Key Takeaways
- Record PAT, weak Q4 wind: FY26 PAT jumped 70% to ₹72 crores on favorable H1 wind, interest refunds and lower debt costs, but Q4 revenue and EBITDA dipped as wind availability fell below even normal low-season levels.
- Growth capex is finally moving: The company commissioned its first 7 MW solar plant, added 9.9 MW of wind, and started repowering 7.8 MW of older turbines, marking a shift from balance-sheet repair to capacity expansion.
- The 1 GW ambition is intact but unfunded: Management insists the 1 GW target is still on, yet declined to provide any timeline or financing roadmap, citing market volatility and the unresolved question of how to fund growth while retaining control.
- Management believes the asset is undervalued: The promoter stated a conviction that the company trades below competitive valuations, but refused to discuss what the ~450 MW portfolio might be worth on a public call.
- What to watch next quarter: Whether management delivers the promised answers on the 1 GW pathway and financing structure, and whether the 17.6 MW of solar commissioned in Q1 translates into a material Q2 revenue lift.
FY26 Financial Performance
- PAT drivers: The 70% PAT surge to a historic high of ₹72 crores rested on three legs: favorable wind patterns in H1, a refund of excess interest charged in earlier periods, and a 21% reduction in interest costs achieved through lower absolute debt and a 45 bps rate cut on the largest loan.
- Q4 wind drag: Total income and EBITDA fell marginally in Q4 because wind availability, already seasonally low, was even weaker than normal; higher solar generation and interest cost savings only partially absorbed the shortfall.
- Cost movements: Other expenses rose in Q4 on higher legal and consultancy charges plus a one-time write-off of roughly ₹1.67 crores for long-overdue items. Depreciation increased by ~₹1 crore on newly capitalized assets, though those assets carry first-year free O&M so no operating cost impact yet.
- Revenue quality: Tariffs were fixed throughout the year, with a significant percentage tied to C&I customers and the rest under long-term PPAs; no material power evacuation issues surfaced, and the Q4 wind deficit was an industry-wide phenomenon.
Capacity Build-Out & Repowering
- First solar milestone: A 7 MW solar plant was commissioned in December 2025 (Q3 FY26), representing the company's first move beyond its legacy wind portfolio.
- Wind additions: 9.9 MW of new wind capacity came online, with 6.6 MW commissioned at the end of March 2026 and the remaining 3.3 MW in April 2026.
- Repowering begins: The company initiated repowering of 7.8 MW of older wind turbines under Tamil Nadu's New Repowering Policy and is proactively evaluating all older wind assets for repowering, either as standalone wind or wind-solar hybrid projects, with more capacities to be added during the year.
- Near-term solar pipeline: 17.6 MW of solar capacity will be commissioned in Q1 FY27, with full production expected during Q2, offering a near-term revenue catalyst that is independent of wind seasonality.
- Battery storage exploration: Management is evaluating the addition of battery storage to solar capacity, aiming to make the renewable offering more customer-friendly by addressing the 24x7 power need.
The 1 GW Target: Ambition Without a Roadmap
- The target stands, the path does not: Management reiterated that the 1 GW renewable energy target is still on, but acknowledged that strategic initiatives have slowed due to market volatility and that the company is still working on how to achieve the target while retaining control.
- Financing gap: Anything larger than roughly 50 MW of expansion will require external equity; management confirmed it is working on this but has suffered setbacks due to market conditions, and declined to discuss whether the route would be a preferential issue, rights issue, or asset acquisition until a concrete project is in hand.
- Timeline vacuum: When asked directly whether 1 GW is now a three-year target, management did not answer the timeframe question, saying only "the target is on." The company expects to provide answers "in the next quarter or so," making the next earnings call a critical checkpoint.
- Debt paydown vs. growth capital: An analyst asked whether surplus EBITDA could be used to repay loans and eventually fund dividends; management deflected, noting that loan repayment already happens via surplus cash flow but that this will not provide the capital needed for large-scale expansion.
Shivaraman: "The target is on. How we achieve it while still retaining control of the company is something that we are looking at."
Valuation & Shareholder Value
- Undervaluation conviction: The promoter stated a clear belief that the company's asset is currently undervalued, citing competitive valuation of other companies as the benchmark, but refused to discuss what the ~450 MW portfolio might be worth on a public call, calling such estimates forward-looking and inappropriate for the forum.
- Shareholder value priority: Management characterized increasing shareholder value as "very high in our priority list" and said it is working on options, though no specific mechanism or timeline was offered.
- Foreign investor and control: An analyst asked about a potential foreign investor arrangement with management control retained; management declined to discuss anything until a transaction reaches the exchange-notification stage.
- Credit rating improvement: The credit rating and outlook were enhanced for key subsidiaries during FY26, a signal of improving balance-sheet health that may lower future financing costs.
Shivaraman: "I believe that the asset is currently undervalued, but that is based on competitive valuation of other companies."
Operational Outlook & Risks
- No curtailment fear: Management does not foresee significant curtailment this year, noting that the last few years have seen only technical curtailment.
- Performance trajectory: The company hopes to continue improving performance year-on-year and is "working 24x7 to increase shareholder value," though this aspiration carries no quantified commitment.
- Wind dependency persists: Despite the solar diversification, the portfolio remains heavily exposed to wind patterns; Q4 demonstrated that even in the absence of tariff or evacuation problems, a weak wind quarter can drag revenue and EBITDA.
Shivaraman: "I can only say that we are working very hard on all options."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Solar commissioning | 17.6 MW solar capacity commissioned and in full production | Commissioning Q1 FY27; full production Q2 FY27 |
| Repowering expansion | Additional repowering capacities to be added during the year across older wind assets | During FY27 |
| Strategic roadmap disclosure | Answers on 1 GW target pathway and financing structure | "Next quarter or so" |
| Battery storage decision | Evaluation of adding battery storage to solar capacity | No timeline given |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Total income | ₹46 crores, marginally lower than Q4 FY25 |
| EBITDA | ₹18 crores, marginally lower than Q4 FY25 |
| Loss before exceptional items and tax | ₹16.4 crores, compared to ₹14.7 crores in Q4 FY25 |
| Total income (FY26) | ₹316 crores, 13% improvement over FY25 |
| EBITDA (FY26) | ₹206 crores, 10% improvement over FY25 |
| PAT (FY26) | ₹72 crores, 70% growth, highest in company history |
| Interest cost reduction (FY26) | ~21%, driven by debt decline and 45 bps rate reduction in largest loan |
| Operating capacity | 399 MW, consisting of 392 MW wind and 7 MW solar |
| Wind capacity added | 9.9 MW, 6.6 MW commissioned end of March 2026 and 3.3 MW in April 2026 |
| Solar capacity under construction | 17.6 MW, expected to commission in Q1 and enter full production in Q2 FY27 |
| Repowering capacity initiated | 7.8 MW of older wind turbines under Tamil Nadu New Repowering Policy |
| Expected full-year revenue from 17.6 MW solar | ₹14.5 crores, assuming 12 months of operation |
| Expected full-year EBITDA from 17.6 MW solar | ₹12.8 crores, assuming 12 months of operation |
| Expected full-year revenue from 9.9 MW wind | ₹14 crores, in a normal wind year |
| Expected full-year EBITDA from 9.9 MW wind | ₹10 crores, in a normal wind year |
| One-time write-off of long overdue | ₹1.67 crores, impacting other expenses in Q4 |