GE Power India Ltd Q3 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/llcm64gnw5agj30dtp501969.pdf

Key Takeaways


Strategy Execution & Turnaround

Ghai: "this is a long-term turnaround story. This is not a 1-quarter turnaround story. And it would take time while we are delivering on our commitments to the customers on the long gestation cycle FGD EPC contracts."

Order Wins & Demand Environment


FGD Market: Green Shoots Return

Bhatla: "the green shoots, which were not available during the last quarter, are now coming back in the market."

Hydro Business Divestment


Insurance Claims & Other Income

Ghai: "I don't want to put a number, because insurer is an external party. So, of course, we are pushing for the maximum is what I can say... putting a number puts us in a worse condition in front of the insurers."

Operational Updates

Bhatla: "I would just reiterate the information which I already said earlier also that when the new strategy of your company was announced, we decided that we would only be focusing on the de-risked opportunities with a short cash cycle."

Guidance & Commitments

CommitmentSpecificsTimeline
Hydro business transferSlump sale completion and loss transferBy end of March 2025
Solapur insurance claimFinal settlement and closureBy June 2025
Sipat insurance claimConclusion of claim; some money expected soonerNext 3-4 months for partial inflow; June 2025 for conclusion
Durgapur factory hoursFull-year utilization~165,000 hours for FY25
Strategy executionStick to 4-pillar strategy, implement and execute successfullyOngoing

Key Metrics

MetricQ3 FY25
Revenue from continuing operations₹317 cr, +8% YoY from ₹294 cr
Profit before exceptional items₹8 cr, second consecutive profitable quarter for continuing business
Loss before tax (including exceptional items)Negative ₹20 cr, vs negative ₹2 cr YoY; includes ₹27 cr loss from discontinued operations
Other income₹27 cr, includes ₹10 cr fire insurance claim recovery at NTPC Sipat FGD project
Order inflow₹461 cr, 3x+ increase vs ₹134 cr in Q3 FY24
Order backlog (continuing operations, Steam)₹2,706 cr as of December 31, 2024
Standalone net worthPositive ₹92 cr as of December 31, 2024
Debt~₹5 cr as of December 31, 2024, for internal cash flow arrangement
Employee cost~18% of revenue (per an analyst's math)
Durgapur factory hours clocked (9M FY25)On track for full-year estimate of 165,000 hours; breakeven at ~265,000 hours
Solapur fire insurance recovery₹59.3 cr collected (₹58 cr cash + ₹1.3 cr salvage) vs ₹99.8 cr total loss; final reconciliation ongoing
Sipat fire insurance recovery₹20 cr collected; final claim submitted, reconciliation in progress
Vindyachal steam turbine upgrade order (NTPC)₹348 cr, received in Q3 FY25
Overseas boiler services footprint~13 countries; small spare-parts orders received from Saudi, Turkey, Malaysia, Dubai