Garden Reach Shipbuilders & Engineers Ltd Q3 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/7nbulo27z9tcue0hxgwy5uk1.pdf

Key Takeaways


Execution & Delivery Momentum

P. R. Hari: “This is the first time we are dipping below ₹20,000, which is good news for you, which means our execution rate has picked up.”

Order Book & Pipeline

P. R. Hari: “Like what I assured you last year when we met physically, so this year my KRA is to win the P-17 Bravo project. So, let us see.”

Capacity Expansion


Margins & Profitability

P. R. Hari: “I can only assure you that we would be bidding to win the P-17 Bravo, because that is what will keep the company moving for another 10 years, 8 years. So, that is a project which we will go all over to win, without compromising at all on the margins.”

Revenue Trajectory & Peak Concerns


Indigenization, New Capabilities & Non-Defense

P. R. Hari: “Non-defense segment, I suggest just wait and watch. Maybe six months, we will have better clarity.”

Guidance & Commitments

CommitmentSpecificsTimeline
NGC contract conclusionContract signed for 5-ship ~₹33,000 cr projectCurrent financial year (by March 2026)
Three more vessel deliveriesSecond P-17 Alpha, fourth Survey Vessel, fourth ASW Shallow Water CraftNext three months (by ~May 2026)
Third P-17 Alpha ship deliveryDelivery of third frigateThis calendar year (2026)
ASW Shallow Water Craft project closureFull contract closedNext financial year (FY27)
Hybrid ferry project closureFirst 2 vessels delivered Q1 FY27; project closedFirst half of FY28
German client deliveries commenceFirst of 12 multipurpose vessels deliveredQ2 FY27
Bangladesh dredger deliverySingle vessel deliveredQ3 FY27
Ocean Research Vessel deliveryContractual deliveryFY27-28
Acoustic Research Ship deliveryDeliveryFY27-28
Coastal Research Vessels (2) completionProject completedFirst half of FY28
NGC revenue accrual beginsRevenue recognition startsQ4 FY28
30mm gun program completionAll 17 guns completedMid-2027
30mm gun Coast Guard contractContract concludedQ1 FY27
Order book target~₹50,000 croresEnd of FY26
Order book target~₹70,000 crores (assuming P-17 Bravo at least L2)End of FY27
Brownfield production startTwo Kolkata facilities commence productionEnd of calendar year 2026
Third brownfield facility productionLarger Kolkata facility operational post-modernizationTwo years from now (~2028)
Gujarat greenfield production readinessProduction can commenceThree years from now (~2029)
Concurrent construction capacity32 ships within own premisesEnd of calendar year 2026
Concurrent construction capacity~35 shipsEnd of 2026
Gujarat facilities full capacity~12 additional large shipsFour years from now (~2030)
Revenue CAGR25–30%Current financial year (FY26)

Key Metrics

MetricQ3 FY26
Revenue from operations₹1,896 cr, +49% YoY from ₹1,271 cr in Q3 FY25
Revenue from operations (9M FY26)₹4,883 cr, nearly touching FY25 full-year revenue of ₹5,076 cr
Profit after tax₹171 cr, +74% YoY from ₹98 cr in Q3 FY25
Order book₹18,482 cr as of 31 Dec, comprising 10 projects and 42 platforms
Order book, defense segment₹14,276 cr, 77% of total order book
Order book, non-defense segment₹897 cr, 18% of total order book
Order book, export projects₹1,481 cr
P-17 Alpha order book balance₹8,236 cr, 46% of total order book
Next-Generation Corvette order value~₹33,000 cr, 5-ship project, contract conclusion expected by end of FY26
Expected order book by end of FY26~₹50,000 cr
Production capacity, concurrent platforms28 platforms in 2025, targeting 32 by end of CY26 and 35 by end of 2026
Indigenous content on 3 completed projects85%+
Naval surface guns indigenization achieved60%+
Ship repair contribution to order bookcrossed 1%
Revenue CAGR guidance25% to 30% expected for FY26