Gujarat Alkalies & Chemicals Ltd Guidance Report - SOIC x StockScans Report
as of Nov 2026
- Power cost of Rs. 6.18 per kWh by March 2027, below Rs. 6 by FY30
On track - At the Q2 FY27 call, management guided power cost down to Rs. 6.18 per kWh by March 2027 with increased RE share, and below Rs. 6 by FY30. H1 FY27 power rate fell to Rs. 7.09 per unit from Rs. 7.6, with Rs. 6.95 projected for the full year.
- GNAL to sustain improved profitability over FY27
On track - At the Q2 FY27 call, management said GNAL hopes to sustain improved performance on stabilization, higher caustic soda and hydrogen sales and better realization. H1 FY27 sales rose 27%, EBITDA 73%, and PBT swung from a Rs. 36 crore loss in H1 FY26 to Rs. 8 crore profit.
- SAP S/4HANA migration within two years under digitization and AI strategy
Pending - In the Q4 FY26 result, management stated Board approval for a digitization and AI strategy over the next two years, including migration from SAP ECC to RISE with SAP S/4HANA. No progress disclosure has been made as of Q2 FY27.
- Vision 2047 - Rs. 40,000 crore revenue and 20% EBITDA margin
Pending - In the FY26 annual report, management stated Board approval of Vision 2047 on 23rd July 2026, targeting Rs. 40,000 crores revenue by 2047 with 20% EBITDA margin. The horizon is 21 years away and no outcome evidence exists yet.
- Rs. 10,000+ crore revenue and 20%+ EBITDA margin by FY31 (Project Ahvaan/Aman)
On track - In the FY26 annual report, management launched Vision 2031 targeting over Rs. 10,000 crores revenue and more than 20% EBITDA margin by FY31, reiterated as a medium-term aspiration at the Q2 FY27 call. TTM revenue stands at Rs. 4,772 crore with 12.70% OPM; H1 FY27 EBITDA margin was 16.95%.
- Chlorine integration to 75% in 2-3 years
On track - At the Q2 FY27 call, management stated chlorine integration was \~45% and aimed to reach almost 75% in the next 2 to 3 years as the CapEx pipeline is commissioned. An HCl synthesis unit is targeted around January 2027, with a second board-approved unit next year.
- KOH expansion at Koloda and food-grade phosphoric acid second plant by FY29
On track - At the Q2 FY27 call, management stated KOH expansion at Koloda, the food-grade phosphoric acid second plant and boilers were planned for FY29; the FY26 annual report lists electrolysers reallocation to lift KOH capacity from 120 TPD to 200 TPD. No commissioning disclosed as of Q2 FY27.
- Electronic grade hydrogen peroxide plant around January 2028
On track - At the Q2 FY27 call, management planned commissioning of the electronic grade hydrogen peroxide plant around January 2028; the FY26 annual report lists the 5,000 TPA High Purity plant at Dahej as board-approved. No commissioning disclosed as of Q2 FY27.
- 120 TPD HCl synthesis unit around January 2027
On track - At the Q2 FY27 call, management targeted the 120 TPD HCl synthesis unit around January 2027, listed in the FY26 annual report among FY 2026-27 projects. CWIP shows HCL at Rs. 107.03 lakh to be completed in under 1 year; no commissioning disclosed yet.
- 200 TPD caustic soda flaking facility at Behage by December 2026
On track - At the Q2 FY27 call, management targeted the 200 TPD caustic soda flaking facility at Behage for December 2026; the FY25 annual report listed it as upcoming. CWIP shows the flaker unit at Rs. 605.40 lakh to be completed in under 1 year; no commissioning disclosed yet.
- 62.7 MW hybrid captive power with Aditya Birla Renewable Energy operational by January 2026
Partial - In the FY25 annual report, management anticipated the 62.7 MW hybrid captive power via SPV with Aditya Birla Renewable Energy would be operational by January 2026. The Q2 FY27 call noted a delay in commissioning of long-term RE of AVRN with short-term RE as backup.
- Chlorotoluene downstream Phase 1 by March 2027
On track - At the Q2 FY27 call, management stated Chlorotoluene downstream Phase 1 units were planned for commissioning by March 2027; the FY26 annual report lists the project as under implementation. CWIP shows Chloro Toluene Downstream at Rs. 121.40 lakh, under a year to completion; no commissioning disclosed yet.
- New Phosphoric Acid plant (100 TPD) by April 2023
Delivered - In the Q3 FY23 PPT, management guided commissioning of the 100 TPD, Rs. 520 Cr New Phosphoric Acid plant by April 2023, with 95% completion as of 07.02.2023. The plant was commissioned on 27 April 2023, with the first dispatch on 8 July 2023 and 50% capacity achieved by 31.10.2023.
- Coal-based Power Plant (JV with NALCO) Unit #2 by March 2023
Delivered - In the Q3 FY23 PPT, management stated Coal-based Power Plant (JV with NALCO) Unit #2 was expected by March 2023. Unit #2 was synchronized on 28 April 2023, with the second 65 MW unit commissioned in April 2023, one month after the stated month.
- 65 MW coal-based power plant at Dahej
Missed - In the FY22 annual report, management stated a 65 MW Coal based Power Plant at Dahej was being considered, listed as a committed Rs. 325 Cr project in the Q4 FY22 PPT. The Q4 FY23 PPT and Q2 FY24 PPT both showed the project as "under hold", with no later disclosure of revival.
- 30,000 TPA Chlorotoluene Project at Dahej operational by FY25
Delivered - In the FY22 annual report, management planned the 30,000 TPA Chlorotoluene Project at Dahej to be operational during FY 2024-25; progress moved from 9% in May 2023 to 19.4% by October 2023. The plant was commissioned on March 29, 2025, with FY26 utilization \~80% and Q2 FY27 \~90%.
- Capex of \~Rs. 1,826 crore over two years ending FY23
Partial - In its May 2021 announcement, management stated a capex plan of around Rs. 1,826 crore over the two years ending FY23, funded by Rs. 1,500 crore debt and internal accruals. By 20th May 2023, most named projects were commissioned - including the Rs. 2,300 crore NALCO JV plant, chloromethanes, hydrazine hydrate and caustic soda expansion - out of Rs. 5,380.5 crore announced project cost, though the chlorotoluene project remained at 9% progress and the 65 MW coal power plant under hold.
- GNAL JV - 292,000 MTPA caustic soda plant with 130 MW captive power
Delivered - In the May 2021 announcement, management stated the GNAL JV (60:40 with NALCO) would build a 292,000 MTPA caustic soda plant at Dahej with 130 MW captive power, cost revised to Rs. 2,280 crore from Rs. 2,000 crore. The 800 MTPD plant with 130 MW power commissioned March 30, 2022, and H1 FY27 PBT turned positive at Rs. 8 crore.
- Purified Phosphoric Acid and Caustic Soda Expansion by Q4 FY22
Partial - In the FY20 announcement, management stated both projects, originally planned for Q3 FY22, would reach commercial production in Q4 FY22 after COVID-19 delays; the FY22 annual report revised phosphoric acid to Q3 FY23 and caustic soda to progressive commissioning in Q2 FY23. Caustic soda expansion commissioned 20 September 2022 and phosphoric acid on 27 April 2023.
- Hydrazine Hydrate, Chloromethanes and GNAL commercially operative by Q2 FY22
Partial - In the FY20 announcement, management stated the three projects, originally planned for Q4 FY21, would be commercially operative by Q2 FY22 after COVID-19 delays; the FY22 annual report moved Hydrazine Hydrate and Chloromethanes to Q2 FY23 and the GNAL project to full operational status by Q3 FY23. Chloromethanes commissioned 15 August 2022, Hydrazine Hydrate 26 September 2022, and GNAL partially on 30 March 2022.
- Rs. 5,000 crore revenue aspiration in FY22
Missed - In the FY20 announcement, management aspired to reach annual turnover of Rs. 5,000 crores in 2021-22 via growth plans despite COVID-19. FY22 net external sales were Rs. 3,683.40 Cr per the Q4 FY22 PPT and Rs. 3,807 Cr per SQL - about 26% below the aspiration.