GE Power India Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/fx1ibpc39g708xr4abgz3tu1.pdf

Key Takeaways


Core Services: The Pivot in Numbers

Aashish Ghai: "This is very short-term average. It takes entity plus 12 months to complete the contract. So, it's a low risk, faster working capital, cash and margin accretive projects that we enter into, that's core."

Legacy Clean-Up: BHEL and Jaypee Settlements

Aashish Ghai: "It is going to be almost breakeven. We might have an impact maybe in the range of INR 2 crores to INR 4 crores overall."

Durgapur Demerger and Manufacturing Access


Profitability: Normalized Run-Rate and What Management Won't Define


Strategy and Market Context

Puneet Bhatla: "The idea is that we are focusing on core services, domestic and exports, both."

Guidance & Commitments

CommitmentSpecificsTimeline
Core services growthDeliver double-digit year-over-year growthFY26 (full year)
BHEL cash collectionINR 340 cr settlement received per agreed scheduleOver the next few quarters
Strategic focusNo entry into new industries or avenues; focus on core services, domestic and exportsOngoing
Export penetrationDeepen presence in the 7 countries already entered, no new country additions plannedOngoing
Operational profitabilitySignificantly improve through disciplined backlog execution and services growth initiativesNot quantified, no date

Key Metrics

MetricQ2 FY26
Revenue₹281 cr, vs ₹217 cr in Q2 FY25
Profit before tax and exceptional items₹33 cr, vs ₹8 cr in Q2 FY25
Gross margin~33%, on COGS and work-in-progress basis; ~55% of revenue from core services with better margins
Standalone net worth₹298 cr as on Sep 30, 2025, vs ₹233 cr as on Mar 31, 2025
Order intake₹240 cr, vs ₹446 cr in Q2 FY25 (prior year included Wanakbori turbine upgrade order of ₹243 cr)
Core services order intake₹162 cr, +45% YoY from ₹112 cr in Q2 FY25
Core services H1 FY26 order intake₹343 cr, vs ₹235 cr in H1 FY25
Overall sales growth (core + upgrade), H1 FY26+23% YoY
Order backlog₹1,825 cr as on Sep 30, 2025, down from ₹2,662 cr as on Mar 31, 2025; driven by termination of 2 FGD EP contracts worth ₹775 cr
Jaypee settlement charge in P&L₹27 cr charge in Q2 FY26; net impact of Jaypee cancellation estimated at ₹2–4 cr overall, almost breakeven
BHEL settlement provision reversal₹23 cr credit in Q2 FY26; total BHEL settlement amount ₹340 cr, receivables from BHEL ₹357 cr
Solapur fire insurance claim recovery₹6.6 cr, full and final settlement received in Q2 FY26
Export boiler spare orders₹4 cr across 7 countries, covering ~8 GW of installed base
NOx abatement and performance improvement order from Adani Mahan₹47 cr for 600 MW units, won in H1 FY26
Durgapur demerger share entitlement ratio10 JSW Energy shares for every 139 GEPIL shares, effective Jul 1, 2025