Garden Reach Shipbuilders & Engineers Ltd Q4 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/kfz6t7tyjwazcyai9tzyap6f.pdf

Key Takeaways


Financial Performance & Order Book

Cmde P. R. Hari: "Since we know the cost to completion of the first ship, the condition is going to be more or less same, which is the positive side."

Peak Revenue & Margin Outlook

Cmde P. R. Hari: “I would not like to say so, because from our appreciation… the peak year perhaps could be the next year. That is financial year, the current year. What I mean is, Financial Year '25-26 could be the peak year. Thereafter, it could flat out…”

Project Execution & Delivery Pipeline

ProjectDelivery Timeline
P-17 Alpha (1st ship)~2 months (ahead of contract)
P-17 Alpha (2nd ship)Early next year
P-17 Alpha (3rd ship)August 2026
Survey Vessel Large (3rd)July 2025
Survey Vessel Large (4th)End of calendar year 2025
Anti-Submarine Shallow Watercraft (2nd)July 2025
All Anti-Submarine Shallow WatercraftDuring calendar year 2026
Oceanographic Research VesselOctober 2027

Order Pipeline & Bidding Activity

Cmde P. R. Hari: "I personally feel if together over the L1 shipyard and the Navy pushes, the contract can be signed by end of this calendar year."

Capacity Expansion & Partnerships


Guidance & Commitments

CommitmentSpecificsTimeline
P-17 Alpha first ship deliveryDelivery ahead of contractual period~2 months from call date
Coastal Research Vessels contractContract signing for two vesselsJune 2025
Next Generation Corvette contractContract conclusionOptimistic: Dec 2025; Conservative: Mar 2026
Shipbuilding capacity targetIncrease to 28 shipsEnd of 2025
Shipbuilding capacity targetIncrease to 30 shipsWithin next two years
FY26 deliveries7 ships (1 P-17A, 2 SVL, 4 ASW SWC)FY25-26
FY27 deliveries7 ships (2 P-17A, 3 ASW SWC, 1 NGOPV, 1 Acoustic)FY26-27
FY28 deliveries4+ ships (2 NGOPV, 1 ORV, Coastal Research Vessels)FY27-28
P-17A revenue split40% in FY26, 60% in FY27FY26-FY27
EBITDA marginMaintain ~13% levelOngoing

Key Metrics

MetricQ4 FY25
Revenue from operations₹1,642 cr, up 62% YoY from ₹1,015 cr
EBITDA₹335 cr, up 101% YoY from ₹166 cr
Profit after tax₹244 cr, up 118% YoY from ₹114 cr
Operating profit₹209 cr, up from ₹77 cr
Revenue from operations (FY25)₹5,075 cr, up 41% YoY, crossed ₹5,000 cr barrier
Profit after tax (FY25)₹527 cr, up 46% YoY from ₹360 cr
Operating profit (FY25)₹368 cr, up 103% YoY from ₹181.30 cr
EBITDA margin (FY25)~13%, touched a new high, not a one-off per management
Order book₹22,680 cr as on 31 Mar 2025, flat YoY despite ~₹5,000 cr revenue accrual; 9 projects, 40 platforms
Order book breakup: P-17 Alpha₹11,435 cr remaining
Order book breakup: ASW Shallow Watercraft₹3,946 cr
Order book breakup: NGOPV₹3,327 cr
Order book breakup: Survey Vessel Large₹530 cr
Order book breakup: Export projects~₹1,200 cr (Multipurpose Vessel, Dredger etc.)
Provision write-back₹433 cr, linked to P-17 Alpha first ship nearing delivery; profit to be recognized over 1–2 years
Shipbuilding capacity24 ships concurrently (enhanced from 20 in 2024); targeting 28 ships by end of 2025, 30 ships within two years
P-17 Alpha first ship physical progress95%, final machinery trials completed, delivery expected in ~2 months ahead of contractual date
P-17 Alpha second ship physical progress73%, delivery planned early next year
P-17 Alpha third ship physical progress54%, delivery planned August 2026
Survey Vessel Large third ship physical progress88%, contractor fleet trials completed, delivery expected July 2025
Survey Vessel Large fourth ship physical progress77%, delivery expected by end of calendar year 2025
ASW Shallow Watercraft second shipFinal machinery trials completed, delivery planned July 2025
ASW Shallow Watercraft third ship physical progress82%
ASW Shallow Watercraft fourth ship physical progress68%
NGOPV first two ships physical progress>50%; keel of all four ships laid, two launches planned in FY26
NGOPV last two ships physical progress43%
FY26 planned deliveries7 ships: 1 P-17 Alpha, 2 Survey Vessel Large, 4 ASW Shallow Watercraft
FY27 planned deliveries2 P-17 Alpha, 3 ASW Shallow Watercraft, 1 NGOPV, 1 Acoustic Research Ship
P-17 Alpha revenue split FY26:FY2740:60
Next Generation Corvette anticipated order value~₹40,000+ cr total; L1 shipyard share ~₹25,000+ cr (5 of 8 ships); L1 declaration expected in days
Next Generation Survey Vessel Large anticipated order value~₹3,500 cr
18 NGFPV anticipated order value~₹3,000 cr
31 Water Jet FAC anticipated order value~₹3,000 cr (±₹200 cr)
Mine Counter Measure Vessels AON value₹32,000 cr, 12-ship project, single shipyard
P-17 Bravo AON value~₹70,000 cr, 7-ship project, two shipyards
Indian Navy fleet strength~150 platforms
Indian Coast Guard fleet strength~100 platforms
Warships under construction in India61 platforms, 60 being built by Indian shipyards
GRSE platforms currently under construction16 platforms; 1 delivered in current calendar year, 3 more confident of delivering this calendar year
Refits completed at Syama Prasad Mookerjee Port facility41 refits, including Coast Guard and naval ships
Client retention on project cost10% of project cost withheld till completion of one-year guarantee refit