pertaining to previous years and ₹60–70 lakhs pertaining to the nine months of FY26.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Lead capacity commissioning | 80,000 MTPA (Mundra) + up to 45,000 MTPA (Jaipur) completed | Q4 FY26 |
| Lead capacity ramp-up | Major incremental volume begins; fully ramped up | Q1–Q2 FY27 |
| FY26 CAPEX | Cross ₹200 crores | Q4 FY26 |
| LME license | Receive approval | Q4 FY26 |
| Lithium-ion facility | Become functional | Q4 FY26 |
| Rubber segment reporting | Start sharing separate numbers | Q4 FY26 onwards |
| Mundra rubber project | Commissioning, with revenues following | Q1 FY27 (commissioning), Q2 FY27 (revenues) |
| Aluminum capacity expansion | Begin expansion, conditional on MCX approval | Q1 FY27 (subject to MCX) |
| Plastic capacity expansion | Begin expansion | FY27 |
| Long-term margin improvement | ₹0.50–₹0.75 per kg improvement across all three segments | By FY 2028 |
| Installed capacity target | Scale to over 7 lakh MTPA | By FY 2028 |
| Vision 2029 targets | Volume CAGR >25%, profitability growth >35%, ROIC >25%, non-lead revenue to 30%, renewable energy to 30%, energy intensity reduction >10% | By FY 2029 |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Revenue | ₹1,017 cr, flat YoY and QoQ |
| Adjusted EBITDA | ₹116 cr, up 13% YoY and 4% QoQ |
| EBITDA margin | 11.41%+, supported by operating efficiencies and mix improvements |
| PAT | ₹97.67 cr, up 32% YoY |
| PAT margin | 9.60% |
| 9M FY26 revenue growth | 9% YoY |
| 9M FY26 EBITDA growth | 15% YoY |
| 9M FY26 PAT growth | 32% YoY |
| Total volumes sold | 52,982 tonnes |
| Lead volumes sold | 46,269 tonnes |
| Aluminum volumes sold | ~3,500–3,550 tonnes, declined YoY and QoQ on higher metal prices tightening scrap availability |
| Plastic volumes sold | 3,160 tonnes, up 55% QoQ |
| Lead EBITDA per metric tonne | ₹23,000 |
| Aluminum EBITDA per metric tonne | ₹14,215 |
| Plastic EBITDA per metric tonne | ₹10,462 |
| Installed capacity | ~3.40 lakh metric tonnes per annum |
| India capacity utilization | ~90% |
| Overseas capacity utilization | ~65% |
| Domestic vs overseas sourcing mix | 25% domestic, 75% imported; normal mix expected ~45% domestic, 55% imported |
| Revenue split by geography | ~72% from India, 28% from overseas |
| Profit split by geography | ~76% from India, 24% from overseas |
| CAPEX incurred in 9M FY26 | ~₹125 cr, declining from ~₹65 cr in Q1 to ~₹40 cr in Q2 to ~₹20 cr in Q3 |
| CAPEX expected by Q4 FY26 | crossing ₹200 cr |
| Total CAPEX earmarked through FY 2028 | ₹1,225 cr, of which ~₹850 cr for existing businesses and balance for new verticals |
| Lead capacity expansion targeted by Q4 FY26 | 125,000 tonnes (45,000 tonnes at Jaipur, 80,000 tonnes at Mundra) |
| Medium-term capacity target | over 7 lakh metric tonnes per annum by FY 2028 |
| Plastic segment capacity utilization (9M FY26) | ~40% |
| Plastic segment expected growth (next couple of quarters) | ~8%–10% |
| Romania facility revenue in Q3 | ~₹3.5 cr, rubber segment, first quarter of contribution |
| New labor law impact (FY26) | ₹4.2 cr total impact, of which ₹3.5 cr pertained to prior years and ~₹60–70 lakhs to 9M FY26 |
| Gravita Netherlands BV stake in Gravita Europe S.R.L | increasing from 80% to 95% via acquisition of 3.5 lakh shares |
| Bottom-line growth expectation (FY27 and beyond) | 30% to 35% increase in EBITDA or PAT |
| Per-kg margin improvement expectation by FY 2028 | ₹0.5 to ₹0.75 across all three segments |