GSPL Transmission Ltd Guidance Report - SOIC x StockScans Report
as of Nov 2026
- GITL volumes \~2 MMSCMD in FY27
On track - In the filings around the Q2 FY27 results, management guided GITL volumes to remain \~2 MMSCMD in FY27, after the RFCL plant shutdown and subsequent revival at full capacity. Q2 FY27 transportation volume came in at 1.68 MMSCMD, up 137% YoY, with FY26 at 1.81 MMSCMD vs 2.08 MMSCMD in FY25; the RFCL plant has been revived at full capacity.
- GIGL breakeven "another couple of years or so"
On track - At the Q2 FY27 call, the CFO expected GIGL to reach breakeven in "maybe a period of another couple of years or so" as new industries come along. GIGL remains loss-making with customer contracts not yet sufficient for breakeven; Q2 FY27 volume was 5.49 MMSCMD (+27% YoY) and revenue ₹81.49 cr (+13% YoY), with FY26 TOI ₹315 cr vs ₹240 cr in FY25.
- Next tariff revision filing expected "somewhere in '28 or so"
On track - At the Q2 FY27 call, the CFO guided the next tariff revision (last in April '24) to "somewhere in '28 or so", with pipeline life review and certifications planned before filing, and filing only after '28 given an appeal pending at PNGRB. No tariff filing has been made yet; the PNGRB 2024 order appeal is still pending at the appellate tribunal with no order.
- Expansion capex ₹3,500 cr over 2-2.5 years, \~700 km, network to 3,600+ km
On track - At the Q2 FY27 call, management guided \~₹3,500 cr of capex across 10+ pipeline projects aggregating \~700 km, taking the Gujarat network from \~2,900 km to 3,600 km over 2-2.5 years, with \~₹3,000-odd cr done by March '28; filings said "approx ₹3,500 crore over next 2 to 3 years". H1 FY27 capex was \~₹300 cr, EPC contracts worth ₹1,800 cr for Anjar-Palanpur were awarded in July 2026, and CWIP rose from ₹349.4 cr (31 Mar 2026) to ₹582.9 cr (30 Sep 2026).