Garden Reach Shipbuilders & Engineers Ltd Q3 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/pvnr01vxc1msqo6a08gi7dyn.pdf

Key Takeaways


Revenue Growth & the P17 Alpha Engine

Cmde PR Hari: "If there is no delay, the order book and the progress of the ships, it is pure mathematics."

Order Book & the Replenishment Pipeline


Commercial Shipbuilding: The New Frontier

Cmde PR Hari: "They target a shipyard. They do an independent assessment of the shipyard. When they know that we are interested in commercials, they approach us. That is a strategy which they generally follow unlike a conventional government domestic warship bidding tender."

Diversification: Repairs, Guns, Engines & Green Vessels

Cmde PR Hari: "CSL are slightly ahead of us. And with this delivery, we are very confident of catching up with them and even surpassing them because there is good market potential in this segment."

Margins & Capital Allocation


Strategic Ambition: Navratna by 2030

Cmde PR Hari: "My company's vision is to become a Navratna company by 2030. … So, we aspire to be a Navratna company with a turnover of around 10,000 crore by 2030. It is an ambitious target, very, very aspirational, but it is not impossible, it is very much possible."

Guidance & Commitments

CommitmentSpecificsTimeline
Revenue growth20–25% annual growthAt least next two years (FY25–FY26)
P17 Alpha first ship deliveryFirst ship deliveredJuly–August 2024
P17 Alpha second ship deliverySecond ship deliveredFebruary 2026
P17 Alpha third ship deliveryThird ship deliveredAugust 2026
Survey Vessel Large deliveriesSecond ship: May/June 2024; third: December 2024; fourth: H1 2025FY25 through early FY26
ASW SWC deliveriesFirst ship: June 2024; thereafter one every six months; project complete by mid-2026June 2024 through mid-2026
NGOPV deliveriesCommence from 2026, every six months, completion by FY282026 through FY28
Ocean Graphic Research Vessel contractContract signingMarch 2024
Bangladesh dredger contractContract signingWithin three months
Commercial shipbuilding ordersConclude contracts under negotiationWithin three months
Shipbuilding capacityIncrease from 20 to 24 warships concurrentlyCalendar year 2025
Ship repairs revenue₹200–250 cr internal target, contingent on Navy repair workBy 2025
NGC RFP issuanceRFP expectedJune–July 2024
NGC contract conclusionContract awardMid-2025
NGC revenue startRevenue accrual beginsEnd-2026
P17 Bravo AoNAoN expectedEarly 2025
Order book rangeMaintain at ₹23,000–25,000 crComing years
Navratna statusTurnover of ~₹10,000 crBy 2030
Schedule A statusAchieve Schedule A classification"Another couple of years, this year or next year or next to next year"
Water Jet Propulsion licenseConclude license agreement with Kongsberg3–4 months
Authorized share capital clarityProvide clarity on DIPAM-directed increaseThree months

Key Metrics

MetricQ3 FY24
Revenue from operations (9M FY24)₹2,576 cr, up 31% YoY over 9M FY23
Total income (9M FY24)Up 34% YoY
EBITDA (9M FY24)₹367 cr, up 41% YoY
PAT (9M FY24)₹245 cr, up 42% YoY
FY24 full-year revenue guidance₹3,000+ cr
Revenue growth guidance20–25% at least for next three years
Order book₹23,592 cr as on 31 Dec 2023
Order book target range₹23,000–25,000 cr in coming years
P17 Alpha project remaining order book₹12,700 cr as on 31 Dec 2023
Anti-Submarine Shallow Water Craft remaining order book~₹5,000 cr as on 31 Dec 2023
Survey Vessel Large remaining order book~₹1,050 cr as on 31 Dec 2023
NGOPV project remaining order book~₹3,388 cr as on 31 Dec 2023
P17 Alpha first ship physical progress66%
P17 Alpha second ship physical progress55%
P17 Alpha third ship physical progress43%
Anti-Submarine Shallow Water Craft first ship physical progress77%
Anti-Submarine Shallow Water Craft eighth ship physical progress20%
NGOPV all four ships physical progress~10%
Survey Vessel Large order value per ship₹511 cr
P17 Alpha project total value₹19,293 cr
Next Generation Corvettes pipeline total value~₹36,000 cr, split 5:3 between L1 and L2 shipyards
Next Generation Survey Vessels pipeline value~₹3,000 cr for five ships
Multi-purpose vessels pipeline value~₹1,200 cr for two vessels
P17 Bravo pipeline total value~₹70,000 cr for seven ships
Landing Platform Dock pipeline value~₹40,000 cr for two ships
Ocean Graphic Research Vessel order value~₹840 cr, L1 declared, LoI issued
30mm Naval Surface Gun order value~₹250 cr
Portable steel bridges market share~65%
Portable steel bridges segment revenue₹100–120 cr
Ship repairs current revenue₹85–100 cr
Ship repairs internal target by 2025₹200–250 cr
Other verticals contribution to overall revenueLess than 5%
FY25 planned deliveriesTwo Survey Vessel Large, two Anti-Submarine Shallow Water Craft
Q1 FY25 planned deliveriesOne Survey Vessel Large, one Anti-Submarine Shallow Water Craft
Q3 FY25 planned deliveryOne Survey Vessel Large
Q4 FY25 planned deliveryOne Anti-Submarine Shallow Water Craft
Nomination contract margin~7.5%
Annual CAPEX strategy₹50–60 cr per annum for next 3–4 years
Major CAPEX infusion (latter half of last decade)~₹610 cr
Target turnover by 2030~₹10,000 cr
Export order values (Bangladesh dredger and tug)₹150–200 cr each
Autonomous platform order from DRDO~₹20 cr
Autonomous platforms expected future orders₹50–100 cr level piecemeal over next three years
Rajabagan facility current utilization70%
Shipbuilding capacity target24 warships concurrent construction by calendar year 2025