Key Takeaways
- Orders surge 68% YoY to ₹1,000 crore, driven by a thriving TBCB pipeline and strong domestic demand, setting a much higher base for the year.
- Profitability inflects sharply: Q1 PBT of ₹38.6 crore already exceeds the entire FY23 PBT of ₹38.1 crore, helped by cost rationalization and legacy project execution.
- Legacy drag is known and finite: Low-margin projects still make up 20-25% of the backlog but will phase out sequentially over the next 3-4 quarters, clearing the way for healthier new orders.
- Export and HVDC optionality is real but early: Management is seeking approvals to book part of GE’s global HVDC contracts (12-13 won this year) through India, targeting a ₹700-1,000 crore opportunity.
- What to watch next quarter: Whether the targeted metal sector orders materialize, the pace of legacy backlog burn-off, and any concrete HVDC order booking from global parents.
Order Inflow & Market Backdrop
- TBCB pipeline underpins multi-year confidence: 28-30 tariff-based competitive bidding projects have been bidded out by REC/PFC, and the CEA’s approved project pipeline gives visibility for the next 4-5 years.
- Market size expanding: Excluding HVDC, the domestic T&D market is expected to exceed US$3 billion this year, with private customer share rising in both order intake and backlog.
- Industrial segment targeted for near-term wins: Management is pursuing orders from the metal space this quarter, where investment and expansion plans are active, while the refinery segment shows no big near-term opportunities.
- RDSS and WAMS are secondary growth vectors: RDSS will require many control centers for distribution companies, a market where GE T&D is strongly present in ADMS, though states are still evolving requirements. A large Wide Area Monitoring System project is under discussion but not expected this year.
- Data centers are a focused but small market: Individual TBCB projects dwarf data center volumes, which are mostly at 220 kV, but the segment allows connection with global companies where GE has existing relationships.
Zanzaria: "if I am not mistaken, we are about 28 to 30 projects of tariff based competitive bidding which have been bidded out by REC/PFC. Also, if you look at the CEA pipeline of the projects, which have got approved, I think it gives a good amount of confidence for the future of transmission at least for the next 4-5 years."
Margins & Profitability Bridge
- Gross margin at 31.7% in Q1, with management cautioning against quarterly evaluation and expecting full-year improvement over last year.
- Legacy backlog is the main margin drag: Around 20-25% of the current backlog consists of low-margin old projects affected by commodity price spikes; these will phase out sequentially over the next 3-4 quarters. New orders from April 2022 onward carry healthy margins.
- Cost pass-through is working: Market prices for transformers and switchgear are 35-40% above pre-COVID levels, and manufacturers have been able to pass on cost increases (CRGO, oil, forex, copper) to customers rather than absorbing them into margins.
- Employee cost rationalization is sustainable: Significant cost reduction achieved in FY23 continued into Q1 with a YoY decline; only slight increases expected from annual inflation, offset by ongoing lean initiatives. Full-year employee cost should stay below last year’s ₹350 crore.
- Forex gains boosted other income: Most other income in the quarter was forex-related, with 40-50% of that being realized gains.
- ESSEL and SL projects no longer a concern: ESSEL is fully commissioned and out of the backlog; the SL project was partially commissioned last quarter with no outstanding issues.
Zanzaria: "this quarter, we have a gross profit of 31.7%. Overall, I say that yes, the confidence level is higher, but let us not evaluate on quarterly basis and I think more on a yearly basis, we should be better than the last year."
HVDC & Export Optionality
- Global HVDC supply remains tight for years: The HVDC supply situation in Europe has not eased and is not expected to ease for the next 5-7 years, given robust offshore wind project forecasts in Europe and the US. This will indirectly impact pricing when domestic HVDC projects go up for bidding later this year.
- GE’s global HVDC wins validate technology position: GE has taken 12-13 HVDC contracts globally from January to date, confirming no technology gap. The Leh Ladakh project is a different strategic undertaking requiring aspects beyond HVDC.
- India booking opportunity is material: Management is in discussion with Grid Solution UK to book part of large global HVDC projects through GE T&D India, targeting a ₹700-1,000 crore opportunity for export business. Shareholder approval is being sought for higher related-party transaction limits with Grid Solution SAS and Grid Solution UK to enable this.
- Export pricing is superior: Export pricing is much better than domestic pricing, and GE T&D India has a good cost advantage compared to other GE factories globally, with 95% of GE Grid Solution’s global product range manufactured locally.
- STATCOM is a future target: GE has commissioned large STATCOM projects globally and sees no technology gap; it has not taken any STATCOM order in India yet but aims to do so in future. STATCOM transformers are simpler to make than LCC-HVDC transformers, so supplying from Vadodara is not a concern.
Zanzaria: "It has not eased and looking into the pipelines of various utilities there, I don't think that it is going to ease in next 5 to 7 years."
Balance Sheet & Cash Flow
- Debt reduced by ₹56 crore to ₹117 crore from ₹173 crore, reflecting a deliberate focus on balance sheet health.
- Cash generation of ₹56 crore during the quarter, matching the debt reduction amount.
- Related-party resolutions proposed at the upcoming AGM include borrowing up to ₹500 crore from GE India Industrial Private Limited, inter-corporate deposits up to ₹150 crore, and significantly expanded export transaction limits with Grid Solution SAS (₹440 crore) and Grid Solution UK (₹1,150 crore).
Operational & Competitive Positioning
- Lead times have stretched: TBCB project timelines have increased from 12-15 months to 21-24 months as regulators and EPC companies adjust to supply-side pressure. Getting a transformer in 6-8 months is difficult due to manufacturing capacity and component availability; switchgear lead times remain shorter at a few months.
- Utilization is mixed and hard to quantify: One plant had slightly lower utilization due to stress in an export market; other plants saw much better utilization this year. Management declined to give a specific number, citing dependence on voltage and equipment mix.
- Product competitiveness requires constant R&D: While 95% of GE Grid Solution’s global products are manufactured in India, some legacy products face uncompetitive issues, requiring ongoing R&D to develop next-generation products.
- Strategic focus has shifted to profitability over revenue share: Management outlined three guardrails to avoid repeating legacy issues: selectivity in projects, disciplined commercial terms, and prioritizing profitability over market share in revenue.
Zanzaria: "So, there are 2-3 things... first would be selectivity... second, what are the commercial terms and conditions... third instead of running after market share in revenue, we are today focused more on profitability."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Legacy backlog phase-out | Low-margin projects (20-25% of backlog) to clear sequentially | Next 3-4 quarters |
| Employee cost | Full-year employee cost below last year's ₹350 crore | FY24 |
| HVDC export order booking | Target ₹700-1,000 crore opportunity via global parents | Ongoing discussions, no date |
| Metal sector orders | Targeting a few orders from metal space | This quarter |
| Wide Area Monitoring System | Another large project under discussion | Not this year, maybe next year |
| Full-year margins | Yearly basis should be better than last year | FY24 |
Key Metrics
| Metric | Q1 FY24 |
|---|---|
| Revenue | ₹717.6 cr, +21% YoY |
| Gross profit margin | 31.7% |
| EBITDA | ₹62.8 cr, 8.7% of revenue, +3.5 ppt YoY |
| Profit before tax and exceptional items | ₹38.6 cr, vs ₹10.3 cr in Q1 FY23; higher than full FY23 PBT of ₹38.1 cr |
| Order intake | ₹1,006.6 cr, +68% YoY |
| Order backlog | ₹3,940.3 cr; 72% private, 11% state utilities, 17% central/PSU |
| Net debt | ₹117 cr, reduced by ₹56 cr during the quarter |
| Domestic revenue share | 70% of total revenue |
| Export order share | 22% of order intake |
| Low-margin legacy orders in backlog | 20–25% of backlog, expected to phase out in 3–4 quarters |
| Employee cost (FY23 baseline) | ₹350 cr in FY23; Q1 FY24 lower YoY, full year expected below FY23 |
| Addressable market size (ex-HVDC, FY24) | More than $3 billion (per an analyst's math) |
| GIS localization | ~70% |