Garden Reach Shipbuilders & Engineers Ltd Q1 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/rfbtxvdewuudwkl0pj63i238.pdf

Key Takeaways


The P17A Alpha Engine

Cmde PR Hari: “between now that is FY 25-26 and naturally FY27 also because the ship would be delivered during the year, these three years are going to be the peak years with FY26 most likely the highest in terms of revenue generation.”

Order Book & Pipeline Visibility


Margins: Steady, Not Expanding

Cmde P.R. Hari: “when revenue will grow substantially in the coming years, certainly, it cannot be directly proportional to the margin increase we have to strike the balance”

Capacity & Execution Readiness

Cmde PR Hari: “by the end of this calendar year, I repeat by the end of this calendar year, our ship building capacity will enhance from 20 to 24 ships.”

Diversification Bets: Green, Bridges, Autonomous, Exports


Risks & Unanswered Questions

Cmde P.R. Hari: “This is not a T20 match or even a one-day series. In case of shipbuilding, that's the point is I would like to it, it's like a test match at best so just we would like to maintain the run rate”

Guidance & Commitments

CommitmentSpecificsTimeline
Revenue growth25% growth in FY25, 25–30% in FY26FY25 and FY26
Quarterly revenue run rateMaintain ~₹1,000 crore per quarterFull FY25
PAT marginMinimum 7.5% to 8% on a yearly basisOngoing (quarterly fluctuations possible)
P17A Alpha first ship deliveryFirst ship deliveredMid-next calendar year
P17A Alpha final ship deliveryThird and final ship deliveredMid-calendar year 2026 (Aug/Sep)
Survey Vessel Large completionBalance 3 ships deliveredQ1 FY26
Anti-Submarine Shallow Water Craft completionAll 8 ships deliveredFY27
Shipbuilding capacityIncrease from 20 to 24 shipsEnd of calendar year
L1 contract signingsContracts for Acoustic Research Vessel, coastal reference vessel, hybrid ferries signedNext 3–6 months
Next Generation Corvette bidBid submittedThis month
Next Generation Corvette contractContract concluded (if successful)6–9 months after L1 declaration (~10–13 months from now)
Turnover milestoneCross ₹6,000 crore in a financial yearBetween FY25 and FY27

Key Metrics

MetricQ1 FY25
Revenue from operations~₹1,000 cr (Q1 run rate)
Revenue growth guidance25% to 30% for FY25, similar tempo expected next year
PAT margin guidance7.5% to 8% on a yearly basis, maintained going forward
Total order book₹25,231.29 cr as on 30 June 2024
Order book, shipbuilding share90% of total order book
P17 Alpha remaining order value₹14,392 cr, ~55-56% of total order book
P17 Alpha first ship physical progress~75%, harbor and sea trials being readied
P17 Alpha second ship delivery targetFebruary 2026, currently at ~62% construction
P17 Alpha third ship delivery targetMid-2026 (Aug/Sep), currently at ~50% construction
Survey Vessel Large second ship deliveryEnd of August 2024, all trials completed
Anti-Submarine Shallow Water Craft first ship deliveryIn ~3 months, currently at ~90% physical progress
Ship repair revenue share~5% of revenue, up from ~1% two years ago
Portable Steel Bridges turnover~₹140 cr, up from ~₹60 cr
Next Generation Corvette project value~₹36,000 cr AON cost, split between two shipyards
FY24 revenue from operations₹3,592 cr